Shubhangan Grand
by Sunbreeze Builders And Developers Private Limited · Village- Nizampur, Sector 40
- RERA registration
- Applied, not granted yet
- Applied on
- 16 Aug 2019
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-631-2019
- Land area
- 2.049 acres
- Apartments
- 143 in 6 towers
- Completion (as filed)
- 30 Sep 2023
- Estimated cost
- ₹ 50.4 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-631-2019 |
| Authority | HRERA Panchkula |
| Project type (as filed) | New |
| Project name | Shubhangan Grand |
| Promoter | Sunbreeze Builders And Developers Private Limited |
| Promoter’s registered office | 1ST Floor, C-9/15, Sector-7, Rohini, New Delhi- 110085 |
| CIN | U70101DL2005PTC144228 |
| Site address | Village- Nizampur, Sector 40 |
| Sector | Sector 40 |
| Tehsil / District | Panipat / Panipat |
| Layout plan approved | 10 Jul 2013 |
| Building plans approved | 22 Jan 2014 |
| Construction start (as filed) | 1 Oct 2020 |
| Completion (as filed) | 30 Sep 2023 |
| Application submitted | 16 Aug 2019 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 14.10.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 18.11.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 20.01.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 24.02.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 30.03.2020.
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 20.04.2020.
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 11.05.2020
-
Hearing
Adjournment View order
Proceedings
Adjourned to 08.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 24.08.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 21.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 23.11.2020.
-
Hearing
Sine Die View order
Proceedings
Sine Die.
-
Hearing
Withdrawn/Rejected View order
Proceedings
DISPOSED OF A WITHDRAWN.
Land, licence & cost
| Land area of the project | 2.049 acres |
|---|---|
| Total licensed area | 2.049 acres |
| Licence | 27 of 2013 |
| FAR permissible / proposed | 1.75 / 1.722 |
| Estimated project cost | ₹ 50.4 Cr |
| Cost of land | ₹ 1.3 Cr |
| Cost of construction | ₹ 37.87 Cr |
| Infrastructure and other structures | ₹ 4.04 Cr |
| EDC, taxes, levies and other costs | ₹ 7.18 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 2,142.641 | 25.8% |
| Construction Of Roads | 3,200 | 38.6% |
| Parks And Playgrounds | 932.53 | 11.2% |
| Vehicle Parkings | 1,960.413 | 23.6% |
| Commercial | 57.346 | 0.7% |
Apartments 143 units · 6 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 83.21 | 896 | 72 |
| Apartment/Shops/Other Buildings | 111.44 | 1,200 | 48 |
| Apartment/Shops/Other Buildings | 18.67 | 201 | 20 |
| Apartment/Shops/Other Buildings | 19.11 | 206 | 3 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | No | WATER SUPPLY |
| No | ELECTRICITY | No |
| Sewage Disposal | No | STORM WATER DRAINAGE |
| No | 4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report: | Sr. No. |
| Name of the facility | Estimated cost (In Lakhs)(Within the project area only) | Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) |
| 1 | INTERNAL ROADS AND PAVEMENTS | 108.675 |
| As Per Project Report | 2 | WATER SUPPLY SYSTEM |
| 93.935 | AS PER PROJECT REPORT | 3 |
| Storm Water Drainage | 45.77 | AS PER PROJECT REPORT |
| 4 | ELECTRICITY SUPPLY SYSTEM | 57.5 |
| As Per Project Report | 5 | SEWAGE TREATMENT & GARBAGE DISPOSAL |
| 62.30 | AS PER PROJECT REPORT | 6 |
| Street Lighting | 9.20 | AS PER PROJECT REPORT |
| 7 | SECURITY AND FIRE FIGHTING | 23.00 |
| As Per Project Report | 8 | PLAYGROUNDS AND PARKS |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.09 Cr | As Per Project Report |
| Water Supply System | ₹ 93.94 lakh | As Per Project Report |
| Storm Water Drainage | ₹ 45.77 lakh | As Per Project Report |
| Electricity Supply System | ₹ 57.5 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 62.3 lakh | As Per Project Report |
| Street Lighting | ₹ 9.2 lakh | As Per Project Report |
| Security And Fire Fighting | ₹ 23 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 4.02 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Zoning Plan | Already Been Obtained | 17 May 2013 |
| Pollution Control | Already Been Obtained | 15 May 2015 |
| Fire Fighting Scheme | Already Been Obtained | 12 Aug 2014 |
| Environment Clearnace | Already Been Obtained | 29 May 2014 |
| Layout Plan | Applied For But Yet To Receive |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tile |
|---|---|
| Wall Finishing Details | Acrylic Distemper On All The Internal Walls |
| Kitchen Details | Designer Glazed Ceramic Ile Up To 2’-0” Height Above Counter And Stainless Single Bowl Sink |
| Bathroom Fittings | All Saintary Fittings Are Of Good Quality As Per The Sheet Of Makes Attached |
| Wood Work Etc | Hard Wood Door Frame With Painted Flush Doors |
| Doors And Windos Frames | Hard Wood Door Frame |
| Glass Work | 5 Mm Thick Glass On Window |
| Electric Fittings | Pvc Conduit And Electrical Work Of Any Good Make As Per Make Sheet Attached |
| Conducting And Wiring Details | Kalinga/Poly Pack Etc. |
| Water Storage | Oht To Be Made On Teerace Of Rcc |
| Lift Details | Stone Finish |
| Windows/Glazings | As Per Sample Approved |
| Doors | Flush Door |
| Main Doors | Flush Door |
| Internal Doors | Flush Door |
| Air Conditioning | Air Conditioning Socket To Be Given In All Bedrooms And Drawing Room |
| Electrical Fittings | All Electrical Fittings Are Of Good Make Sheet Attached |
| External Finishing/Colour Scheme | External Paint |
| Internal Finishing | Acrylic Distemper |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Shubhangan Grand?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.