Westerlies Phase 1
by Experion Developers Private Limited · Sector 108
- RERA registration
- GGM/593/325/2022/68
- Registered on
- 18 Jul 2022
- Valid till
- 11 Sep 2024
- Project ID
- RERA-GRG-790-2020
- Land area
- 46.257 acres
- Estimated cost
- ₹ 227.34 Cr
RERA registration
| Registration certificate | GGM/593/325/2022/68, dated 18 Jul 2022 |
|---|---|
| Registration valid till | 11 Sep 2024 |
| Project ID | RERA-GRG-790-2020 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Westerlies Phase 1 |
| Promoter | Experion Developers Private Limited |
| Promoter’s registered office | Second Floor, Plot No-18, Sector 32, Gurugram, Haryana |
| CIN | U70109DL2006PTC151343 |
| Site address | Sector 108 |
| Sector | Sector 108 |
| Tehsil / District | Kadipur St / Gurugram |
| Layout plan approved | 4 Aug 2020 |
| Application submitted | 24 Sep 2021 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
-
Hearing
Examination By Authority
Proceedings
An application received from the promoter regarding adjournment of hearing for the submission of deficit documents. The authority decided to grant one week time and matter adjourned for 21.12.2021.
-
Hearing
Objection
Proceedings
Proceedings Dated: 21.12.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Sumeet Puri (VP Projects) is present on behalf of the promoter. The AR of the promoter requested for one-week time for the submission of reply of 1st deficiency notice conveyed to the promoter on 28.10.2021. The promoter is directed to submit the online DPI along with other deficit documents. This matter will be linked to the application applied for registration of project namely Westerlies Phase 2. Matter to come up on 27.12.2021.
-
Hearing
Objection
Proceedings
Matter adjourned for 17.01.2022.
-
Hearing
Adjournment
Proceedings
Matter adjourned for 31.01.2022.
-
Hearing
Adjournment
Proceedings
The promoter is directed to submit the deficit documents along with corrected online DPI and REP-I (Part A-H). Matter adjourned for 14.03.2022.
-
Hearing
Objection
Proceedings
None is present on behalf of the promoter. The application for registration was received on 08.10.2021 and despite conveying deficiencies/observations and hearing on multiple occasions, the promoter is not coming forward for their rectification and submission of complete information and hence one last opportunity is being granted for removal of all deficiencies failing which the application for registration shall be considered for rejection. Matter to come up on 28.03.2022
-
Hearing
Objection
Proceedings
The matter is adjourned to 31.03.2022
-
Hearing
Adjournment
Proceedings
The matter is adjourned to 02.04.2022
-
Hearing
Adjournment
Proceedings
Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The AR of the promoter is directed to attend the deficiencies before the next date of hearing. The matter is adjourned to 11.04.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 11.04.2022 Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are present on behalf of the promoter. On the request of the promoter, 2 weeks’ time is granted to the promoter for submission of deficit documents. Matter to come up on 25.04.2022
-
Hearing
Objection
Proceedings
Ms. Jyoti Yadav, Planning Coordinator briefed about the facts of the project. Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are present on behalf of the promoter. In the last hearing on the request of the promoter, 2 weeks’ time was granted to the promoter for submission of deficit documents. As on today, the promoter has submitted reply to the notice of deficiencies. The office to examine and put up before the Authority on the next date of hearing on 02.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 02.05.2022 Sh. Utkarsh Suyog (AM-Projects) is present on behalf of the promoter. The promoter had submitted the reply on 25.04.2022 which was scrutinized and the deficiencies which are still needs to be rectified are conveyed to the promoter. Regarding late fee, matter is referred to Mrs. Geeta Rathee Singh, LO, HARERA, GGM for legal opinion with regarding to charging of late fee as part completion for 46.257 acres was obtained on 31.07.2017. The report from the LO needs to be submitted before the next date of hearing. On the request of the promoter, 2-week time is granted for submission of deficit documents and submission of reply regarding late fee. Matter to come up on 16.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 16.05.2022 Sh. Utkarsh Suyog (AM-Projects) is present on behalf of the promoter. The promoter submitted the reply on 13.05.2022 which was scrutinized, and remaining deficiencies have been conveyed to the promoter. In the last hearing, this matter was referred to Mrs. Geeta Rathee Singh, LO, HARERA, GGM for legal opinion with regarding to charging of late fee as part completion for 46.257 acres was obtained on 31.07.2017. The report from the LO is awaited. In the meanwhile, the promoter is directed to submit the reply of deficit documents before next date of hearing. Matter to come up on 30.05.2022.
-
Hearing
Objection
Proceedings
Proceedings dated: 30.05.2022 Sh. Utkarsh Suyog (AM-Projects) is present on behalf of the promoter. The promoter has submitted the reply on 27.05.2022 which was scrutinized and found that all the deficiencies have been fulfilled by the promoter except deficit fee of Rs. 59,63,901/-, online corrections in REP-I (Part A-H) and minor observations and corrections in detailed project information. The matter to come up on 06.06.2022 for considering the report of the Sr. Legal Officer.
-
Hearing
Objection
Proceedings
Proceedings dated: 06.06.2022 Sh. Utkarsh Suyog (AM-Projects) is present on behalf of the promoter. The authority directs the promoter to rectify the defects and submit the corrected online DPI alongwith the corrected (A-H). Matter to come up on 13.06.2022.
-
Hearing
Objection
Proceedings
The matter is adjourned for 11.07.2022
-
Hearing
Adjournment
Proceedings
Proceedings dated 11.07.2022.Sh. J.S. Sindhu briefed about the facts of the case.None is present on behalf of the promoter.The matter is adjourned and fixed for 18.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Proceedings dated: 18.07.2022 Sh. J. S Sindhu, Executive Engineer (Monitoring) briefed about the facts of the project. Sh. Utkarsh Suyog (AM-Projects) is present on behalf of the promoter. The AR submits that all the compliances have been duly made and the late fees has also been deposited and the DPI is also ready and being submitted after binding. Penalty imposed Rs.10 Lakh be also recovered before issuance of registration certificate. The Authority decides to grant registration. Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
- Registration granted GGM/593/325/2022/68
- Certificate uploaded RC uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 46.257 acres |
|---|---|
| Total licensed area | 116.513 acres |
| Licence | 57 of 2013 (11-07-2013), 114 of 2019 (12-09-2019) |
| Estimated project cost | ₹ 227.34 Cr |
| Cost of land | ₹ 139.43 Cr |
| Infrastructure and other structures | ₹ 24.09 Cr |
| EDC, taxes, levies and other costs | ₹ 63.83 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 23.5282 | 50.9% |
| Construction Of Roads | 14.042 | 30.4% |
| Parks And Playgrounds | 2.64 | 5.7% |
| Electricity Sub-Station | 0.412 | 0.9% |
| Sewage And Solid Waste Treatment Facility | 0.7243 | 1.6% |
| Any Other | 4.9105 | 10.6% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | ALREADY CONNECTED | Yes |
| Water Supply | G.M.D.A/HUDA | Yes |
| Electricity | DHBVNL | Yes |
| Sewage Disposal | GMDA/HUDA | Yes |
| Storm Water Drainage | GMDA/HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 13.67 Cr | Submitted To Town & Country Planning |
| Water Supply System | ₹ 4.17 Cr | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 2.04 Cr | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 3.17 Cr | Submitted To Town & Country Planning |
| Street Lighting | ₹ 74.6 lakh | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 28.74 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 11 Jul 2013 |
| Zoning Plan | Already Been Obtained | 22 Nov 2021 |
| Layout Plan | Already Been Obtained | 4 Aug 2020 |
| Part Completion Certificate Phase-1 | Already Been Obtained | 31 Jul 2017 |
| Part Completion Certificate Phase-2 | Already Been Obtained | 22 Mar 2018 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Westerlies Phase 1?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.