House No. 15 & 54,First Floor, Block-C,Pocket-9,Sector-7,Rohini,Metro Station-New Delhi East,Dl-110085 In
Site address
Nizampur Road ,Sector-40
Sector
Sector 40
Tehsil / District
Panipat / Panipat
Layout plan approved
29 Oct 2024
Construction start (as filed)
1 Jun 2025
Completion (as filed)
31 May 2028
Application submitted
26 Feb 2026
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutiny25.03.2026
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
2.049 acres
Total licensed area
2.049 acres
Licence
114 OF 2024 DATED 08.08.2024 GRANTED BY TCP
FAR permissible / proposed
2 / 2
Estimated project cost
₹ 21.91 Cr
Cost of land
₹ 15.03 Cr
Infrastructure and other structures
₹ 2.09 Cr
EDC, taxes, levies and other costs
₹ 4.79 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
4,154.49
50.1%
Construction Of Roads
1,587.057
19.1%
Pavements
645.23
7.8%
Parks And Playgrounds
643.44
7.8%
Area To Be Left For Transferring To The Government For Community Services
829.293
10%
Commercial
433.42
5.2%
Plots 37 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
92.24
110
993
18
109.30
131
1,177
1
128.35
154
1,382
1
131.31
157
1,413
5
143.99
172
1,550
7
147.99
177
1,593
4
433.42
518
4,665
1
External services
Service
Provided by
Approval taken
Roads
SELF (INTERNAL)
No
Water Supply
SELF/HSVP
Yes
Electricity
UHBVN
Yes
Sewage Disposal
SELF/HSVP
Yes
Storm Water Drainage
SELF/HSVP
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 45.6 lakh
As Per Project Report
Water Supply System
₹ 25.3 lakh
As Per Project Report
Storm Water Drainage
₹ 18.2 lakh
As Per Project Report
Electricity Supply System
₹ 25.5 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 15.35 lakh
As Per Project Report
Street Lighting
₹ 5.2 lakh
As Per Project Report
Security And Fire Fighting
₹ 11.2 lakh
As Per Project Report
Playgrounds And Parks
₹ 10.5 lakh
As Per Project Report
Earth Filing
₹ 52 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Demarcation Cum Zoning Plan
Already Been Obtained
29 Oct 2024
Approval Of Revised Service Estimates
Already Been Obtained
10 Mar 2025
Copy Of License
Already Been Obtained
8 Aug 2024
Approval Of Electrification Plan
Already Been Obtained
13 Jan 2026
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Shubhangan 2?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.