The Residences Three Sixty
by Capital Heights Private Limited · Revenue Estate Of Village Palra Sector 70A Sub Tehsil Badshahpur District Gurugram Haryana India
- RERA registration
- GGM/890/622/2024/117
- Registered on
- 2 Dec 2024
- Valid till
- 30 Dec 2026
- Project ID
- RERA-GRG-1396-2023
- Land area
- 1.26 acres
- Apartments
- 110 in 1 tower
- Completion (as filed)
- 31 Dec 2025
- Estimated cost
- ₹ 60.22 Cr
RERA registration
| Registration certificate | GGM/890/622/2024/117, dated 2 Dec 2024 |
|---|---|
| Registration valid till | 30 Dec 2026 |
| Project ID | RERA-GRG-1396-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | The Residences Three Sixty |
| Promoter | Capital Heights Private Limited |
| Promoter’s registered office | N8 Ground Floor Panchsheel Park New Delhi 110017 |
| CIN | U70101DL2011PTC217786 |
| Site address | Revenue Estate Of Village Palra Sector 70A Sub Tehsil Badshahpur District Gurugram Haryana India |
| Sector | Sector 70A |
| Tehsil / District | Badshahpur St / Gurugram |
| Layout plan approved | 25 Jan 2019 |
| Building plans approved | 25 Jan 2019 |
| Construction start (as filed) | 1 Jul 2022 |
| Completion (as filed) | 31 Dec 2025 |
| Application submitted | 19 Jun 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter By Hand
-
Hearing
Examination By Authority View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company against the deficiencies raised by the authority till date. In view of the same the matter is adjourned, and the next date of hearing will be conveyed after the submission of reply of deficiencies already conveyed through notice.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Pramod (AR) and Ms. Hima Kathuria (AR) are present on behalf of the promoter. The AR of the promoter requests for four week’s time for submission of deficit fee alongwith other deficit documents. However, is noticed that the total area of BIP/COD in favour of the applicant promoter is 2.79 acres and the promoter had applied only for the area i.e., 1.26 acres. The AR of the promoter stated that they had obtained the OC for the balance area in 2018 only. Therefore, the Authority directed the promoter to apply for the whole area as per BIP/COD i.e., 2.79 acres and to submit the requisite fee alongwith the other deficiencies as per whole area i.e., 2.79 acres. The matter to come up on 15.01.2024 for further proceedings.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Sh. M.L. Sardana, Accountant briefed about the facts of the case. Sh. Pramod Kumar (AR) and Ms. Hima Kashyap (AR) are present on behalf of the promoter. Further in compliance to earlier proceedings, the promoter has deposited the requisite fee in respect of applied area only while the promoter is required to make application along with fee for the area 2.79 acres as per BIP permission along with other deficit documents. One more opportunity is being given to the applicant promoter to comply and to submit the deficit fee and documents within four weeks. Further it is observed that the above project is part of a licensed colony measuring 27.7163 acres granted to M/s Haamid Real Estate Pvt. Ltd. and office to examine and put up the details of area already registered under above licensed colony and to initiate necessary action if any area remains either unregistered or unapplied for registration. The matter to come up on 19.02.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Pramod Kumar and Sh. Bhim Singh are present on behalf of the promoter. The AR of the promoter states that reply to the deficiencies was submitted on 16.02.2024 and only a few deficiencies are left to be rectified. He further stated that the application has been revised for the complete area of 2.79 Acres. The rest of the deficiencies shall be removed within the next two weeks. The matter to come up on 04.03.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive briefed about the facts of the case. None is present on behalf of the promoter. One more and last opportunity is being granted to the applicant promoter to rectify the above deficiencies and to attend personal hearing failing which the matter shall be decided on basis of fact available on file. The matter to come up on 08.04.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Pramod Kumar (AR) and Sh. Bhim (AR) are present on behalf of the promoter and states that reply to the deficiency notice has been submitted today. The same be examined by office. The matter to come up on 29.04.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the case. None of the director/CEO/Project-Incharge is present on behalf of the promoter except Sh. Pramod Kumar, a clerk carrying the Board Resolution who has no idea about the project. The director/CEO/Project-Incharge of the promoter company is directed to be present on the next date of hearing. The matter to come up on 20.05.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the case. S/Shri Hima Kashyap, BB Sahu and Pramod Kumar are present on behalf of the promoter and state that they had applied for renewal of license. One more opportunity is being given to the promoter to rectify the deficiencies. The matter to come up on 10.06.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Nikita Mittal, Planning Executive and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the case. Sh. Pramod Kumar (AR) and Sh. B.B. Sahu (AR) are present on behalf of the promoter. The AR of the promoter seeks four weeks’ time to submit renewed license along with other deficit documents. The same is allowed. The matter to come up on 15.07.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 09.09.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 04.11.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 25.11.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 02.12.2024.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Pramod Kumar (AR), Sh. B.B. Sahu (AR) and Ms. Hima Kashyap (AR) are present on behalf of the promoter. Approved as proposed.
- Registration granted GGM/890/622/2024/117
- Registration valid till
Land, licence & cost
| Land area of the project | 1.26 acres |
|---|---|
| Total licensed area | 27.716 acres |
| Licence | 16 OF 2009 AND 73 OF 2013 |
| FAR permissible / proposed | 175.38 / 175.38 |
| Estimated project cost | ₹ 60.22 Cr |
| Cost of land | ₹ 17.35 Cr |
| Cost of construction | ₹ 26.82 Cr |
| Infrastructure and other structures | ₹ 4.63 Cr |
| EDC, taxes, levies and other costs | ₹ 11.42 Cr |
Apartments 110 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 82.77 | 891 | 110 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHVBN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 54.86 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 1.09 Cr | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 23.83 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 2 Cr | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 58.82 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 8.16 lakh | Submitted To Town & Country Planning |
| Any Other | ₹ 8.28 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Airport Heights Clearance | Already Been Obtained | 24 May 2019 |
| Environment Clearance | Already Been Obtained | 15 Sep 2020 |
| Zoning Plan | Already Been Obtained | 11 Nov 2013 |
| Forest Noc | Already Been Obtained | 3 Oct 2013 |
| Fire Scheme | Already Been Obtained | 1 Aug 2015 |
| License 16 Of 2009 | Already Been Obtained | 24 Sep 2019 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tile Flooring Of Kajaria Or Equivalent. |
|---|---|
| Wall Finishing Details | Pop Punning With Emulsion Paint. |
| Kitchen Details | Combination Of Tiles Up To 2' - O" Above The Counter And Emulsion In The Balance Areas. |
| Bathroom Fittings | Cp Fittings |
| Wood Work Etc | Flush Door With Laminate Of Merino & Hardwarefitting Of Ipsa/ Ozone Or Equivalent. |
| Doors And Windos Frames | Flush Door With Laminate Of Merino & Hardwarefitting Of Ipsa/Ozone Or Equivalent. , Upvc Windowframes With Clear Toughened Glass. |
| Glass Work | Clear Toughened Glass. |
| Electric Fittings | Havells |
| Conducting And Wiring Details | Polycab/ Havells |
| Cupboard Details | Commercial Ply + Laminate |
| Water Storage | Rcc Tanks |
| Lift Details | Johnson |
| External Glazings | Upvc Window Frames With Clear Toughened Glass. |
| Windows/Glazings | Upvc Window Frames With Clear Toughened Glass. |
| Doors | Flush Door With Laminate Of Merino |
| Main Doors | Flush Door With Laminate Of Merino |
| Internal Doors | Flush Door With Laminate Of Merino |
| Air Conditioning | Split And Window |
| Electrical Fittings | Polycab/ Havells |
| Cng Pipe Line | Ms Pipeing |
| External Finishing/Colour Scheme | Texture Paint |
| Internal Finishing | Emulsion Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about The Residences Three Sixty?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.