Layout plan approved
9 Sep 2022
Building plans approved
9 Sep 2022
Construction start (as filed)
1 Oct 2022
Completion (as filed)
30 Sep 2024
Application submitted
22 Sep 2022
Authority, hearings & orders
Current statusExtension Certificate Uploaded
Initial scrutinyThe matter will be heard dated 03.10.2022
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
Notice sent to the promoterBy Hand
HearingExamination By AuthorityView order Proceedings
Proceedings dated: 03.10.2022 Ms. Deepika, Planning Executive briefed about the facts of the project. Sh. Kapil Bhardwaj (Liaison Officer) and Sh. Vipul Bhardwaj (Advocate) are present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. The matter to come up on 17.10.2022. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
Proceedings dated: 17.10.2022 Ms. Deepika, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Kapil Bhardwaj (Liaisoner) and Sh. Vipul Bhardwaj (Advocate) are present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Regarding the deficit fee, the AR of the promoter stated that the fee has been calculated on the basis of permissible component of commercial area which is upto 4% of the total area while proposed and approved by DTCP in the layout plan is only to the extent of 0.89 acres and remaining area of commercial component has been utilized towards residential/industrial use and hence the fee be calculated on the basis of the area allocated and approved by DTCP in the layout plan. The application for registration is in principally approved subject to submission of above deficit documents and fee if any. The matter to come up on 14.11.2022 (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Vijay Kumar Goyal) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Approved.
Registration grantedGGM/625/357/2022/100
Registration valid till
Land, licence & cost
Land area of the project
118.15 acres
Total licensed area
118.15 acres
Licence
License No. 136 of 2022 issued by DTCP Haryana, Chandigarh
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 869.09 Cr
Cost of land
₹ 387.5 Cr
Infrastructure and other structures
₹ 73.52 Cr
EDC, taxes, levies and other costs
₹ 408.07 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
72.168
61.1%
Construction Of Roads
23.628
20%
Green Belts
6.025
5.1%
Electricity Sub-Station
2.41
2%
Sewage And Solid Waste Treatment Facility
0.57
0.5%
Community
2.2416
1.9%
Anganwadi
0.0988
0.1%
Health
0.2471
0.2%
Skill
0.9884
0.8%
Sector
8.45
7.2%
Ud
1.33
1.1%
Plots 511 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
292,052.59
349,292
3,143,625
511
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HSVP
Yes
Storm Water Drainage
HSVP
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 21.46 Cr
As Per Project Report
Water Supply System
₹ 5.68 Cr
As Per Project Report
Storm Water Drainage
₹ 4.25 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 6.44 Cr
As Per Project Report
Street Lighting
₹ 4.53 Cr
As Per Project Report
Playgrounds And Parks
₹ 25.84 lakh
As Per Project Report
Any Other
₹ 30.51 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Non Encumbrance
Already Been Obtained
20 Dec 2021
Layout Plan
Already Been Obtained
9 Sep 2022
Forest
Already Been Obtained
29 Jun 2022
License No 136 Of 2022
Already Been Obtained
8 Sep 2022
Aravali Noc
Already Been Obtained
25 Aug 2022
Demarcation Cum Zoning Plan
Applied For But Yet To Receive
13 Sep 2022
Electricity Assurance
Applied For But Yet To Receive
8 Sep 2022
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about The Golden City?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.