2ND Floor, Arjun Marg, DLF Shopping Mall, DLF City Phase I, Gurugram, 122002
CIN
U74899HR1995PLC082458
Site address
Sector 84, Gurugram, Haryana 122004
Sector
Sector 84
Tehsil / District
Manesar / Gurugram
Layout plan approved
15 Jan 2025
Construction start (as filed)
1 Jul 2025
Completion (as filed)
30 Jun 2030
Application submitted
21 Apr 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
Notice sent to the promoter1st Deficiency Notice
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Rohit Sharma (AR), Sh. Anish Dham (AR) and Sh. Saurabh Chorasia (AR) are present on behalf of the promoter. Approved as proposed subject to the correction in Form A-H and DPI. The registration certificate shall be issued after submission of corrected Form A-H and DPI.
Registration grantedGGM/969/701/2025/72
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
6.544 acres
Total licensed area
6.544 acres
Licence
08 of 2025 dated 14.01.2025
FAR permissible / proposed
1.5 / 1.5
Estimated project cost
₹ 155.26 Cr
Cost of land
₹ 36.36 Cr
Infrastructure and other structures
₹ 54.19 Cr
EDC, taxes, levies and other costs
₹ 64.7 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
9,262.72
35%
Construction Of Roads
9,618.2
36.3%
Parks And Playgrounds
2,922.94
11%
Vehicle Parkings
3,590.42
13.6%
Electricity Sub-Station
350
1.3%
Sewage And Solid Waste Treatment Facility
247
0.9%
Toilet
20
0.1%
Rain
90
0.3%
Ug
215
0.8%
Meter
30
0.1%
Misc
135
0.5%
Plots 46 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
149.80
179
1,612
20
234.35
280
2,523
24
286.13
342
3,080
1
320.19
383
3,446
1
External services
Service
Provided by
Approval taken
Roads
GMDA
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 5.96 Cr
As Per Project Report
Water Supply System
₹ 2.17 Cr
As Per Project Report
Storm Water Drainage
₹ 2.71 Cr
As Per Project Report
Electricity Supply System
₹ 16.26 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 5.96 Cr
As Per Project Report
Street Lighting
₹ 54 lakh
As Per Project Report
Security And Fire Fighting
₹ 54 lakh
As Per Project Report
Playgrounds And Parks
₹ 7.05 Cr
As Per Project Report
Earthwork
₹ 2.71 Cr
As Per Project Report
Parking
₹ 54 lakh
As Per Project Report
Ug Tank
₹ 3.25 Cr
As Per Project Report
Rain Water Harvesting
₹ 2.17 Cr
As Per Project Report
Electrical Sub Station
₹ 4.34 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Service Plan Estimate
Already Been Obtained
25 Apr 2025
Layout Plan Dwg No. Dtcp -10779
Already Been Obtained
15 Jan 2025
License No. 8 Of 2025
Already Been Obtained
14 Jan 2025
Layout Plan
Already Been Obtained
15 Jan 2025
Architectural Control Sheet
Already Been Obtained
16 Apr 2025
Service Plan And Estimates
Already Been Obtained
25 Apr 2025
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Central 84?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.