SS Linden Residential Floors
by SS Group Private Limited · SS Linden, Sector-84
- RERA registration
- GGM/557/289/2022/32
- Registered on
- 2 May 2022
- Valid till
- 28 Feb 2025
- Project ID
- RERA-GRG-958-2021
- Land area
- 0.678 acres
- Apartments
- 44 in 11 towers
- Plots
- 11
- Completion (as filed)
- 29 Feb 2024
- Estimated cost
- ₹ 38.42 Cr
RERA registration
| Registration certificate | GGM/557/289/2022/32, dated 2 May 2022 |
|---|---|
| Registration valid till | 28 Feb 2025 |
| Project ID | RERA-GRG-958-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | SS Linden Residential Floors |
| Promoter | SS Group Private Limited |
| Promoter’s registered office | SS House, Plot No.-77, Sector-44, Gurugram-122003 |
| CIN | U70109HR2010PTC048739 |
| Site address | SS Linden, Sector-84 |
| Sector | Sector 84 |
| Tehsil / District | Manesar / Gurugram |
| Layout plan approved | 25 May 2021 |
| Building plans approved | 16 Sep 2021 |
| Construction start (as filed) | 1 Nov 2021 |
| Completion (as filed) | 29 Feb 2024 |
| Application submitted | 9 Nov 2021 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st deficiency notice
-
Hearing
Examination By Authority View order
Proceedings
Prachi Singh Planning Executive briefed the facts of the case through video conferencing. By the orders of the authority the promoter is directed to remove the deficit documents as mentioned above. The matter to come up on 07.02.2022.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 19.04.2022.
-
Hearing
Adjournment View order
Proceedings
Due to the administrative work of the authority, the matter is adjourned to 02.05.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Proceedings dated 02.05.2022Prachi Singh, Planning Executive briefed about the facts of the case.Sh. Ashok Jonapuria (Director)is present on behalf of the promoter.An application regarding registration of residential floors projects namely “SS Linden” situated at Sector-84 and85, Gurugram, Haryana being developed by M/s North Star Apartments Pvt. Ltd. now formerly known as (M/s SSGroup Private Limited.) was submitted on 11.01.2022 under section 4 of Real Estate (Regulation andDevelopment), Act 2016.This application for registration is a part of the residential plotted colony which falls under license no. 105 of2013 for area admeasuring 26.793 acres dated 16.12.2013 valid up to 10.12.2024 being issued in favour of M/sMatrix Buildwell Pvt. Ltd. and 7 others in collaboration of M/s North Star Apartments Pvt. Ltd. now formerlyknown as (M/s SS Group Private Limited.)The application submitted by the promoter for the said project contains 11 plots on which total of 44 units are tobe constructed.On scrutiny of the application, some of the major deficiencies/observations were observed which were conveyedto the promoter vide notice no. HARERA/GGM/RPIN/421 dated 19.01.2022. The promoter has submitted theTemp ID- RERA-GRG-PROJ-958-2021Project Name- SS Linden Floorsreply dated 28.01.2022, 08.02.2022, 21.02.2022, 25.03.2022 01.04.2022, 21.04.2022 and 02.05.2022 which werescrutinized and still the following deficiency is pending which is mentioned below: -1. Approvals for sewage disposal and storm water drainage need to be submitted.The Authority decided to grant registration as all prerequisites for registration of the project has beencompleted and an application for grant of permission for sewage disposal/storm water already stand appliedto the concerned authority. The promoter is directed to submit the same within 4 weeks.
- Registration granted GGM/557/289/2022/32
- Registration valid till
Land, licence & cost
| Land area of the project | 0.678 acres |
|---|---|
| Total licensed area | 29.928 acres |
| Licence | 105 of 2013 dated 11.12.2013 as modified by order dated 25.05.2021. |
| FAR permissible / proposed | 1.792 / 264 |
| Estimated project cost | ₹ 38.42 Cr |
| Cost of land | ₹ 7.69 Cr |
| Cost of construction | ₹ 23.95 Cr |
| EDC, taxes, levies and other costs | ₹ 6.78 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 2,747 | 100% |
Apartments 44 units · 11 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 6,083.00 | - | 44 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
Plots 11 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 250.00 | 299 | 2,691 | 11 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | No |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | No |
| Storm Water Drainage | GMDA | No |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Licence | Already Been Obtained | 25 May 2021 |
| Zoning Plan | Already Been Obtained | 1 Sep 2021 |
| Service Plan | Already Been Obtained | 1 Feb 2022 |
| Layout Plan | Already Been Obtained | 25 May 2021 |
| Electricity Load | Already Been Obtained | 13 Jan 2022 |
| Water Supply | Already Been Obtained | 14 Feb 2022 |
| Br-III (Building Plan) | Already Been Obtained | 16 Sep 2021 |
| Loi | Already Been Obtained | 20 Jun 2013 |
| License | Already Been Obtained | 11 Dec 2013 |
| Renewed License | Already Been Obtained | 22 Sep 2021 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Italian Marble Flooring, Vitrified, Anti-Skid Tile & Wooden Flooring |
|---|---|
| Wall Finishing Details | Acrylic Paint / Texture Paint |
| Kitchen Details | Modular Kitchen |
| Bathroom Fittings | Chinaware & Cp Fittings As Per Indian Standard Code |
| Doors And Windos Frames | Hardwood /Upvc Doors/ Window Frames |
| Glass Work | 12MM Thk. Toughened Glass / 5MM Thk. Plain Glass As Per Spec. |
| Electric Fittings | Modular Type As Per Is Code |
| Conducting And Wiring Details | Pvc Conduting / Copper Wiring As Per Is Code |
| Cupboard Details | 19MM Thk. Commercial Board With Mica Finish |
| Water Storage | 1000 Liter Water Storage Tank At Terrace Lvl Make Of Polyethylene Sheet |
| Lift Details | 01 No Lift With 06 Nos Passenger Capacity |
| External Glazings | Upvc/ Aluminum Frame |
| Windows/Glazings | Upvc/ Aluminum Frame |
| Doors | Solid Flush Door |
| Main Doors | Solid Flush Door |
| Internal Doors | Solid Flush Door |
| Air Conditioning | High Wall Units Of Branded Make |
| Electrical Fittings | Modular Type As Per Is Code |
| External Finishing/Colour Scheme | Textured Paint |
| Internal Finishing | Acrylic Emulsion Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about SS Linden Residential Floors?