Whiteland Blissville
by Whiteland Corporation Private Limited · Sector- 76
- RERA registration
- GGM/598/330/2022/73
- Registered on
- 1 Aug 2022
- Valid till
- 30 Jun 2027
- Project ID
- RERA-GRG-1114-2022
- Land area
- 7.319 acres
- Plots
- 111
- Completion (as filed)
- 30 Jun 2027
- Estimated cost
- ₹ 118.92 Cr
RERA registration
| Registration certificate | GGM/598/330/2022/73, dated 1 Aug 2022 |
|---|---|
| Registration valid till | 30 Jun 2027 |
| Project ID | RERA-GRG-1114-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Whiteland Blissville |
| Promoter | Whiteland Corporation Private Limited |
| Promoter’s registered office | 10TH Floor, Worldmark Tower, 1, Maidawas, Sector - 65, Gurugram, Haryana 122001 |
| CIN | U70109HR2021PTC092905 |
| Site address | Sector- 76 |
| Sector | Sector 76 |
| Tehsil / District | Manesar / Gurugram |
| Layout plan approved | 12 Jul 2022 |
| Construction start (as filed) | 1 Jan 2023 |
| Completion (as filed) | 30 Jun 2027 |
| Application submitted | 19 Jul 2022 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter Not Dispatched To Ar
-
Hearing
Examination By Authority
Proceedings
Due to administrative work of the Authority, the matter is adjourned to 27.07.2022
-
Hearing
Adjournment
Proceedings
Proceedings dated 27.07.2022 Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Rachit Vohra (CRM) and Sh. Krishan Kumar (Director) are present on the behalf of the promoter. The AR of the promoter submits that they have applied for all clearances including submission of service plan and estimates which are under process with GMDA and seeks 2 weeks’ time for submission of the deficit documents. The AR further clarifies that the payment plan under the above project has not been submitted as no plot is proposed to be sold and floor-wise construction shall be undertaken after approval of building plans from the concerned authority. The promoter is advised to seek prior registration of floor-wise sale after approval of building plans and making a separate application. The matter to come up on 01.08.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Ms. Geeta Rathee Singh, Sr. Legal Officer and Neeraj Gautam (Associate Architectural Executive) briefed thefacts of the case.Sh. Sumit Chaudhary (Director), Sh. Krishan Kumar (Director), Sh. Rachit Vohra (CRM) and Sh. Rohit Shukla(Manager) are present on the behalf of the promoter.Keeping in view the above recommendation the Authority decides to grant registration with the conditionthat no sale of plots will be done and only sale of floors will be done for which separate registration will besought.
- Registration granted GGM/598/330/2022/73
-
Hearing
Objection
Proceedings
Proceedings dated 27.07.2022 Neeraj Gautam (Associate Architectural Executive) briefed the facts of the case. Sh. Rachit Vohra (CRM) and Sh. Krishan Kumar (Director) are present on the behalf of the promoter. The AR of the promoter submits that they have applied for all clearances including submission of service plan and estimates which are under process with GMDA and seeks 2 weeks’ time for submission of the deficit documents. The AR further clarifies that the payment plan under the above project has not been submitted as no plot is proposed to be sold and floor-wise construction shall be undertaken after approval of building plans from the concerned authority. The promoter is advised to seek prior registration of floor-wise sale after approval of building plans and making a separate application. The matter to come up on 01.08.2022.
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 7.319 acres |
|---|---|
| Total licensed area | 7.319 acres |
| Licence | 93 of 2022 Dated 12.07.2022 |
| FAR permissible / proposed | 100 / 100 |
| Estimated project cost | ₹ 118.92 Cr |
| Cost of land | ₹ 71.81 Cr |
| Infrastructure and other structures | ₹ 11.74 Cr |
| EDC, taxes, levies and other costs | ₹ 35.37 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Plots To Be Sold | 15,786.79 | 53.3% |
| Construction Of Roads | 7,156 | 24.2% |
| Parks And Playgrounds | 2,428.11 | 8.2% |
| Electricity Sub-Station | 99.96 | 0.3% |
| Area To Be Left For Transferring To The Government For Community Services | 2,962.3 | 10% |
| Any Other | 1,184.5679 | 4% |
Plots 111 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 15,786.79 | 18,881 | 169,927 | 111 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | NA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.18 Cr | Submitted To HUDA |
| Water Supply System | ₹ 1.15 Cr | Submitted To HUDA |
| Storm Water Drainage | ₹ 1.04 Cr | Submitted To HUDA |
| Sewage Treatment & Garbage Disposal | ₹ 1.54 Cr | Submitted To HUDA |
| Street Lighting | ₹ 16.85 lakh | Submitted To HUDA |
| Playgrounds And Parks | ₹ 3.11 lakh | Submitted To HUDA |
| Any Other | ₹ 1.17 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No. 93 Of 2022 | Already Been Obtained | 12 Jul 2022 |
| Layout Plan | Already Been Obtained | 12 Jul 2022 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.