Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Deepak Sharma (Head Corporate Affairs), Sh. Akash Gupta (Manager) and Sh. Pratik Gautam (Manager) are present on behalf of the promoter and state that an affidavit through Director of the company has been submitted to the Authority on 10.01.2025 stating that no RERA application, advertisement, marketing, booking, sale and offer to sale in any manner based on earlier approved building plan and phasing plan of the project has been made. A public notice inviting objections with respect to the claim of the promoter regarding no advertisement, marketing, booking, sale and offer to sale in any manner based on earlier approved building plan and phasing plan of the project be issued in three leading newspaper (Two English and One Hindi). The AR of the promoter is directed to rectify the remaining deficiencies before the next date of hearing. The matter to come up on 27.01.2025.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Deepak Sharma (Head Corporate Affairs), Sh. Akash Gupta (Manager) and Sh. Pratik Gautam (Manager) are present on behalf of the promoter. Approved as proposed subject to submission of DD/BG of Rs. 25 lakhs each for submission of Environmental Clearance, Fire Scheme approval and Service Plans and Estimates approval within a period of four months and correction in form REP-I (Part A to H) and DPI. The RC shall be issued after compliance of the above.
Registration grantedGGM/908/640/2025/11
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
1.077 acres
Total licensed area
11.09 acres
Licence
License No. 199 of 2023 dated 05.10.2023 and 15 of 2024 dated 30.01.2024
FAR permissible / proposed
3.62 / 3.62
Estimated project cost
₹ 665.2 Cr
Cost of land
₹ 292.3 Cr
Cost of construction
₹ 251.28 Cr
Infrastructure and other structures
₹ 43.5 Cr
EDC, taxes, levies and other costs
₹ 78.12 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
0.1912
17.8%
Construction Of Roads
0.5166
48%
Parks And Playgrounds
0.2345
21.8%
Electricity Sub-Station
0.0529
4.9%
Sewage And Solid Waste Treatment Facility
0.0433
4%
Underground
0.0313
2.9%
Rain
0.007
0.7%
Apartments 174 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
134.35
1,446
168
Apartment/Shops/Other Buildings
118.14
1,272
6
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
AP-1687756478349
Yes
Water Supply
MEMO NO. EE(PROJ)/GMDA/2024/41
Yes
Electricity
MEMO NO. CH-40/DRG-PLC
Yes
Sewage Disposal
EIC II-203009(01)/6/2023-O/O SE-INFRA II -I/8804/2024
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about The Palatial Phase 2 (Tower-D)?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.