HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Neeraj Mishra (AR) and Sh. Ashwani Kumar (AR) are present on behalf of the promoter. The site of the project is visited by the concerned officials and it is confirmed that the site is accessible through service road of the existing 60 m wide road. The registration of the project is approved as proposed subject to rectification of deficiencies listed above at S. No. 21 and deposit of security amount of Rs. 25 lakhs on account of submission of approved service plans and estimates within four months from the issuance of registration certificate. The registration certificate shall be issued after the above compliance is made by the promoter.
Registration grantedGGM/977/709/2025/80
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
5 acres
Total licensed area
5 acres
Licence
7 OF 2022 DATED 19.01.2022
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 142.08 Cr
Cost of land
₹ 47.94 Cr
Infrastructure and other structures
₹ 41.64 Cr
EDC, taxes, levies and other costs
₹ 52.5 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
2.551
51%
Construction Of Roads
1.3335
26.7%
Parks And Playgrounds
0.375
7.5%
Electricity Sub-Station
0.037
0.7%
Area To Be Left For Transferring To The Government For Community Services
0.5
10%
Commercialarea
0.2
4%
Roadareatobetakeninlicensedarea
0.0035
0.1%
Plots 70 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
134.70
161
1,450
1
143.10
171
1,540
1
147.21
176
1,585
1
150.00
179
1,615
66
809.37
968
8,712
1
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
GMDA
Yes
ELECTRICITY
No
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
657.32
Yet To Be Prepared
2
WATER SUPPLY SYSTEM
535.78
YET TO BE PREPARED
3
Storm Water Drainage
282.90
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
426.47
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
566.57
YET TO BE PREPARED
6
Street Lighting
27.20
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
187.02
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
136.49
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
15
Underground Water Tank
627.27
YET TO BE PREPARED
16
RAIN WATER HARVESTING
82.41
Yet To Be Prepared
17
ELECTRICAL SUB STATION
426.47
YET TO BE PREPARED
18
Sewerage Sysytem
208.19
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
19-06-2025
(date)
6. Date of approval of Building Plans
NA
(date)
7. New projects:
i) Likely date of starting the construction work
01-05-2025
ii) Likely date of completing the project
11-01-2027
iii) Sizes of the plots to be offered in the project
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
150.00
66
2
134.703
1
3
143.096
1
4
147.207
1
5
809.37
1
Total
70
iv. Type of apartments to be constructed in the project:
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.92
134.39
Water Supply System
109.54
109.54
Sewerage treatment & garbage disposal
42.56
42.56
Electricity Supply System
217.97
208.50
Storm Water Drainage
57.84
57.84
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
STP
193.05
193.05
Street lighting
0
0.60
Security and Fire Fighting
0
4.16
Electrical Sub Station
0
7.11
Underground Water Tank
213.74
213.74
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
131.46
132.93
134.39
121.24
Water Supply System
107.16
108.35
101.20
0
Sewerage treatment & garbage disposal
41.64
42.10
39.32
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
56.58
57.21
53.44
0
Parks and Playgrounds
0
56.87
69.76
9.86
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Electrical Sub Station
159.93
161.70
97.73
Security and Fire Fighting
93.51
89.35
Street Lighting
13.60
12.99
Rainwater Harvesting
2.20
50.00
30.22
STP
180.46
Underground Water Tank
199.80
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
ICICI BANK LTD, SHOP NO. 6 ,MAGNUM CITY CENTRE, SEC 63A,GURGAON-122011
Bank Account number
777705539616
IFSC code
ICIC0005396
MICR code
110229411
Branch code
5396
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
SATISH KUMAR, MOHIT GARG,
Vikas Garg, Mayank Garg
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
ATTACHED
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
Yes
ii. Demarcation Plan
Yes
iii. Zoning Plan
Yes
iv. Building Plan
No
Site Plan
Yes
Floor Plan
No
Apartment Plans
No
Elevation Section
No
Detail of Permissible FAR
No
Detail of covered area achieved FAR
No
2. Annex copies of the following in Folder E:
I. Roads And Pavement Plan
Yes
II. ELECTRICITY SUPPLY PLAN
No
III. WATER SUPPLY PLAN
Yes
IV. Sewerage And Garbage Disposal Plan
Yes
V. STROM WATER DRAINAGE
Yes
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
Yes
Vii. Street Lighting Plan
No
VIII. PARKING PLAN
No
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 7 OF 2022
Already Been Obtained
19-01-2022
II. DEMARCATION CUM ZONING 11260
Already Been Obtained
16-07-2025
III. REVISED LAYOUT PLAN
Already Been Obtained
19-06-2025
IV. REVISED ZOINING
Already Been Obtained
17-07-2025
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
Form Rep-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
Agreement Attached
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - G
Projects launched by the promoter in last five years:
1. Name and location of the project
ANANTAM,VILLAGE NAURANGPUR, SECTOR-78, GURUGRAM
2. Particulars of the project in brief:
i. Total area of the project
5.29375
ii. Total number of apartments
617
iii. Total number of plots
0
3. The number of plots/ apartments booked/sold to the allottees:
(a) Apartments
100
(b) Plots
0
4. Details of the expenditure incurred upto date:
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
116794.61
0
0
Cost of the apartments
82407.78
0
2343.01
Cost of the infrastructure
11762.26
0
0
Others costs
22624.66
0
5273.03
5. Total amount of money collected from current allottees of the apartments/ plots upto the date of filing this application.
134778 Lakhs
6. Remaining amount of sale price money to be collected from the current allottees of the apartments.
9932.58 Lakhs
7. Loan sanctioned by the banks/ other financial institutions against the project.
0 Lakhs
8. Amount drawn from the banks/ other financial institutions till the date of filing this application.
0 Lakhs
9. Whether any litigation is pending against the Project:
Yes/No
(If yes-give Annex details in folder G)
No
10. Initial date of completion of the project.
21-10-2028
11. Likely date of completion of the project.
21-10-2028
I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - H
Specification Of Construction
Specification of apartments and other buildings including the following:
1
Flooring Details Of Various Parts Of House
NA
2
Wall Finishing Details
NA
3
Kitchen Details
NA
4
Bathroom Fittings
NA
5
Wood Work Etc
NA
6
Doors And Windos Frames
NA
7
Glass Work
NA
8
Electric Fittings
NA
9
Conducting And Wiring Details
NA
10
Cupboard Details
NA
11
Water Storage
NA
12
Lift Details
NA
13
External Glazings
NA
13.1
Windows/Glazings
NA
14
Doors
NA
14.1
Main Doors
NA
14.2
Internal Doors
NA
15
Air Conditioning
NA
16
Electrical Fittings
NA
17
Cng Pipe Line
NA
18
Provision Of Wifi And Broadband Facility
NA
19
External Finishing/Colour Scheme
NA
20
Internal Finishing
NA
SPECIFICATION UNIT WISE
1 . Living/Dining/Foyer/Family Lounge
1 . 1
FLOOR
Na
1 . 2
WALLS
Na
1 . 3
CEILING
Na
2 . MASTER BEDROOM/DRESSROOM
2 . 1
Floor
NA
2 . 2
Walls
NA
2 . 3
Ceiling
NA
2 . 4
Modular Wardrobes
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . Bed Rooms
4 . 1
FLOOR
Na
4 . 2
WALLS
Na
4 . 3
CEILING
Na
4 . 4
WARDROBES
Na
5 . TOILET
5 . 1
Floor
NA
5 . 2
Walls
NA
5 . 3
Ceiling
NA
5 . 4
Counters
NA
5 . 5
Sanitary Ware/Cp Fittings
NA
5 . 6
Fixtures
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . Utility Rooms/Utility Balcony/Toilet
7 . 1
FLOOR
Na
7 . 2
WALLS & CEILING
Na
7 . 3
TOILET
Na
7 . 4
BALCONY
Na
8 . SIT-OUTS
8 . 1
Floor
NA
8 . 2
Walls & Ceiling
NA
8 . 3
Railings
NA
8 . 4
Fixtures
NA
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
List of Uploaded Documents
Sr. No.
Document Description
Date of Document Upload
View Document
1
NOC ARAVLI
26-08-2025
View Document
2
MUTATION 2025
26-08-2025
View Document
3
Zoning Plan
19-07-2025
View Document
4
IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN
26-08-2025
View Document
5
AFFIDAVIT FOR LANDOWNER SHARE
28-08-2025
View Document
6
In Case Of Group Housing/ Commercial Sites, A Copy Of The Approved Site Plan
19-07-2025
View Document
7
A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS
19-07-2025
View Document
8
DEMARCATION PLAN
19-07-2025
View Document
9
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record
18-07-2025
View Document
10
SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
19-07-2025
View Document
11
UNDERTAKING NCZ, TREE CUTTING AND OTHERS
26-08-2025
View Document
12
Undertaking For No Sale Of Plot
28-08-2025
View Document
13
COLLABORATION AGREEMENT
26-08-2025
View Document
14
AFFIDAVIT 4(2)(1)(D)
26-08-2025
View Document
15
Undertaking Regarding 10% Edc
26-08-2025
View Document
16
UNDERTAKING FOR NO CHARGE CREATION
26-08-2025
View Document
17
BANK UNDERTAKING
26-08-2025
View Document
18
Jamabandi 25 89
26-08-2025
View Document
19
SEWARAGE ASSURANCE
26-08-2025
View Document
20
STP TREATED WATER ASSURANCE
26-08-2025
View Document
21
Aai Noc 5 Acres 89 DDJAY
26-08-2025
View Document
22
WATER SUPPLY LAYOUT PLAN
26-08-2025
View Document
23
CASH FLOW STATEMENT OF THE PROPOSED PROJECT
26-08-2025
View Document
24
Non Default Certificate From A Chartered Accountant
26-08-2025
View Document
25
ANNEX C RULE 14
26-08-2025
View Document
26
SIZRA 25
26-08-2025
View Document
27
Loi
26-08-2025
View Document
28
DEMARCATION CUM ZONING PLAN SECTOR 89 & 93
26-08-2025
View Document
29
LC IV AND LC IV B
26-08-2025
View Document
30
Current Jamabandi 2025 93
26-08-2025
View Document
31
DRINKING WATER ASSURANCE
26-08-2025
View Document
32
FOREST NOC
26-08-2025
View Document
33
Copy Of License Along With Schedule Of Land
26-08-2025
View Document
34
NON ENCUMBRANCE
26-08-2025
View Document
35
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT
26-08-2025
View Document
36
Declaration Supported By Affidavit Duly Signed By The Promoter To Be Enclosed.
26-08-2025
View Document
37
ROAD LAYOUT PLAN
26-08-2025
View Document
38
ZONING APPROVAL LETTER SECTOR 89 & 93
26-08-2025
View Document
39
Sewer Layout Plan
26-08-2025
View Document
40
SIZRA SUPERIMPOSED LAYOUT
26-08-2025
View Document
41
STORM LAYOUT PLAN
26-08-2025
View Document
42
No Proposed Sale Affidavit
28-08-2025
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Print
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 6.57 Cr
Yet To Be Prepared
Water Supply System
₹ 5.36 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 2.83 Cr
Yet To Be Prepared
Electricity Supply System
₹ 4.26 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 5.67 Cr
Yet To Be Prepared
Street Lighting
₹ 27.2 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 1.87 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 1.36 Cr
Yet To Be Prepared
Underground Water Tank
₹ 6.27 Cr
Yet To Be Prepared
Rain Water Harvesting
₹ 82.41 lakh
Yet To Be Prepared
Electrical Sub Station
₹ 4.26 Cr
Yet To Be Prepared
Sewerage Sysytem
₹ 2.08 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License No. 7 Of 2022
Already Been Obtained
19 Jan 2022
Demarcation Cum Zoning 11260
Already Been Obtained
16 Jul 2025
Revised Layout Plan
Already Been Obtained
19 Jun 2025
Revised Zoining
Already Been Obtained
17 Jul 2025
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Kashi?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.