Registration validHRERA GurugramOC / CC on record

Tulip Yellow

by Tulip Infratech Pvt. Ltd. · Sector 69, Village Badshahpur

RERA registration
GGM/376/108/2019/70
Registered on
14 Nov 2019
Valid till
31 Dec 2027
Project ID
RERA-GRG-292-2019
Land area
7.458 acres
Apartments
744 in 6 towers
Completion (as filed)
31 Dec 2027
Estimated cost
₹ 379.16 Cr

RERA registration

Registration certificateGGM/376/108/2019/70, dated 14 Nov 2019
Registration valid till31 Dec 2027
Project IDRERA-GRG-292-2019
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameTulip Yellow
PromoterTulip Infratech Pvt. Ltd.
Promoter’s registered office76 G, Sector 18, Gurugram, Haryana
CINU70101DL2005PTC144086
Site addressSector 69, Village Badshahpur
SectorSector 69
Tehsil / DistrictGurgaon / Gurugram
Construction start (as filed)1 Oct 2019
Completion (as filed)31 Dec 2027
Application submitted31 Jul 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyDeficiency to be conveyed dated 04.09.2019
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Hearing Examination By Authority
    Proceedings

    Next hearing date 13.09.2019 for remove deficiency.

  1. Hearing Objection
    Proceedings

    Next date for hearing to remove deficiencies is 18-09-2019

  2. Hearing Adjournment
    Proceedings

    Next date for hearing to remove deficiencies is 01-10-2019

  3. Hearing Adjournment View order
    Proceedings

    Next date for hearing to remove deficiencies is 17-10-2019

  1. Hearing Adjournment View order
    Proceedings

    Next date for hearing to remove deficiencies is 22-10-2019. (Ashish)

  2. Hearing Adjournment View order
    Proceedings

    Next date for hearing to remove deficiencies is 04-11-2019. (Ashish)

  3. Hearing Adjournment View order
    Proceedings

    Next date for hearing to remove deficiencies is 06-11-2019. (Ashish)

  1. Hearing Adjournment View order
    Proceedings

    Next date for hearing to remove deficiencies is 18-11-2019. (Ashish)

  2. Registration granted GGM/376/108/2019/70
  3. Certificate uploaded RC Approved
  1. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Approved

  2. Hearing Objection
  3. Registration valid till

Land, licence & cost

Land area of the project7.458 acres
Total licensed area7.458 acres
Licence16 of 2019 dated 09/02/2019
FAR permissible / proposed250 / 249.921
Estimated project cost₹ 379.16 Cr
Cost of land₹ 15.64 Cr
Cost of construction₹ 189.73 Cr
Infrastructure and other structures₹ 31.73 Cr
EDC, taxes, levies and other costs₹ 142.06 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments3,518.75811.7%
Construction Of Roads6,37021.1%
Pavements8,403.64927.8%
Parks And Playgrounds3,820.33812.7%
Green Belts2,367.0917.8%
Vehicle Parkings2,162.57.2%
Electricity Sub-Station2000.7%
Club House748.4522.5%
Area To Be Left For Transferring To The Government For Community Services463.9641.5%
Any Other2,127.8697%

Apartments 744 units · 6 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings96.091,034624
Apartment/Shops/Other Buildings170.181,8326
Apartment/Shops/Other Buildings197.882,1302
Apartment/Shops/Other Buildings18.79202112

Areas are as filed with HRERA.

External services

ServiceProvided byApproval taken
RoadsDGTCPYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalDGTCPYes
Storm Water DrainageDGTCPYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.07 CrSubmitted To Town & Country Planning
Water Supply System₹ 2.46 CrSubmitted To Town & Country Planning
Storm Water Drainage₹ 77.5 lakhSubmitted To Town & Country Planning
Sewage Treatment & Garbage Disposal₹ 1.46 CrSubmitted To Town & Country Planning
Street Lighting₹ 28.61 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 6.16 lakhSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
Site PlanAlready Been Obtained18 Apr 2019
Demarcation PlanAlready Been Obtained1 Feb 2019
Zoning PlanAlready Been Obtained9 Feb 2019
Building PlanAlready Been Obtained18 Apr 2019
Elevation SectionAlready Been Obtained18 Apr 2019

Specifications (as filed)

Flooring Details Of Various Parts Of HouseAnti Skid Tiles Ceramic Tiles/ Vitrified Tiles
Wall Finishing DetailsOil Bound Distemper
Kitchen DetailsMarble/Granite Counter With SS Sink
Bathroom FittingsWhite Sanitary, Cp Fitting And Mirror
Wood Work EtcNot Applicable
Doors And Windos FramesUpvc/ Hardwood
Glass WorkNot Applicable
Electric FittingsSwitches Only (No Lights & Fixtures)
Conducting And Wiring DetailsType Of Electrical Wires Used: Copper Wires
Cupboard DetailsNot Applicable
Water StorageUnder Ground/Over Head Tank
Lift Details3 Nos, CAPACITY10 & 13 Person, Kone Or Equivalent
External GlazingsNot Applicable
Windows/GlazingsUpvc Windows Or Equivalent
DoorsFlush Door
Main DoorsFlush Door
Internal DoorsFlush Door
Air ConditioningNot Applicable
Electrical FittingsAs Above Sr. NO.8
Cng Pipe LineNot Applicable
Provision Of Wifi And Broadband FacilityNot Applicable
External Finishing/Colour SchemePaint Finishes
Internal FinishingNot Applicable

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Tulip Yellow?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.