10TH Floor Global Business Park, Tower D, Mg Road, Gurugram-122002
CIN
U74899DL1990PTC039324
Site address
Sector-62, Village Ullhawas, Wazirabad, Gurugram, Haryana
Sector
Sector 62
Tehsil / District
Wazirabad St / Gurugram
Layout plan approved
31 Oct 2023
Building plans approved
31 Oct 2023
Construction start (as filed)
29 Feb 2024
Completion (as filed)
1 Oct 2030
Application submitted
21 Oct 2023
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
Notice sent to the promoterBy Hand
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. S.K. Kaushik (AR) and Sh. Ajay Gupta (AR) are present on behalf of the promoter. The promoter shall submit the fire scheme approval within 4 months, Environment Clearance and approval of service plans and estimates within 6 months from the date of issuance of registration certificate and mining permission shall be submitted before the commencement of the construction. Approved as proposed.
Registration grantedGGM/757/489/2023/101
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
4.844 acres
Total licensed area
4.844 acres
Licence
Licence No. 114/2023 dated 02.06.2023 granted by Town and Country Planning Department, Haryana Government
FAR permissible / proposed
3.228 / 3.228
Estimated project cost
₹ 1,083.59 Cr
Cost of land
₹ 301.49 Cr
Cost of construction
₹ 464.4 Cr
Infrastructure and other structures
₹ 67.25 Cr
EDC, taxes, levies and other costs
₹ 250.45 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
0.4372
9%
Construction Of Roads
1.0247
21.2%
Pavements
0.7623
15.7%
Parks And Playgrounds
0.969
20%
Club House
0.3525
7.3%
Any Other
1.298
26.8%
Apartments 474 units · 2 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
35,866.64
-
240
Apartment/Shops/Other Buildings
7,605.40
-
190
Apartment/Shops/Other Buildings
1,426.61
15,356
1
Apartment/Shops/Other Buildings
1,001.60
10,781
43
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
ALREADY CONNECTED
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 4.22 Cr
As Per Project Report
Water Supply System
₹ 3.02 Cr
As Per Project Report
Storm Water Drainage
₹ 70.64 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 55.48 lakh
As Per Project Report
Street Lighting
₹ 64 lakh
As Per Project Report
Security And Fire Fighting
₹ 41.83 lakh
As Per Project Report
Playgrounds And Parks
₹ 40.6 lakh
As Per Project Report
Club House/Community Centre
₹ 35 Cr
As Per Project Report
Renewable Energy System
₹ 52 lakh
As Per Project Report
Parking
₹ 9.27 Cr
As Per Project Report
Stp
₹ 60 lakh
As Per Project Report
Electrical Sub Station
₹ 2.23 Cr
As Per Project Report
Over Head Water Tanks
₹ 38.22 lakh
As Per Project Report
Rain Water Harvesting
₹ 51 lakh
As Per Project Report
Underground Water Tank
₹ 42.16 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Electricity Load Availability
Already Been Obtained
9 Jun 2023
Storm Water Drainage
Already Been Obtained
16 Jun 2023
Zoning Plan Approval
Already Been Obtained
2 Jun 2023
Forest Noc
Already Been Obtained
28 Apr 2023
Tree Cutting Permission
Already Been Obtained
10 Jul 2023
Water Supply
Already Been Obtained
22 Jun 2023
Sewage Disposal
Already Been Obtained
15 Jun 2023
Specifications (as filed)
Flooring Details Of Various Parts Of House
Marble/ Premium Quality Tiles/ Equivalent
Wall Finishing Details
Paint Surface
Kitchen Details
Floor Tiles & Paint
Bathroom Fittings
Standard Cp Fitting + Wc+Washbasin
Wood Work Etc
Flush Floor
Doors And Windos Frames
Double/Single Glass
Electric Fittings
Led Fixtures
Conducting And Wiring Details
Frls Insultated Copper Conductor Wire
Water Storage
Water Tank Ug/Oh
Lift Details
Passenger/Service/Fireman Lift
Windows/Glazings
Aluminium/ Upvc/ Equivalent
Main Doors
Flush Door
Internal Doors
Both Side Laminated
Air Conditioning
Vrv System
Electrical Fittings
Led Fixtures
External Finishing/Colour Scheme
Texture Paint
Internal Finishing
Paint Surface
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Elevate Reserve?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.