Footfalls
by Vatika Limited · Sector - 88B, Village Harsaru
- RERA registration
- GGM/929/661/2025/32
- Registered on
- 27 Mar 2025
- Valid till
- 30 Sep 2029
- Project ID
- RERA-GRG-1796-2024
- Land area
- 2.625 acres
- Plots
- 40
- Completion (as filed)
- 30 Sep 2029
- Estimated cost
- ₹ 30.56 Cr
RERA registration
| Registration certificate | GGM/929/661/2025/32, dated 27 Mar 2025 |
|---|---|
| Registration valid till | 30 Sep 2029 |
| Project ID | RERA-GRG-1796-2024 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Footfalls |
| Promoter | Vatika Limited |
| Promoter’s registered office | Unit No. - A-002, Inxt City Centre, Ground Floor, Block - A, Sector - 83, Vatika India Next, Gurugram - 122012 |
| CIN | U74899HR1998PLC054821 |
| Site address | Sector - 88B, Village Harsaru |
| Sector | Sector 88B |
| Tehsil / District | Harsaru St / Gurugram |
| Layout plan approved | 11 Mar 2024 |
| Construction start (as filed) | 1 Oct 2024 |
| Completion (as filed) | 30 Sep 2029 |
| Application submitted | 22 Nov 2024 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
The matter is adjourned and to come up on 30.12.2024.
- Notice sent to the promoter Deficiency Notice
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 27.01.2025.
-
Hearing
Adjournment View order
Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Virender Dhar (AR) and Sh. Jitender Kumar (AR) are present on behalf of the promoter. A public notice of two weeks for inviting objections if any regarding the affidavit of the promoter regarding no sale/creation of 3rd party rights in the project be issued in three newspapers (one in Hindi and two in English) of wide circulation. The distribution of plots between the landowners and collaborator be got signed from the concerned landowners duly attested by 1st Class Magistrate. Balance deficiencies to be also rectified. Further, the planning executive to visit the site and submit report within seven days. The matter to come up on 17.02.2025.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 24.02.2025.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Ms. Prachi Singh, Planning Executive and Ms. Asha Chartered Accountant briefed about the facts of the project. Mr. Virender Dhar and Mr.Jitender Kumar are present on behalf of the promoter. The penal proceedings for violation of section 3 of the Act, 2016 have been dealt separately vide complaint no. 983 of 2025. Approved as proposed subject to rectification of deficiencies mentioned above including correction in A-H form and Online DPI. The Registration Certificate shall be issued after submission of remaining deficiencies mentioned above including correction in A-H form and Online DPI.
- Registration granted GGM/929/661/2025/32
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 2.625 acres |
|---|---|
| Total licensed area | 2.625 acres |
| Licence | License No. 35 of 2024 dated 07.03.2024 and valid upto 06.03.2029. |
| FAR permissible / proposed | 150 / 150 |
| Estimated project cost | ₹ 30.56 Cr |
| Cost of land | ₹ 0.17 Cr |
| Infrastructure and other structures | ₹ 6 Cr |
| EDC, taxes, levies and other costs | ₹ 24.39 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 0.9153 | 34.9% |
| Road And Pavement | 1.7097 | 65.1% |
Plots 40 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 30.85 | 37 | 332 | 6 |
| 90.00 | 108 | 969 | 17 |
| 108.00 | 129 | 1,163 | 3 |
| 112.50 | 135 | 1,211 | 10 |
| 135.00 | 161 | 1,453 | 4 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | No |
| Water Supply | GMDA | No |
| Electricity | DHBVN | No |
| Sewage Disposal | GMDA | No |
| Storm Water Drainage | GMDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 3.04 Cr | Submitted To Town & Country Planning |
| Water Supply System | ₹ 66.37 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 24.89 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 66.37 lakh | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 82.94 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 55.28 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No. 35 Of 2024 | Already Been Obtained | 7 Mar 2024 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Footfalls?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.