Westerlies Phase-2
by Experion Developers Private Limited · Sector 108
- RERA registration
- GGM/694/426/2023/38
- Registered on
- 2 Feb 2023
- Valid till
- 11 Sep 2024
- Project ID
- RERA-GRG-795-2021
- Land area
- 44.178 acres
- Estimated cost
- ₹ 210.19 Cr
RERA registration
| Registration certificate | GGM/694/426/2023/38, dated 2 Feb 2023 |
|---|---|
| Registration valid till | 11 Sep 2024 |
| Project ID | RERA-GRG-795-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Westerlies Phase-2 |
| Promoter | Experion Developers Private Limited |
| Promoter’s registered office | Second Floor Plot No 18, Sector 32, Gurugram, Haryana |
| CIN | U70109DL2006PTC151343 |
| Site address | Sector 108 |
| Sector | Sector 108 |
| Tehsil / District | Kadipur St / Gurugram |
| Layout plan approved | 4 Aug 2020 |
| Application submitted | 12 Jan 2021 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
-
Hearing
Examination By Authority View order
Proceedings
Sh. Suneet Puri, Vice President is present on behalf of the promoter, who submits that out of total license area of 100.48 acres the part completion certificate for 46.257 acres was obtained on 31.07.2017 which was two days after coming into operation of the HARERA Rules, 2017 and hence a view was taken in the Authority to not insist on registration of this phase with a condition that the developer get registered the entire remaining area of the colony. The developer has now applied for registration of 44.178acres of land but it was noted that as per latest orders of the Hon'ble High Court in case of Appeal no 52 of 2018, the developer is required to seek registration for the entire project and hence advised to apply for the same accordingly. Matter will be heard on 26.04.2021
-
Hearing
Objection View order
Proceedings
Proceedings dated: 26.04.2021 Ms Jyoti Yadav, Coordinator Planning Branch briefed about the facts of the case. Sh. Suneet Puri, Vice President appeared on behalf of the promoter. The promoter has submitted some documents and reply to the deficiencies today itself. Office to examine the documents and reply and submit before the Authority before next date of hearing on 03.05.2021.Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member) (through video conferencing)
-
Hearing
Objection View order
Proceedings
Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 30.06.2021.
- Notice sent to the promoter By hand
-
Hearing
Objection
Proceedings
The matter is Adjourned for 01.07.2021.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 01.07.2021 Ms. Jyoti Yadav (Planning Coordinator) briefed the facts about the project. Sh. Suneet Puri (Vice President), Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter.The promoter submitted the reply on 23.06.2021 which was scrutinized, and remaining deficiencies are conveyed to the promoter. Promoter is also advised to reply to show cause as why penal proceedings for non-registration shall not be initiated. Matter was discussed at length and promoter is advised to apply the whole project as one single unit giving information of the parts for which CC has been obtained including the additional licensed area. Regarding late fee the promoter is advised to give a representation and meanwhile processing fee and registration fee be deposited. Necessary online information be submitted at https://hrera.in/app1/signup. The matter to come up on 27.07.2021.
-
Hearing
Objection View order
Proceedings
Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed the facts about the project. None present on behalf of the promoter and nor any reply on account of non-registration notice dated 11.11.2020 has been given. One last opportunity be given to the promoter failing which necessary legal penal action will be initiated. The matter to come up on17.08.2021
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 17.08.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh. Hemansh R. (DGM) are is present on behalf of the promoter. The promoter had filed an application regarding registration of plotted colony project namely “Westerlies Phase 3” situated at sector 108, Gurugram being developed by M/s Experion Developers Pvt Ltd was submitted on 05.03.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. License no. 57 of 2013 dated 11.07.2013 valid upto 10.07.2024 on an area admeasuring 100.48125 acres was issued in favor of Experion Realty Pvt Ltd, Experion Real Estate Developers Pvt Ltd, Moksha Buildtech Pvt Ltd and 8 others in collaboration with M/s Experion Developers Pvt Ltd. Total licensed area is divided into 3 phases which is as follows: 1. Phase 1 area admeasuring 46.257 acres and part completion certificate obtained on 31.07.2017. 2. Phase 2 area admeasuring 44.178 acres and part completion certificate obtained on 22.03.2018. 3. Phase 3 area admeasuring 10.4625 acres and registration certificate obtained vide RC no. 67 of 2019. The promoter has not submitted the reply of the remaining deficiencies neither submitted any representation nor reply of show cause notice as why penal proceedings for non-registration shall not be initiated. The AR of the promoter assured that necessary registration formalities shall be completed within 15 days. Authority decided to link penal proceedings already initiated against the promoter with the registration so that decision is taken jointly. The matter to come up on 07.09.2021.
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 07.09.2021Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The AR for promoter submits that the application for registration of land under phase-I measuring 46.257 acres is being prepared by filling online DPI and will be completed in next one week. Further the deficiencies conveyed for phase-II measuring 44.178 acres has been rectified and a detailed reply has been submitted in the Authority today only i.e., on 07.09.2021 and is to be examined. The matter is adjourned to 21.09.2021.
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 27.09.2021.
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 27.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has submitted the reply in the hearing itself which needs to be examined. Matter decided to come up on 11.10.2021.
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 11.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K. Malangi (CEO), Sh. Suneet Puri (VP), Sh. Vikash Aggarwal (DGM Project) and Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter. The deficiencies have still not been attended by the promoter. The promoter is directed to submit the deficit documents along with online detailed project information. The matter decided to come up on 26.10.2021.
-
Hearing
Objection View order
Proceedings
THE MATTER IS ADJOURNED FOR 27.10.2021
-
Hearing
Adjournment View order
Proceedings
Proceedings Dated: 27.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (Authorized Signatory) and Sh. Suneet Puri (Director) are present on behalf of the promoter. The promoter is directed to submit the deficit documents along with hardcopy of online detailed project information. The matter to come up on 15.11.2021.
-
Hearing
Objection View order
Proceedings
Proceedings Dated: 15.11.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. No one appeared on behalf of the promoter. Deficiencies have already been communicated. Despite various opportunity needful has not been done. A penalty of Rs. Ten lac is imposed for noncompliance of the orders of the authority. A show cause notice be issued to the promoter as why application for registration shall not be rejected for want of information. Matter to come up on 20.12.2021.
-
Hearing
Objection View order
Proceedings
Sh. Sumeet Puri (VP Projects) is present on behalf of the promoter. A show cause notice was sent to the promoter on 15.11.2021 as why application for registration of real estate project shall not be rejected under section 5(b) of Real Estate (Regulation and Development) Act, 2016 and Rules 5(2) of Haryana Real Estate (Regulation and Development) Rules, 2017. The promoter has submitted the online DPI, which was scrutinized, and corrections are conveyed to the promoter. The promoter is directed to submit the corrected copy of online DPI along with other deficit documents. Matter to come up on 27.12.2021.
-
Hearing
Objection View order
Proceedings
Matter adjourned for 17.01.2022.
-
Hearing
Adjournment View order
Proceedings
Matter adjourned for 31.01.2022.
-
Hearing
Adjournment View order
Proceedings
The promoter is directed to submit the deficit documents along with corrected online DPI and REP-I (Part A-H). Matter adjourned for 14.03.2022.
-
Hearing
Objection View order
Proceedings
None is present on behalf of the promoter. The application for registration was received on 05.03.2021 and despite conveying deficiencies/observations and hearing on multiple occasions, the promoter is not coming forward for their rectification and submission of complete information and hence one last opportunity is being granted for removal of all deficiencies failing which the application for registration shall be considered for rejection. Matter to come up on 28.03.2022
-
Hearing
Objection
Proceedings
The matter is adjourned to 31.03.2022
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 02.04.2022
-
Hearing
Adjournment View order
Proceedings
Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The AR of the promoter is directed to attend the deficiencies before the next date of hearing. The matter is adjourned to 11.04.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Proceedings dated: 11.04.2022 Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The promoter has submitted all the deficit documents except corrections in online REP-I (A-H) and corrections in online detailed project information. The promoter has obtained the part completion certificate on 22.03.2018 for the area applied for registration i.e., 44.178 acres. Therefore, the authority decided to grant registration subject to submission of corrected copy of REP-I (A-H) and DPI within one week.
- Registration granted GGM/694/426/2023/38
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 44.178 acres |
|---|---|
| Total licensed area | 116.513 acres |
| Licence | 57 of 2013 (11-07-2013) and 114 of 2019 (12.09.2019) |
| Estimated project cost | ₹ 210.19 Cr |
| Cost of land | ₹ 133.16 Cr |
| Infrastructure and other structures | ₹ 23.01 Cr |
| EDC, taxes, levies and other costs | ₹ 54.03 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 21.4766 | 48.6% |
| Construction Of Roads | 11.0618 | 25% |
| Parks And Playgrounds | 8.917 | 20.2% |
| Nursery | 0.27 | 0.6% |
| Nursery | 0.23 | 0.5% |
| Taxi | 0.5065 | 1.1% |
| Nursing | 0.24 | 0.5% |
| Nursing | 0.25 | 0.6% |
| Area | 1.226 | 2.8% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | ALREADY CONNECTED | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HUDA | Yes |
| Storm Water Drainage | HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 13.06 Cr | Submitted To Town & Country Planning |
| Water Supply System | ₹ 3.98 Cr | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 1.95 Cr | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 3.03 Cr | Submitted To Town & Country Planning |
| Street Lighting | ₹ 71.24 lakh | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 27.44 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 11 Jul 2013 |
| Zoning Plan | Already Been Obtained | 22 Nov 2021 |
| Layout Plan | Already Been Obtained | 4 Aug 2020 |
| Part Completion Certificate Of Phase 2 | Already Been Obtained | 22 Mar 2018 |
| Part Completion Certificate Of Phase 1 | Already Been Obtained | 31 Jul 2017 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.