Residences 360
by Capital Heights Private Limited · Village- Parla Sector 70-A Gurugram
- RERA registration
- Applied, not granted yet
- Applied on
- 1 Jul 2022
- Application status
- Rejected
- Project ID
- RERA-GRG-1093-2022
- Land area
- 1.26 acres
- Apartments
- 110 in 1 tower
- Completion (as filed)
- 31 Dec 2025
- Estimated cost
- ₹ 60.22 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-1093-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Residences 360 |
| Promoter | Capital Heights Private Limited |
| Promoter’s registered office | N-8, Ground Floor Panchsheel Park New Delhi 110017 |
| CIN | U70101DL2011PTC217786 |
| Site address | Village- Parla Sector 70-A Gurugram |
| Sector | Sector 70 |
| Tehsil / District | Badshahpur St / Gurugram |
| Layout plan approved | 27 Jan 2017 |
| Building plans approved | 1 May 2012 |
| Construction start (as filed) | 1 Jul 2022 |
| Completion (as filed) | 31 Dec 2025 |
| Application submitted | 1 Jul 2022 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st Deficiencies Notice
-
Hearing
Examination By Authority View order
Proceedings
Proceedings dated: 29.08.2022 Ms. Geeta Rathee Singh, Sr. L.O. and Sh. J.S Sindhu, Executive Engineer Monitoring briefed about the facts of the case. Sh. B.B. Sahu (Manager), Ms. Hema Kashyap (Manager) and Sh. Pramod Sharma (Asstt. Manager) are present on behalf of the promoter. It is noticed that the license was transferred in the name of M/s Haamid Real Estate Pvt. Ltd. vide DTCP order dated 25.11.2011. However, the instant application has been made by M/s Capital Heights Pvt. Ltd. who is neither a license holder nor a collaborator or BIP holder duly recognized by DTCP. The AR submits that the applicant has already applied to DTCP for grant of BIP permission which is under consideration of DTCP. Keeping in view a large number of deficiencies in the documents required to be attached with the application as mentioned above and the lack of legal capacity to develop the project the Authority hereby decides to issue show cause notice to the promoter under section 5 of Act of 2016 and the rules made thereunder as why this application for grant of registration shall not be rejected and if the promoter has to say anything in the matter he may appear in person or through AR on 03.10.2022 at 3.00 PM. The matter to come up on 03.10.2022. Member(Vijay Kumar Goyal), Chairman(Dr. K.K. Khandelwal)
-
Hearing
Rejected View order
Proceedings
Proceedings dated: 03.10.2022 : Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Pramod Kumar Sharma and Ms. Hima Kashyap are present on behalf of the promoter. The applicant promoter was given time for one months for rectifying the deficiencies particularly the documents pertaining to legal capacity to apply as a promoter as presently the applicant promoter is neither license holder nor collaborator nor BIP holder. The applicant promoter has been given opportunity of hearing as per requirement of section 5 of the Act and Rule 5(2) of the Haryana Rules, 2017. For the reasons recorded above the Authority decides to reject the application and forfeit the processing fee. Rest of the documents will remain intact, and the registration fee paid will be adjusted as and when BIP permission is obtained and the application for registration is filed. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
Land, licence & cost
| Land area of the project | 1.26 acres |
|---|---|
| Total licensed area | 27.72 acres |
| Licence | 16 of 2009(28-05-2024), 73 of 2013(29-07-2024) RERA Registration is being applied for Tower No. CR01 (1.26 acres) under the provision of the said Licences |
| FAR permissible / proposed | 175.38 / 175.38 |
| Estimated project cost | ₹ 60.22 Cr |
| Cost of land | ₹ 17.35 Cr |
| Cost of construction | ₹ 26.82 Cr |
| Infrastructure and other structures | ₹ 4.63 Cr |
| EDC, taxes, levies and other costs | ₹ 11.42 Cr |
Apartments 110 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 82.77 | 891 | 110 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 54.86 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 1.09 Cr | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 23.83 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 2 Cr | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 58.82 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 8.16 lakh | Submitted To Town & Country Planning |
| Any Other | ₹ 8.28 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Airport Height Clearance | Already Been Obtained | 24 May 2019 |
| Environment Clearance | Already Been Obtained | 15 Sep 2020 |
| Zoning Plan | Already Been Obtained | 11 Nov 2013 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tile Flooring Of Kajaria Or Equivalent. |
|---|---|
| Wall Finishing Details | Pop Punning With Emulsion Paint. |
| Kitchen Details | Combination Of Tiles Up To 2' - O" Above The Counter And Emulsion In The Balance Areas. |
| Bathroom Fittings | Cp Fittings |
| Wood Work Etc | Flush Door With Laminate Of Merino & Hardware Fitting Of Ipsa/ Ozone Or Equivalent. |
| Doors And Windos Frames | Flush Door With Laminate Of Merino & Hardware Fitting Of Ipsa/Ozone Or Equivalent. , Upvc Window Frames With Clear Toughened Glass. |
| Glass Work | Clear Toughened Glass. |
| Electric Fittings | Havells |
| Conducting And Wiring Details | Polycab/ Havells |
| Cupboard Details | Commercial Ply + Laminate |
| Water Storage | Rcc Tanks |
| Lift Details | Johnson |
| External Glazings | Upvc Window Frames With Clear Toughened Glass. |
| Windows/Glazings | Upvc Window Frames With Clear Toughened Glass. |
| Doors | Flush Door With Laminate Of Merino |
| Main Doors | Flush Door With Laminate Of Merino |
| Internal Doors | Flush Door With Laminate Of Merino |
| Air Conditioning | Split And Window |
| Electrical Fittings | Polycab/ Havells |
| Cng Pipe Line | Ms Pipeing |
| External Finishing/Colour Scheme | Texture Paint |
| Internal Finishing | Emulsion Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Residences 360?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.