Alameda Central
by DLF Home Developers Limited · Sector 73
- RERA registration
- Applied, not granted yet
- Applied on
- 22 Jul 2024
- Application status
- Approved And Ready For Certificate Issuing Process
- Project ID
- RERA-GRG-1639-2024
- Land area
- 3.156 acres
- Plots
- 42
- Completion (as filed)
- 8 Sep 2027
- Estimated cost
- ₹ 78.7 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-1639-2024 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Alameda Central |
| Promoter | DLF Home Developers Limited |
| Promoter’s registered office | 2ND Floor, Arjun Marg, DLF Shopping Mall, DLF City Phase 1, Gurugram |
| CIN | U74899HR1995PLC082458 |
| Site address | Sector 73 |
| Sector | Sector 73 |
| Tehsil / District | Kadipur St / Gurugram |
| Layout plan approved | 6 Nov 2023 |
| Building plans approved | 18 Jan 2024 |
| Construction start (as filed) | 1 Apr 2023 |
| Completion (as filed) | 8 Sep 2027 |
| Application submitted | 22 Jul 2024 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter Deficiency Notice
-
Hearing
Examination By Authority View order
Proceedings
The matter is adjourned and to come up on 09.09.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anish Dham (AR), Sh. Ketan Nanda (AR) and Sh. Nitin Gupta (AR) are resent on behalf of the promoter. The AR to submit the requisite consent of 2/3rd allottees and thereafter a public notice for objections if any be issued. The matter to come up on 30.09.2024.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 28.10.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Anish Dham (AR), Sh. Kabir Kapoor (AR) and Sh. Nitin Gupta (AR) are present on behalf of the promoter. The AR of the promoter states that they have obtained the additional license no. 237 of 2023 dated 03.11.2023 for area measuring 0.175 acres in addition to earlier license no. 139 of 2022 dated 09.09.2022 for area admeasuring 2.98125 acres, thereby forming total area admeasuring 3.156 acres for development of commercial plotted colony. Accordingly, layout plan has been revised and approved by DTCP, Haryana. The earlier licensed area is already registered with the authority and the promoter requests to grant an amendment in the earlier registration due to grant of additional license instead of granting separate registration for additional licensed area as the additional area is very small (i.e., 0.175 acres) and there are only two plots added in revised layout plan and that too demarcated on earlier licensed land. Further, the promoter has submitted the consent of 2/3rd allottees of the project for revision in the existing layout plan. A two weeks public notice be issued in three newspapers (One Hindi and Two English) of wide circulation for inviting objections if any regarding revision in layout plan. Meanwhile, the office to process the request for amendment in earlier registration. The matter to come up on 18.11.2024.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Sumeet, Engineering Officer briefed about the facts of the project. Sh. Anish Dham (AR), Sh. Kabir Kapoor (AR) and Sh. Nitin Gupta (AR) are present on behalf of the promoter. The AR of the promoter clarifies that 0.175 acres area has been got migrated from earlier license area (license no. 88 of 2010) as the said area/pocket was reserved for UD (undetermined use) and CC in respect of the said license already stand obtained in the year 2013. The requisite consent of 2/3rd allotees has been submitted in the authority and no objection in respect of the public notice issued by the Authority has been received. No plots or saleable area is approved/shown in the additional licensed area. In view of the same, the addendum to the earlier RC no. 107 of 2022 is approved as proposed subject to corrections in online A-H form & DPI and this shall be without prejudice the rights of the existing allotees under section 14 of the Act.
Land, licence & cost
| Land area of the project | 3.156 acres |
|---|---|
| Total licensed area | 3.156 acres |
| Licence | 237 of 2023 dated 03.11.2023 and 139 of 2022 dated 09.09.2022 |
| FAR permissible / proposed | 1.5 / 1.5 |
| Estimated project cost | ₹ 78.7 Cr |
| Cost of land | ₹ 27.02 Cr |
| Infrastructure and other structures | ₹ 22.65 Cr |
| EDC, taxes, levies and other costs | ₹ 29.03 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 1.086 | 34.4% |
| Construction Of Roads | 1.11 | 35.2% |
| Parks And Playgrounds | 0.45 | 14.3% |
| Electricity Sub-Station | 0.06 | 1.9% |
| Sewage And Solid Waste Treatment Facility | 0.04 | 1.3% |
| Openarea | 0.41 | 13% |
Plots 42 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 86.44 | 103 | 930 | 17 |
| 88.20 | 105 | 949 | 10 |
| 136.15 | 163 | 1,466 | 15 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 3.41 Cr | As Per Project Report |
| Water Supply System | ₹ 1.18 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 1.15 Cr | As Per Project Report |
| Electricity Supply System | ₹ 4.14 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.2 Cr | As Per Project Report |
| Street Lighting | ₹ 49.52 lakh | As Per Project Report |
| Earth Works | ₹ 1.2 Cr | As Per Project Report |
| Sewerage System | ₹ 2.27 Cr | As Per Project Report |
| Ugt | ₹ 1.08 Cr | As Per Project Report |
| Rainwater Harvesting | ₹ 86.31 lakh | As Per Project Report |
| Parking And Parks | ₹ 5.67 Cr | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Licence 237 Of 2023 | Already Been Obtained | 3 Nov 2023 |
| Layout Plan | Already Been Obtained | 6 Nov 2023 |
| Acs II | Already Been Obtained | 18 Jan 2024 |
| Spe Revised | Already Been Obtained | 30 Aug 2024 |
| License 139 Of 2022 | Already Been Obtained | 9 Sep 2022 |
| Acs I | Already Been Obtained | 14 Nov 2022 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Alameda Central?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.