- RERA-GRG-1558-2024
- Land area
- 8.009 acres
- Plots
- 142
- Completion (as filed)
- 31 Dec 2029
- Estimated cost
- ₹ 75.38 Cr
RERA registration
| Registration certificate | GGM/1002/734/2025/105, dated 17 Oct 2025 |
|---|---|
| Registration valid till | 31 Dec 2029 |
| Project ID | RERA-GRG-1558-2024 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Horizon 82 |
| Promoter | Vatika Limited |
| Promoter’s registered office | Unit No. - A-002, Inxt City Centre, Ground Floor, Block - A, Sector - 83,Vatika India Next, Gururam - 122012 |
| CIN | U74899HR1998PLC054821 |
| Site address | Sector - 82A, Village Shikohpur |
| Sector | Sector 82A |
| Tehsil / District | Manesar / Gurugram |
| Construction start (as filed) | 1 Jan 2024 |
| Completion (as filed) | 31 Dec 2029 |
| Application submitted | 29 Apr 2024 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
The matter is adjourned and to come up on 24.06.2024
-
Hearing
Adjournment View order
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (AR), Sh. Jitender Kumar (AR) and Sh. Rahul Johri (AR) are present on behalf of the promoter. The promoter has applied for registration after migration of the part of the area falling under already registered project wherein 3rd party rights were also created, and claims were filed in the Authority. The promoter to clarify the status of each of the allottee and payments received along with amount refunded, sold and unsold inventory. The office to convey other deficiencies in the application and to also put up on file to sending a reference to DTCP as to how the part of already registered area has been migrated to another scheme without consent/full and final settlement of the allottees of earlier project. The matter to come up on 05.08.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 30.09.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 21.10.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 04.11.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 02.12.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 13.01.2025.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 27.01.2025.
-
Hearing
Adjournment
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (AR) and Sh. Jitender Kumar (AR) are present on behalf of the promoter. A public notice be published in two prominent widely circulated English newspapers and one Hindi newspaper of three weeks inviting objections if any regarding the settlement of existing allottees claimed by the promoter and migration of the land of the existing project namely Tranquil Heights be issued. Further, matter be pursued with DTCP/State Government with respect to migration of registered projects. The matter to come up on 10.03.2025.
-
Hearing
Adjournment
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (AR), Sh. Jitender Kumar (AR) and Sh. Rahul Johri (AR) are present on behalf of the promoter. A public notice be published again in two prominent widely circulated English newspapers namely “The Tribune” & “Hindustan Times” and one Hindi namely “Dainik Bhaskar” of two weeks inviting objections if any regarding the settlement of existing allottees claimed by the promoter and migration of the land of the existing project namely Tranquil Heights be issued. Further, the office to put up on file to sending a final reminder to DTCP as to how the part of already registered area has been migrated to another scheme without consent/full and final settlement of the allottees of earlier project. The matter to come up on 07.04.2025.
-
Hearing
Adjournment
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (Vice President), Sh. Jitender Kumar (Sr. Manager) are present on behalf of the promoter. Few objections were received against a public notice inviting objections in the Authority for which copy of the same to be supplied to the promoter. Further, the promoter is directed to submit the reply against the same. The matter to come up on 26.05.2025.
-
Hearing
Adjournment
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (Vice President), Sh. Jitender Kumar (Sr. Manager) are present on behalf of the promoter. Sh. Siddharth Loiwal (Allottee), Sh. Himanshu Chawla (Allottee), Sh. Yogesh (Allottee), Ms. Anita Sardana (Allottee) are present. The promoter has requested for a passover for one hour as the concerned counsel was not present on the behalf of promoter whereas Authority has allowed for the same. Further, even after allowing the request of promoter for passover, the concerned counsel did not appear before the Authority. Therefore, the matter is adjourned. The matter to come up on 07.07.2025.
- Hearing Adjournment View order
- Hearing Adjournment
-
Hearing
Adjournment View order
Proceedings
The matter to come up on 29.09.2025.
- Hearing Adjournment View order
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Ms. Nikita Mittal (Planning Executive) and Sh. Ashish Dubey (Chartered Accountant) briefed about the facts of the case. Sh. Virender Dhar (Vice President), Sh. Jitender Kumar (Sr. Manager), Sh. Amit Malhotra and Sh. Sumit Arora are present on behalf of the promoter and states that all the allottees including the objectors who have filed the objections including the two allottees, namely Smt. Anita Sardana, whose claims to have been settled. With respect to the claim of Smt. Anita Sardana, he submits that the amount due has been paid in compliance with the Authority’s earlier directions, and a certain amount has also been deposited before the Hon’ble Appellate Tribunal. As far as claim of Sh. Praveen Singh is concerned, he has placed on record a Settlement Agreement dated 06.10.2025. Meanwhile, the promoter states that objection filed by Sh. Siddhartha Loiwal has also been settled as per the orders of Hon’ble NCDRC. Further, Sh. Virender Dhar (Vice President), states that they are submitting an affidavit of the Director of the company affirming that there are no remaining unsettled claims of allottees and, if any further claims of the allottees will arise, the promoter will settle the claims accordingly. The Authority observes that the none of the aforesaid objectors have appeared today before us. This Authority has waited sufficiently and has given sufficient opportunity to the objectors to raise their objections but since no one is present today hence, given the circumstance, it can safely be presumed that claims of all the objectors have been settled which is also corroborated by the Affidavit of the Director of the Promoter dt. 13.10.2025. In light of the foregoing, the registration of the project is hereby approved, subject to the rectification of the remaining deficiencies. The declaration made by the Director of the promoter company, as contained in the affidavit dated 13.10.2025, shall form an integral part of the registration certificate. The certificate shall be issued upon due compliance with the outstanding requirements and necessary corrections in Forms A to H and the Detailed Project Information (DPI). Needless to mention that with the approval of the present application for registration, earlier RC bearing no. 359 of 2017 dt. 17.11.2017 regarding the project “Tranquil Heights” stands subsumed. This is without prejudice to the rights of the allottees of the project under Section 18 of the Act of 2016.
- Registration granted GGM/1002/734/2025/105
- Certificate uploaded RCUploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 8.009 acres |
|---|---|
| Total licensed area | 8.009 acres |
| Licence | License No. 19 of 2024 dated 09.02.2024 and valid upto 08.02.2029 |
| FAR permissible / proposed | 100 / 100 |
| Estimated project cost | ₹ 75.38 Cr |
| Cost of land | ₹ 0.4 Cr |
| Cost of construction | ₹ 0.21 Cr |
| Infrastructure and other structures | ₹ 3.8 Cr |
| EDC, taxes, levies and other costs | ₹ 70.97 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Plots To Be Sold | 16,119.85 | 49.7% |
| Construction Of Roads | 9,178.667 | 28.3% |
| Sewage And Solid Waste Treatment Facility | 150 | 0.5% |
| Area To Be Left For Transferring To The Government For Community Services | 3,241.53 | 10% |
| Any Other | 1,289.07 | 4% |
| Organised | 2,433.65 | 7.5% |
Plots 142 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 75.25 | 90 | 810 | 1 |
| 77.32 | 92 | 832 | 2 |
| 77.39 | 93 | 833 | 1 |
| 77.51 | 93 | 834 | 1 |
| 77.58 | 93 | 835 | 1 |
| 78.26 | 94 | 842 | 1 |
| 78.72 | 94 | 847 | 1 |
| 89.39 | 107 | 962 | 1 |
| 91.88 | 110 | 989 | 1 |
| 92.50 | 111 | 996 | 1 |
| 96.01 | 115 | 1,033 | 1 |
| 96.57 | 115 | 1,039 | 1 |
| 96.72 | 116 | 1,041 | 1 |
| 97.09 | 116 | 1,045 | 1 |
| 97.50 | 117 | 1,049 | 67 |
| 98.60 | 118 | 1,061 | 1 |
| 99.40 | 119 | 1,070 | 1 |
| 100.13 | 120 | 1,078 | 1 |
| 103.13 | 123 | 1,110 | 1 |
| 104.26 | 125 | 1,122 | 1 |
| 108.42 | 130 | 1,167 | 1 |
| 108.69 | 130 | 1,170 | 1 |
| 112.55 | 135 | 1,211 | 1 |
| 116.48 | 139 | 1,254 | 1 |
| 117.18 | 140 | 1,261 | 1 |
| 118.93 | 142 | 1,280 | 1 |
| 119.77 | 143 | 1,289 | 1 |
| 120.09 | 144 | 1,293 | 1 |
| 137.77 | 165 | 1,483 | 1 |
| 140.26 | 168 | 1,510 | 1 |
| 140.46 | 168 | 1,512 | 1 |
| 140.77 | 168 | 1,515 | 1 |
| 147.00 | 176 | 1,582 | 43 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.1 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 24.03 lakh | Yet To Be Prepared |
| Storm Water Drainage | ₹ 18.01 lakh | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 17.03 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 20.04 lakh | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 24.03 lakh | Yet To Be Prepared |
| Parking | ₹ 70.1 lakh | Yet To Be Prepared |
| Sewerage | ₹ 24.04 lakh | Yet To Be Prepared |
| Ugt | ₹ 16.03 lakh | Yet To Be Prepared |
| Rain Water Harvesting | ₹ 9.01 lakh | Yet To Be Prepared |
| Electrification | ₹ 24.03 lakh | Yet To Be Prepared |
| Electrical Meter Room | ₹ 23.03 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No. 19 Of 2024 | Already Been Obtained | 8 Feb 2029 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Horizon 82?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.