Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Sudhir Solanki (AR), Sh. Sonu Kumar (AR) and Sh. Akhil Kumar (AR) are present on behalf of the promoter. The AR of the promoter is directed to rectify the deficiencies mentioned above at S. No. 29. Further, on the next date of hearing, the promoter is instructed to bring the landowners in person. Also, the promoter shall submit duly signed collaboration agreement reflecting the sharing arrangement for 6.0750 acres of land, signed by both the promoters and the respective landowners. Further, the promoter is directed to open bank accounts as per the section 4(2)(l)(D) of the Real Estate (Regulation and Development) Act, 2016. The matter to come upon 13.10.2025.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Sudhir Solanki (AR) and Sh. Sonu Kumar (AR) are present on behalf of the promoter and states that the remaining two bank accounts (Collection & free account) for the project have also been opened, in compliance with Section 4(2)(l)(D) of the Real Estate (Regulation and Development) Act, 2016. A reply in this regard has been submitted before the Authority today. The office to examine the same. Sh. Jeet Singh, Sh. Kapil Dayma, Sh. Sanjeev Jain, Sh. Ravinder Kumar and Sh. Hare Krishna Sinha are present on behalf of the landowners and stated that they have duly acknowledged and accepted the sharing arrangement as per the Collaboration Agreement executed between the Promoter and the Landowners.The Authorized Representative of the promoter also submits that presently, the environment clearance, approved service plans and estimates along with domestic water connection are under process and the said approvals have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit:i. The Approved Environmental Clearance and Approved Service Plans and Estimates within 3 months from the date of grant of registration.ii. Approval NOC for domestic water connection within 2 months from the date of grant of registration.Further, he undertakes to submit two Demand Drafts / Bank Guarantees amounting to Rs 25 lakhs each, as a security deposit for timely compliance with the above requirements at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approvals within the stipulated time frames, the said security amount(s) shall be liable to be forfeited by the Authority.The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit two separate Demand Drafts / Bank Guarantees, each amounting to Rs 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amounts for timely submission of the following approvals:a. Approved Environmental Clearance: within 3 months from the date of grant of registration; and b. Approved Service Plans and Estimates: within 3 months from the date of grant of registration.In the event of non-submission of any of the above approvals within the prescribed time frames, the corresponding security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Further, the promoter shall submit the approval NOC for domestic water connection within 2 months from the grant of registration certificate.Approved as proposed subject to rectification of deficiencies mentioned above. The Registration Certificate shall be issued after submission of remaining deficiencies mentioned above including correction in A-H form, Online DPI and submission of two BG/DD of Rs. 25 lakhs each for submission of approved environment clearance and approved Service plan and Estimates within the timeframe mentioned above.
Registration grantedGGM/1003/735/2025/106
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
6.075 acres
Total licensed area
121.068 acres
Licence
LICENCE NO. 211 OF 2023, 104 OF 2019, 71 OF 2014, 119 OF 2011 GRANTED BY dtcp GURUGRAM
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 114.26 Cr
Cost of land
₹ 68.21 Cr
Infrastructure and other structures
₹ 16.19 Cr
EDC, taxes, levies and other costs
₹ 29.86 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
3.182
52.4%
Construction Of Roads
1.7549
28.9%
Parks And Playgrounds
0.424
7%
Commercial
0.4671
7.7%
Nursing
0.247
4.1%
Plots 62 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
163.99
196
1,765
10
182.00
218
1,959
1
212.86
255
2,291
21
214.40
256
2,308
7
224.02
268
2,411
7
224.57
269
2,417
9
248.48
297
2,675
3
249.97
299
2,691
3
1,890.27
2,261
20,347
1
External services
Service
Provided by
Approval taken
Roads
GMDA
No
Water Supply
GMDA
No
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 59.71 lakh
As Per Project Report
Water Supply System
₹ 69.24 lakh
As Per Project Report
Storm Water Drainage
₹ 77.48 lakh
As Per Project Report
Electricity Supply System
₹ 3.25 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 1.68 Cr
As Per Project Report
Street Lighting
₹ 58.59 lakh
As Per Project Report
Security And Fire Fighting
₹ 33.84 lakh
As Per Project Report
Playgrounds And Parks
₹ 36.24 lakh
As Per Project Report
Shopping Area
₹ 1.24 Cr
As Per Project Report
Renewable Energy System
₹ 1.65 lakh
As Per Project Report
Nursing Home Site
₹ 65.7 lakh
As Per Project Report
Electric Sub Station
₹ 4.04 Cr
As Per Project Report
Rain Water Harvesting
₹ 34.26 lakh
As Per Project Report
Underground Water Tank
₹ 35.54 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Assurance Of Storm Water Drainage By GMDA
Already Been Obtained
24 Mar 2025
Assurance Of Sewerage By GMDA
Already Been Obtained
10 Mar 2025
Demarcation Plan
Already Been Obtained
License No 211 Of 2023
Already Been Obtained
18 Oct 2023
Zoning Plan
Already Been Obtained
4 Apr 2025
License No 119 Of 2011
Already Been Obtained
28 Dec 2011
License No 71 Of 2014
Already Been Obtained
29 Jul 2014
Assurance Of Electricity By DHBVN
Already Been Obtained
7 Jun 2017
Phasing Approval By Dtcp
Already Been Obtained
25 Aug 2025
Environment Clerance
Applied For But Yet To Receive
21 Jan 2025
Service Plan Estimate
Applied For But Yet To Receive
License No 104 Of 2019
Applied For But Yet To Receive
7 Sep 2019
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Anant Raj Estate?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.