2ND Floor, C-9/15, Sector- 7, Rohini New Delhi- 110085
CIN
U70101DL2005PTC144228
Site address
Village- Nizampur, Sector 40
Sector
Sector 40
Tehsil / District
Panipat / Panipat
Layout plan approved
1 Mar 2019
Construction start (as filed)
1 Jul 2019
Completion (as filed)
30 Jun 2021
Application submitted
17 Jun 2019
Authority, hearings & orders
Current statusExtension Certificate Uploaded
Initial scrutinyListed for first hearing.
Next hearing24 Jun 2019
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Approved for Registration.
Next hearing
Registration valid till
Land, licence & cost
Land area of the project
9.481 acres
Total licensed area
9.481 acres
Licence
35 OF 2019
FAR permissible / proposed
2 / 2
Estimated project cost
₹ 42.41 Cr
Cost of land
₹ 6.02 Cr
Infrastructure and other structures
₹ 24.05 Cr
EDC, taxes, levies and other costs
₹ 12.34 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
22,875.206
59.6%
Construction Of Roads
5,000
13%
Pavements
2,543
6.6%
Parks And Playgrounds
3,168.69
8.3%
Electricity Sub-Station
30
0.1%
Sewage And Solid Waste Treatment Facility
148.574
0.4%
Area To Be Left For Transferring To The Government For Community Services
3,838.24
10%
Any Other
767.69
2%
Plots 170 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
102.00
122
1,098
2
106.14
127
1,142
2
109.68
131
1,181
46
112.64
135
1,212
1
112.70
135
1,213
1
113.10
135
1,217
1
113.22
135
1,219
1
113.85
136
1,225
1
119.43
143
1,285
1
123.12
147
1,325
1
127.56
153
1,373
1
128.01
153
1,378
1
133.10
159
1,433
1
134.44
161
1,447
4
137.62
165
1,481
1
137.63
165
1,481
1
138.22
165
1,488
1
138.84
166
1,494
1
139.12
166
1,498
1
139.14
166
1,498
1
139.19
166
1,498
1
140.75
168
1,515
1
141.47
169
1,523
1
141.52
169
1,523
1
142.30
170
1,532
1
143.86
172
1,548
1
143.99
172
1,550
7
145.77
174
1,569
4
145.84
174
1,570
1
146.31
175
1,575
1
147.12
176
1,584
1
147.81
177
1,591
1
148.24
177
1,596
1
148.29
177
1,596
1
148.69
178
1,601
1
148.73
178
1,601
1
148.84
178
1,602
1
148.94
178
1,603
1
148.97
178
1,603
1
149.04
178
1,604
1
149.14
178
1,605
2
149.25
178
1,606
1
149.26
179
1,607
1
149.30
179
1,607
1
149.35
179
1,608
2
149.37
179
1,608
1
149.45
179
1,609
1
149.46
179
1,609
1
149.46
179
1,609
1
149.57
179
1,610
1
149.62
179
1,611
1
149.66
179
1,611
4
149.68
179
1,611
1
149.78
179
1,612
1
149.79
179
1,612
1
149.83
179
1,613
45
149.89
179
1,613
1
149.94
179
1,614
5
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
No
ELECTRICITY
No
Sewage Disposal
No
STORM WATER DRAINAGE
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
19500000
As Per Project Report
2
WATER SUPPLY SYSTEM
9500000
AS PER PROJECT REPORT
3
Storm Water Drainage
6000000
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
6000000
As Per Project Report
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
5500000
AS PER PROJECT REPORT
6
Street Lighting
1500000
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
1100000
As Per Project Report
8
PLAYGROUNDS AND PARKS
1200000
AS PER PROJECT REPORT
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
1700000
AS PER PROJECT REPORT
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
15
Earth Filling
34000000
AS PER PROJECT REPORT
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
01-03-2019
(date)
6. Date of approval of Building Plans
NA
(date)
7. New projects:
i) Likely date of starting the construction work
01-07-2019
ii) Likely date of completing the project
30-06-2021
iii) Sizes of the plots to be offered in the project
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
102.000
2
2
106.140
2
3
109.678
46
4
112.640
1
5
112.704
1
6
113.097
1
7
113.217
1
8
113.852
1
9
119.425
1
10
123.122
1
11
127.563
1
12
128.014
1
13
133.102
1
14
134.444
4
15
137.624
1
16
137.626
1
17
138.222
1
18
138.839
1
19
139.123
1
20
139.142
1
21
139.189
1
22
140.746
1
23
141.469
1
24
141.520
1
25
142.303
1
26
143.860
1
27
143.990
7
28
145.771
4
29
145.843
1
30
146.310
1
31
147.123
1
32
147.807
1
33
148.239
1
34
148.289
1
35
148.692
1
36
148.728
1
37
148.836
1
38
148.944
1
39
148.965
1
40
149.037
1
41
149.138
2
42
149.246
1
43
149.260
1
44
149.303
1
45
149.354
2
46
149.368
1
47
149.447
1
48
149.455
1
49
149.462
1
50
149.570
1
51
149.623
1
52
149.656
4
53
149.678
1
54
149.778
1
55
149.792
1
56
149.834
45
57
149.886
1
58
149.944
5
Total
170
iv. Type of apartments to be constructed in the project:
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
25.5
0
39
39
Water Supply System
17
0
0
17
Sewerage treatment & garbage disposal
10
0
0
11
Electricity Supply System
0
0
0
0
Storm Water Drainage
11
0
0
12
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
EARTH FILLING
40
0
150
150
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
15
25.5
22
15
Water Supply System
16
14.5
14.5
16
Sewerage treatment & garbage disposal
8
10
8
8
Electricity Supply System
10
16
12
12
Storm Water Drainage
8.5
10
10
8.5
Parks and Playgrounds
4
0
0
5
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
SOLAR ENERGY SYSTEM
4
4
STREET LIGHTING
3
4
3
3
Security And Fire Fighting
3
5
Solar Energy Systems
3
4
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
14
0
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
10
0
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
3
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Security And Fire Fighting
3
SOLAR ENERGY SYSTEM
2
STREET LIGHTING
2
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
BANK OF INDIA, MAIN BRANCH, PANIPAT
Bank Account number
675320110000043
IFSC code
BKID0006753
MICR code
132013003
Branch code
006753
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
Anil Wadhwa
MUNISH BAJAJ
VIVEK NARANG
Vikas Narang
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
CERTIFICATE ATTACHED
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
Yes
ii. Demarcation Plan
No
iii. Zoning Plan
No
iv. Building Plan
No
Site Plan
No
Floor Plan
No
Apartment Plans
No
Elevation Section
No
Detail of Permissible FAR
No
Detail of covered area achieved FAR
No
2. Annex copies of the following in Folder E:
I. Roads And Pavement Plan
Yes
II. ELECTRICITY SUPPLY PLAN
Yes
III. WATER SUPPLY PLAN
Yes
IV. Sewerage And Garbage Disposal Plan
Yes
V. STROM WATER DRAINAGE
Yes
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
No
Vii. Street Lighting Plan
Yes
VIII. PARKING PLAN
No
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. DEMARCATION PLAN
Applied For But Yet To Receive
08-05-2019
II. ZONING PLAN
Yet To File For Approval
NA
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
Form Rep-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
Annexure Attached
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - G
Projects launched by the promoter in last five years: (No Projects)
I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - H
Specification Of Construction
Specification of apartments and other buildings including the following:
1
Flooring Details Of Various Parts Of House
NA
2
Wall Finishing Details
NA
3
Kitchen Details
NA
4
Bathroom Fittings
NA
5
Wood Work Etc
NA
6
Doors And Windos Frames
NA
7
Glass Work
NA
8
Electric Fittings
NA
9
Conducting And Wiring Details
NA
10
Cupboard Details
NA
11
Water Storage
NA
12
Lift Details
NA
13
External Glazings
NA
13.1
Windows/Glazings
NA
14
Doors
NA
14.1
Main Doors
NA
14.2
Internal Doors
NA
15
Air Conditioning
NA
16
Electrical Fittings
NA
17
Cng Pipe Line
NA
18
Provision Of Wifi And Broadband Facility
NA
19
External Finishing/Colour Scheme
NA
20
Internal Finishing
NA
SPECIFICATION UNIT WISE
1 . Living/Dining/Foyer/Family Lounge
1 . 1
FLOOR
Na
1 . 2
WALLS
Na
1 . 3
CEILING
Na
2 . MASTER BEDROOM/DRESSROOM
2 . 1
Floor
NA
2 . 2
Walls
NA
2 . 3
Ceiling
NA
2 . 4
Modular Wardrobes
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . Bed Rooms
4 . 1
FLOOR
Na
4 . 2
WALLS
Na
4 . 3
CEILING
Na
4 . 4
WARDROBES
Na
5 . TOILET
5 . 1
Floor
NA
5 . 2
Walls
NA
5 . 3
Ceiling
NA
5 . 4
Counters
NA
5 . 5
Sanitary Ware/Cp Fittings
NA
5 . 6
Fixtures
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . Utility Rooms/Utility Balcony/Toilet
7 . 1
FLOOR
Na
7 . 2
WALLS & CEILING
Na
7 . 3
TOILET
Na
7 . 4
BALCONY
Na
8 . SIT-OUTS
8 . 1
Floor
NA
8 . 2
Walls & Ceiling
NA
8 . 3
Railings
NA
8 . 4
Fixtures
NA
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
List of Uploaded Documents
Sr. No.
Document Description
Date of Document Upload
View Document
1
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.
04-05-2019
View Document
2
STREET LIGHTING PLAN
02-05-2019
View Document
3
Road And Pavement Plan
02-05-2019
View Document
4
ELECTRICITY SUPPLY PLAN
02-05-2019
View Document
5
SEWAGE & GARBAGE DISPOSAL PLAN
02-05-2019
View Document
6
Storm Water Drainage
02-05-2019
View Document
7
WATER SUPPLY PLAN
02-05-2019
View Document
8
COPY OF LICENSE ALONG WITH SCHEDULE OF LAND
14-06-2019
View Document
9
In Case Of Plotted Colony, The Latest Layout Plan
14-06-2019
View Document
10
DRAFT ALLOTMENT LETTER
14-06-2019
View Document
11
FORM 3 CA CERTIFICATE
14-06-2019
View Document
12
Receiving From Demarcation Application
14-06-2019
View Document
13
GIST OF IMPORTANT PROVISIONS OF DRAFT AGREEMENT
17-06-2019
View Document
14
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT
17-06-2019
View Document
15
Cash Flow Statement Of The Proposed Project
17-06-2019
View Document
16
DRAFT AGREEMENT FOR SALE
17-06-2019
View Document
17
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN
17-06-2019
View Document
18
Non Default Certificate From A Chartered Accountant
17-06-2019
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Documents Uploaded After Registration
Sr. No.
Document Description
Date of Document Upload
View Document
1
General extension of registration.
29-04-2022
View Document
2
First extension of registration
12-08-2022
View Document
3
EXTENSION UPLOAD
23-11-2023
View Document
4
Fifth Extension Uploaded.
28-05-2025
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 195,000 Cr
As Per Project Report
Water Supply System
₹ 95,000 Cr
As Per Project Report
Storm Water Drainage
₹ 60,000 Cr
As Per Project Report
Electricity Supply System
₹ 60,000 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 55,000 Cr
As Per Project Report
Street Lighting
₹ 15,000 Cr
As Per Project Report
Security And Fire Fighting
₹ 11,000 Cr
As Per Project Report
Playgrounds And Parks
₹ 12,000 Cr
As Per Project Report
Renewable Energy System
₹ 17,000 Cr
As Per Project Report
Earth Filling
₹ 340,000 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Demarcation Plan
Applied For But Yet To Receive
8 May 2019
Zoning Plan
Yet To File For Approval
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Shubhangan?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.