The Sixty Three
by DLF Home Developers Limited · Sector 63, Gurugram, Haryana-122102
- RERA registration
- GGM/671/403/2023/15
- Registered on
- 23 Jan 2023
- Valid till
- 31 Mar 2030
- Project ID
- RERA-GRG-1138-2022
- Land area
- 25.087 acres
- Apartments
- 1,155 in 5 towers
- Completion (as filed)
- 31 Mar 2030
- Estimated cost
- ₹ 5,418.03 Cr
RERA registration
| Registration certificate | GGM/671/403/2023/15, dated 23 Jan 2023 |
|---|---|
| Registration valid till | 31 Mar 2030 |
| Project ID | RERA-GRG-1138-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | The Sixty Three |
| Promoter | DLF Home Developers Limited |
| Promoter’s registered office | 1ST Floor, DLF Gateway Tower R Block, DLF City Phase-III, Gurugram 122002, Haryana |
| CIN | U74899HR1995PLC082458 |
| Site address | Sector 63, Gurugram, Haryana-122102 |
| Sector | Sector 63 |
| Tehsil / District | Badshahpur St / Gurugram |
| Layout plan approved | 20 Jan 2023 |
| Building plans approved | 20 Jan 2023 |
| Construction start (as filed) | 1 Sep 2022 |
| Completion (as filed) | 31 Mar 2030 |
| Application submitted | 29 Aug 2022 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter Deficiency notice
-
Hearing
Examination By Authority View order
Proceedings
Sh. J.S. Sindhu, Executive Engineer (Monitoring) and Ms. Asha (Chartered Accountant) briefed the facts of the case. Sh. Anish Dham (AVP) and Sh. Sidharth Gandhi (AVP) are present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Deficit fee, if any be also paid before the next date of hearing along with proof of having deposited the deficit fee. However, the AR has submitted a copy of circular issued by interim HRERA bearing Memo No. 1049, dated 15.09.2017 vide which a clarification has been issued to M/s NAREDCO Haryana that a promoter may register his license (unlaunched) projects any time in future before advertising, marketing or sale of the real estate project and seeks a liberty to file representation in this regard. The applicant promoter may submit the representation within 2 weeks and same shall be got examined by the Authority by taking a legal opinion from Addl. AG, Haryana. The matter to come up on 10.10.2022.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned for 17.10.2022.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 17.10.2022. Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Anish Dham (AVP), Sh. Sidharth Gandhi (AVP) and Sh. Nishith Jain (Sr. Manager) are present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. During the hearing dated 19.09.2022 it was submitted that copy of circular issued by interim HRERA bearing Memo No. 1049, dated 15.09.2017 vide which a clarification has been issued to M/s NAREDCO Haryana that a promoter may register his license (unlaunched) projects any time in future before advertising, marketing or sale of the real estate project and seeks a liberty to file representation in this regard. The promoter has submitted the detailed representation in this regard which be sent to the A.G. Haryana for taking legal opinion. The matter to come up on 14.11.2022. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Anish Dham (AVP) and Sh. Siddharth Gandhi are present on behalf of the promoter. The legal opinion is yet to be received in the Authority. Accordingly, the matter is adjourned to 28.11.2022. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
-
Hearing
Adjournment View order
Proceedings
The authorized representative of the promoter is advised to rectify the deficiencies and submit the deficit fee (if any) along with the deficit documents apart from filing information in REP-I A to H format and online detailed project information. Matter to come up on 12.12.2022 (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 26.12.2022
-
Hearing
Adjournment View order
Proceedings
The AR of the promoter is directed to remove the deficiencies and the matter is adjourned to 09.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 16.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 23.01.2023.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Anish Dham (A.V.P), Sh. Siddharth Gandhi, Sh. Nishith Jain and Sh. Abhinav Sarwan are present on behalf of the promoter. As per the legal opinion received from Ld. Advocate General, Haryana the late fees for registration of project has not been charged. However, in case any liability/demand on this account occurs in future, the applicant promoter shall be liable to pay the same on demand. Approved as proposed.
- Registration granted GGM/671/403/2023/15
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 25.087 acres |
|---|---|
| Total licensed area | 25.087 acres |
| Licence | 123 of 2012 (20.12.2012) |
| FAR permissible / proposed | 3.15 / 3.14204 |
| Estimated project cost | ₹ 5,418.03 Cr |
| Cost of land | ₹ 312.25 Cr |
| Cost of construction | ₹ 3,254.72 Cr |
| Infrastructure and other structures | ₹ 93.28 Cr |
| EDC, taxes, levies and other costs | ₹ 1,757.78 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 2.68 | 10.7% |
| Construction Of Roads | 4.89 | 19.5% |
| Parks And Playgrounds | 3.8 | 15.1% |
| Any Other | 11.06 | 44.1% |
| Areaundercommercialunits | 0.09 | 0.4% |
| Schools | 0.5 | 2% |
| Openparkingarea | 0.34 | 1.4% |
| EWS | 0.39 | 1.6% |
| Areaundertwentyfourmeterroad | 1.34 | 5.3% |
Apartments 1,155 units · 5 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 209.51 | 2,255 | 1137 |
| Apartment/Shops/Other Buildings | 21.01 | 226 | 14 |
| Apartment/Shops/Other Buildings | 12.51 | 135 | 2 |
| Apartment/Shops/Other Buildings | 17.57 | 189 | 2 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY | No |
| Water Supply | GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY | Yes |
| Electricity | DAKSHIN HARYANA BIJLI VITRAN NIGAM | Yes |
| Sewage Disposal | GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY | Yes |
| Storm Water Drainage | GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 5.21 Cr | As Per Project Report |
| Water Supply System | ₹ 6.09 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 1.55 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.48 Cr | As Per Project Report |
| Street Lighting | ₹ 45.82 lakh | As Per Project Report |
| Security And Fire Fighting | ₹ 34.99 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 1.27 Cr | As Per Project Report |
| Renewable Energy System | ₹ 35.7 lakh | As Per Project Report |
| Maintenance Charges And Surfacing Of Roads | ₹ 7.16 Cr | As Per Project Report |
| Stp | ₹ 1.54 Cr | As Per Project Report |
| Underground Water Tank | ₹ 91.39 lakh | As Per Project Report |
| Rain Water Harvesting | ₹ 57.12 lakh | As Per Project Report |
| Electrical Sub Station | ₹ 31.54 Cr | As Per Project Report |
| Plantation And Road Side Trees | ₹ 15.12 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Zoning Plan Approval | Already Been Obtained | 2 Jan 2023 |
| License Approval | Already Been Obtained | 20 Dec 2012 |
| Building Plan /Site Plan Approval | Already Been Obtained | 20 Jan 2023 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Tiles / Marble / Granite / Laminated Wood |
|---|---|
| Wall Finishing Details | Obd/ Semi-Acrylic / Acrylic Emulsion / Tiles |
| Kitchen Details | Modular Kitchen With Appliances As Per Point 6.6 In Unit Wise Specifications, Cabinetry And SS Sink |
| Bathroom Fittings | Cp Fittings, Wash Basin, Wc With Accessories |
| Doors And Windos Frames | Ms / Upvc / Al / Wood / Composite Material |
| Glass Work | Clear / Tinted / Coated / Frosted Glass As Per Point Number 13 |
| Conducting And Wiring Details | Pvc Conduits, Fr Wiring |
| Cupboard Details | Modular Wardrobes In Bedrooms |
| Water Storage | Oht & Ugt Water Tanks |
| Lift Details | Branded Make |
| External Glazings | Upvc / Aluminium |
| Windows/Glazings | Upvc / Aluminium |
| Doors | Wooden Flush Door |
| Main Doors | Wooden Fire Resistant Flush Door |
| Internal Doors | Wooden Flush Door |
| Air Conditioning | Vrv / Vrf With High Wall Units In Living, Dining, Bedrooms, Utility & Kitchen |
| Electrical Fittings | Switch Box And Sockets. Home Automation In Select Areas As Per Design |
| Cng Pipe Line | Gas Pipe Line Provision Only |
| Provision Of Wifi And Broadband Facility | Provision Only |
| External Finishing/Colour Scheme | Exterior Grade Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.