Signature Global Park-III
by Signatureglobal Homes Private Limited · 1309 13TH Floor Dr. Gopal Das Bhawan 28 Barakhamba Road New Delhi 110001
- RERA registration
- GGM/427/159/2020/43
- Registered on
- 20 Nov 2020
- Valid till
- 30 Sep 2022
- Project ID
- RERA-GRG-728-2020
- Land area
- 10.556 acres
- Plots
- 188
- Completion (as filed)
- 30 Sep 2022
- Estimated cost
- ₹ 86.74 Cr
RERA registration
| Registration certificate | GGM/427/159/2020/43, dated 20 Nov 2020 |
|---|---|
| Registration valid till | 30 Sep 2022 |
| Project ID | RERA-GRG-728-2020 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Signature Global Park-III |
| Promoter | Signatureglobal Homes Private Limited |
| Promoter’s registered office | 1309 13TH Floor Dr Gopal Das Bhawan 28 Barakhamba Road New Delhi 110001 |
| CIN | U70100DL2008PTC176641 |
| Site address | 1309 13TH Floor Dr. Gopal Das Bhawan 28 Barakhamba Road New Delhi 110001 |
| Tehsil / District | Sohna / Gurugram |
| Layout plan approved | 6 Feb 2020 |
| Construction start (as filed) | 1 Sep 2019 |
| Completion (as filed) | 30 Sep 2022 |
| Application submitted | 18 Aug 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
-
Hearing
Examination By Authority
Proceedings
Sh. Anurag Srivastva, Authorised Representative of the promoter is present during online hearing. The Authority directed the promoter to submit the deficient document mentioned below: 1. The annexures in the online are not uploaded as well as the correction needs to be done in the online (A-H). 2. DPI not filled Properly. 3. Approved Service plan and Estimates needs to be submitted. 4. Latest Mutation and Jamabandi needs to be submitted. 5. List of sold and unsold inventory needs to be submitted. 6. Allotment letter is not as per the prescribed format. 7. Payment plan is not as per the prescribed format. 8. CA Certificate for the equity by the promoter needs to be provided. 9. Marketing cost mention in s.no 1.7 needs to be excluded from the total estimated cost as it is not a part of project cost. 10. Debenture trust deed needs to be provided. 11. Board resolution authorising the operating of bank account has not been in proper format. 12. Copy of Home loan tie up has not been provided. The Authority directed the promoter to explain clearly that in case loan is not paid by them what remedy will be available with the promoter. Next date of hearing is fixed for 22.09.2020
-
Hearing
Objection
Proceedings
The matter is fixed for 25.09.2020
-
Hearing
Objection
Proceedings
The matter is fixed for 29.09.2020
-
Hearing
Adjournment
Proceedings
The matter is adjourned and fixed for hearing on 06.10.2020.
-
Hearing
Adjournment
Proceedings
Mr. Anurag Srivastva (GM Legal) present on behalf of the promoter during the online hearing. The promoter has requested for the time to remove the below mentioned deficiencies. 1. The annexures in the online are not uploaded as well as the correction needs to be done in the online (A-H). 2. Approved Service plan and Estimates needs to be submitted. 3. List of sold and unsold inventory license wise needs to be submitted. 4. Allotment letter is not as per the prescribed format. 5. CA Certificate for the equity by the promoter needs to be provided. 6. Marketing cost mention in s.no 1.7 needs to be excluded from the total estimated cost as it is not a part of project cost. The Authority directed the promoter to remove the above mentioned deficiencies within the given time. The matter is fixed for 27.10.2020.
-
Hearing
Adjournment
Proceedings
The matter is adjourned for 17.11.2020.
-
Hearing
Adjournment
Proceedings
The matter is adjourned for 03.12.2020.
- Registration granted GGM/427/159/2020/43
-
Hearing
Adjournment
Proceedings
The Matter adjourned for 10.12.2020
-
Hearing
Adjournment
Proceedings
The Coram is not complete. The hearing is adjourned and matter is fixed for 23.12.2020
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Approved
- Certificate uploaded RC Approved and Certificate Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 10.556 acres |
|---|---|
| Total licensed area | 10.556 acres |
| Licence | 130 of 2019 dated 07/12/2019 and 40 of 2019 dated 01/03/2019 |
| FAR permissible / proposed | 1 / 1 |
| Estimated project cost | ₹ 86.74 Cr |
| Cost of land | ₹ 43.14 Cr |
| Infrastructure and other structures | ₹ 7.97 Cr |
| EDC, taxes, levies and other costs | ₹ 35.63 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 6.406 | 60.7% |
| Construction Of Roads | 1.716 | 16.3% |
| Parks And Playgrounds | 0.792 | 7.5% |
| Electricity Sub-Station | 0.055 | 0.5% |
| Sewage And Solid Waste Treatment Facility | 0.111 | 1.1% |
| Area To Be Left For Transferring To The Government For Community Services | 1.056 | 10% |
| Any Other | 0.42 | 4% |
Plots 188 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 61.13 | 73 | 658 | 1 |
| 61.62 | 74 | 663 | 1 |
| 78.75 | 94 | 848 | 6 |
| 93.80 | 112 | 1,010 | 12 |
| 93.80 | 112 | 1,010 | 10 |
| 93.80 | 112 | 1,010 | 2 |
| 93.80 | 112 | 1,010 | 20 |
| 93.80 | 112 | 1,010 | 30 |
| 98.15 | 117 | 1,056 | 12 |
| 98.15 | 117 | 1,056 | 15 |
| 98.15 | 117 | 1,056 | 8 |
| 101.17 | 121 | 1,089 | 14 |
| 113.57 | 136 | 1,222 | 3 |
| 113.57 | 136 | 1,222 | 4 |
| 113.57 | 136 | 1,222 | 3 |
| 129.98 | 155 | 1,399 | 20 |
| 129.98 | 155 | 1,399 | 20 |
| 149.99 | 179 | 1,614 | 7 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | NHAI | No |
| Water Supply | HSVP | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HSVP | Yes |
| Storm Water Drainage | No | STP |
| HSVP | No | 4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report: |
| Sr. No. | Name of the facility | Estimated cost (In Lakhs)(Within the project area only) |
| Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) | 1 | INTERNAL ROADS AND PAVEMENTS |
| 200.20 | SUBMITTED TO HUDA | 2 |
| Water Supply System | 188.16 | SUBMITTED TO HUDA |
| 3 | STORM WATER DRAINAGE | 83.53 |
| Submitted To HUDA | 4 | ELECTRICITY SUPPLY SYSTEM |
| 0 | SUBMITTED TO HUDA | 5 |
| Sewage Treatment & Garbage Disposal | 118.23 | SUBMITTED TO HUDA |
| 6 | STREET LIGHTING | 24.29 |
| Submitted To HUDA | 7 | SECURITY AND FIRE FIGHTING |
| 0 | SUBMITTED TO HUDA | 8 |
| Playgrounds And Parks | 15.27 | SUBMITTED TO HUDA |
| 9 | CLUB HOUSE/COMMUNITY CENTRE | 0 |
| Submitted To HUDA | 10 | SHOPPING AREA |
| 0 | SUBMITTED TO HUDA | 11 |
| Renewable Energy System | 0 | SUBMITTED TO HUDA |
| 12 | SCHOOL | 0 |
| Submitted To HUDA | 13 | HOSPITAL/DISPENSARY |
| 0 | SUBMITTED TO HUDA | 14 |
| Any Other | 167.13 | SUBMITTED TO HUDA |
| 5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed. | 06-02-2020 | (date) |
| 6. Date of approval of Building Plans | NA | (date) |
| 7. New projects: | i) Likely date of starting the construction work | 01-09-2019 |
| ii) Likely date of completing the project | 30-09-2022 | iii) Sizes of the plots to be offered in the project |
| Sr. No | Plot Area(In Square Meter) | Number of plots in the project |
| 1 | 149.99 | 7 |
| 2 | 129.98 | 20 |
| 3 | 129.98 | 20 |
| 4 | 113.57 | 3 |
| 5 | 113.57 | 4 |
| 6 | 113.57 | 3 |
| 7 | 93.80 | 12 |
| 8 | 93.80 | 10 |
| 9 | 93.80 | 2 |
| 10 | 93.80 | 20 |
| 11 | 93.80 | 30 |
| 12 | 101.17 | 14 |
| 13 | 98.15 | 12 |
| 14 | 98.15 | 15 |
| 15 | 98.15 | 8 |
| 16 | 78.75 | 6 |
| 17 | 61.62 | 1 |
| 18 | 61.13 | 1 |
| Total | 188 | iv. Type of apartments to be constructed in the project: |
| Type | Carpet area(In Square Meter) | Number of apartments |
| Number of towers | Apartment/Shops/Other Buildings | 0 |
| 0 | 0 | (vi) Quarterly schedule of development of whole/remaining part of the project: |
| (c) Apartments/Shops/Other Buildings | Expenditure incurred till the date of application (In Lakhs) | Particulars |
| Expenditure | Apartments | 0 |
| Shops | 0 | Plots |
| 0 | External Development Charges | 278.87 |
| Infrastructure Development Work | 77 | Internal Development Works |
| 351.4 | Land Cost | 3278.77 |
| Other Costs | 1180 | Expenditure to be made in each quarter (In Lakhs) |
| Particulars | Year-2020 | Jan-Mar |
| Apr-June | July-Sep | Oct-Dec |
| Apartments | 0 | 0 |
| Shops | 0 | 0 |
| Plots | 0 | 0 |
| Cost of Construction of Community Facilities | 0 | 0 |
| Cost of Construction of Floors | 0 | 0 |
| Internal Development Works | 53.62 | 47.80 |
| Infrastructure Development Charges | 52.40 | 0 |
| External Development Charges | 157.03 | 0 |
| Land Cost | 95.50 | 86.20 |
| Other Cost | 265 | 95 |
| Particulars | Year-2021 | Jan-Mar |
| Apr-June | July-Sep | Oct-Dec |
| Apartments | 0 | 0 |
| 0 | 0 | Shops |
| 0 | 0 | 0 |
| 0 | Plots | 0 |
| 0 | 0 | 0 |
| Other Cost | 70 | 80 |
| 130 | 130 | Cost of Construction of Community Facilities |
| 0 | 0 | 0 |
| 0 | Cost of Construction of Floors | 0 |
| 0 | 0 | 0 |
| Internal Development Works | 25 | 55.37 |
| 263.63 | 0 | Infrastructure Development Charges |
| 0 | 0 | 0 |
| 0 | External Development Charges | 154.51 |
| 0 | 152 | 0 |
| Land Cost | 102.83 | 95 |
| 98.30 | 158.45 | Particulars |
| Year-2022 | Jan-Mar | Apr-June |
| July-Sep | Oct-Dec | Apartments |
| 0 | 0 | 0 |
| Shops | 0 | 0 |
| 0 | Plots | 0 |
| 0 | 0 | Other Cost |
| 200 | 200 | 200 |
| External Development Charges | 49.48 | 0 |
| 46.96 | Land Cost | 140.80 |
| 147.78 | 110.81 | Particulars |
| Year-2023 | Jan-Mar | Apr-June |
| July-Sep | Oct-Dec | Apartments |
| 0 | 0 | 0 |
| 0 | Shops | 0 |
| 0 | 0 | 0 |
| Plots | 0 | 0 |
| 0 | 0 | External Development Works |
| 44.45 | 0 | 0 |
| 0 | (d) Infrastructure | Expenditure incurred till the date of application (In Lakhs) |
| Particulars | Expenditure | Roads & Pavements |
| 110.4 | Water Supply System | 97.3 |
| Sewerage treatment & garbage disposal | 68.7 | Electricity Supply System |
| 0 | Storm Water Drainage | 52.9 |
| Parks and Playgrounds | 3 | Clubhouse/community centres |
| 0 | Shopping area | 0 |
| Other | 0 | Street Light |
| 19.1 | Expenditure to be made in each quarter (In Lakhs) | Particulars |
| Year-2019 | Jan-Mar | Apr-June |
| July-Sep | Oct-Dec | Roads & Pavements |
| 0 | 0 | Water Supply System |
| 0 | 0 | Sewerage treatment & garbage disposal |
| 0 | 0 | Electricity Supply System |
| 0 | 0 | Storm Water Drainage |
| 0 | 0 | Parks and Playgrounds |
| 0 | 0 | Clubhouse/community centres |
| 0 | 0 | Shopping area |
| 0 | 0 | Other |
| 0 | 0 | Street Light |
| 0 | 0 | Particulars |
| Year-2020 | Jan-Mar | Apr-June |
| July-Sep | Oct-Dec | Roads & Pavements |
| 0 | 0 | 0 |
| 0 | Water Supply System | 0 |
| 0 | 0 | 0 |
| Sewerage treatment & garbage disposal | 0 | 0 |
| 0 | 0 | Electricity Supply System |
| 0 | 0 | 0 |
| 0 | Storm Water Drainage | 0 |
| 0 | 0 | 0 |
| Parks and Playgrounds | 0 | 0 |
| 0 | 0 | Clubhouse/community centres |
| 0 | 0 | 0 |
| 0 | Shopping area | 0 |
| 0 | 0 | 0 |
| Other | 0 | 0 |
| 0 | 0 | Street Light |
| 0 | 0 | 0 |
| 0 | Particulars | Year-2021 |
| Jan-Mar | Apr-June | July-Sep |
| Oct-Dec | Roads & Pavements | 20 |
| 14.8 | 0 | Water Supply System |
| 5 | 20 | 25.86 |
| Sewerage treatment & garbage disposal | 0 | 5 |
| 43.23 | Electricity Supply System | 0 |
| 0 | 0 | Storm Water Drainage |
| 0 | 15 | 0 |
| Parks and Playgrounds | 0 | 0.57 |
| 11.2 | Clubhouse/community centres | 0 |
| 0 | 0 | Shopping area |
| 0 | 0 | 0 |
| Other | 0 | 0 |
| 0 | Street Light | 0.57 |
| It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented. | Signature of the Applicant / Authorised Representative | Stamp _____________ |
| Date _____________ | FORM REP-I | Part - D |
| Accounts related information: | 1. Annex copy of the balance sheet of last 3 years | Yes |
| 2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D. | Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form. | No |
| 3. Bank account to which the deposits received from apartment buyers will be credited | Bank and Branch address | YES BANK LIMITED, GROUND AND MEZZANINE FLOOR, , 56, JANPATH, ALPS BLDG, , NEXT TO PIZZA HUT, CONNAUGHT PLACE, DELHI-110001 |
| Bank Account number | 013672400000088 | IFSC code |
| YESB0000136 | MICR code | 110532031 |
| Branch code | 0136 | 4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority) |
| Pradeep Kumar Aggarwal and Ravi Aggarwal, | Address: 34 , Road No. 61, West Punjabi Bagh, Delhi-110026 | 5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details) |
| Attached | I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| Form Rep-I | Part - E | Details of the statutory approvals: |
| 1. Annex copies of the following in Folder E: | i. Lay out Plan | Yes |
| ii. Demarcation Plan | Yes | iii. Zoning Plan |
| Yes | iv. Building Plan | No |
| Site Plan | No | Floor Plan |
| No | Apartment Plans | No |
| Elevation Section | No | Detail of Permissible FAR |
| No | Detail of covered area achieved FAR | No |
| 2. Annex copies of the following in Folder E: | I. ROADS AND PAVEMENT PLAN | Yes |
| II. Electricity Supply Plan | No | III. WATER SUPPLY PLAN |
| Yes | IV. SEWERAGE AND GARBAGE DISPOSAL PLAN | Yes |
| V. Strom Water Drainage | Yes | VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY |
| No | VII. STREET LIGHTING PLAN | No |
| Viii. Parking Plan | No | 3. Statutory Approvals Status |
| Statutory Approvals | Statutory Approvals Status | Date |
| I. License No. 130 Of 2019 | ALREADY BEEN OBTAINED | 07-12-2019 |
| II. Water Supply Memo NO.6510 | ALREADY BEEN OBTAINED | 10-01-2020 |
| III. Sewage Disposal Memo No. 6507 | ALREADY BEEN OBTAINED | 10-01-2020 |
| IV. Memo No.ch-56/Drg-26B | ALREADY BEEN OBTAINED | 15-01-2020 |
| It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees. | Signature _____________ | Seal _____________ |
| Date _____________ | FORM REP-I | Part - F |
| 1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers. | (Annex a copy in Folder F) | Yes |
| 2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules) | (Annex a copy in Folder F) | Yes |
| 3. Gist of the important provisions of the Draft Agreement | (Annex a copy in Folder F) | Yes |
| I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. | Signature of the Applicant / Authorised Representative |
| Stamp _____________ | Date _____________ | FORM REP-I |
| Part - G | Projects launched by the promoter in last five years: (No Projects) | I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| Form Rep-I | Part - H | SPECIFICATION OF CONSTRUCTION |
| Specification of apartments and other buildings including the following: | 1 | FLOORING DETAILS OF VARIOUS PARTS OF HOUSE |
| Na | 2 | WALL FINISHING DETAILS |
| Na | 3 | KITCHEN DETAILS |
| Na | 4 | BATHROOM FITTINGS |
| Na | 5 | WOOD WORK ETC |
| Na | 6 | DOORS AND WINDOS FRAMES |
| Na | 7 | GLASS WORK |
| Na | 8 | ELECTRIC FITTINGS |
| Na | 9 | CONDUCTING AND WIRING DETAILS |
| Na | 10 | CUPBOARD DETAILS |
| Na | 11 | WATER STORAGE |
| Na | 12 | LIFT DETAILS |
| Na | 13 | EXTERNAL GLAZINGS |
| Na | 13.1 | WINDOWS/GLAZINGS |
| Na | 14 | DOORS |
| Na | 14.1 | MAIN DOORS |
| Na | 14.2 | INTERNAL DOORS |
| Na | 15 | AIR CONDITIONING |
| Na | 16 | ELECTRICAL FITTINGS |
| Na | 17 | CNG PIPE LINE |
| Na | 18 | PROVISION OF WIFI AND BROADBAND FACILITY |
| Na | 19 | EXTERNAL FINISHING/COLOUR SCHEME |
| Na | 20 | INTERNAL FINISHING |
| Na | SPECIFICATION UNIT WISE | 1 . LIVING/DINING/FOYER/FAMILY LOUNGE |
| 1 . 1 | FLOOR | NA |
| 1 . 2 | WALLS | NA |
| 1 . 3 | CEILING | NA |
| 2 . Master Bedroom/Dressroom | 2 . 1 | FLOOR |
| Na | 2 . 2 | WALLS |
| Na | 2 . 3 | CEILING |
| Na | 2 . 4 | MODULAR WARDROBES |
| Na | 3 . MASTER TOILET | 3 . 1 |
| Floor | NA | 3 . 2 |
| Walls | NA | 3 . 3 |
| Ceiling | NA | 3 . 4 |
| Counters | NA | 3 . 5 |
| Sanitary Ware/Cp Fittings | NA | 3 . 6 |
| Fitting/Fixtures | NA | 4 . BED ROOMS |
| 4 . 1 | FLOOR | NA |
| 4 . 2 | WALLS | NA |
| 4 . 3 | CEILING | NA |
| 4 . 4 | WARDROBES | NA |
| 5 . Toilet | 5 . 1 | FLOOR |
| Na | 5 . 2 | WALLS |
| Na | 5 . 3 | CEILING |
| Na | 5 . 4 | COUNTERS |
| Na | 5 . 5 | SANITARY WARE/CP FITTINGS |
| Na | 5 . 6 | FIXTURES |
| Na | 6 . KITCHEN | 6 . 1 |
| Floor | NA | 6 . 2 |
| Walls | NA | 6 . 3 |
| Ceiling | NA | 6 . 4 |
| Counters | NA | 6 . 5 |
| Fixtures | NA | 6 . 6 |
| Kitchen Appliances | NA | 7 . UTILITY ROOMS/UTILITY BALCONY/TOILET |
| 7 . 1 | FLOOR | NA |
| 7 . 2 | WALLS & CEILING | NA |
| 7 . 3 | TOILET | NA |
| 7 . 4 | BALCONY | NA |
| 8 . Sit-Outs | 8 . 1 | FLOOR |
| Na | 8 . 2 | WALLS & CEILING |
| Na | 8 . 3 | RAILINGS |
| Na | 8 . 4 | FIXTURES |
| Na | I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| List of Uploaded Documents | Sr. No. | Document Description |
| Date of Document Upload | View Document | 1 |
| Demarcation Plan | 12-11-2020 | View Document |
| 2 | ZONING SITE 3 EXTEN 13.08.20 | 12-11-2020 |
| View Document | 3 | DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. |
| 12-11-2020 | View Document | 4 |
| Pl-Water Supply Layout Plan Sg Park 3 10.55 18.11.20 | 24-11-2020 | View Document |
| 5 | NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT | 12-11-2020 |
| View Document | 6 | SUPERIMPOSED LAYOUT PARK 3 1055 |
| 12-11-2020 | View Document | 7 |
| Equity Certificate Sg Park 3 10.55625ACRES. | 18-11-2020 | View Document |
| 8 | DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD | 18-11-2020 |
| View Document | 9 | FF-ROAD LAYOUT SG PARK 3 10.55 18.11.20 |
| 18-11-2020 | View Document | 10 |
| Pl-Domestic Layout Plan 18.11.20 | 18-11-2020 | View Document |
| 11 | PL-SEWERAGE (H.S.E.M) SG PARK 3.55 18.11.20 | 18-11-2020 |
| View Document | 12 | ASSURANCE SEWERAGE(SITE-3) FINAL |
| 12-11-2020 | View Document | 13 |
| Br For Account Park 3EXTENSION | 12-11-2020 | View Document |
| 14 | PL-FLUSHING & IRRIGATION LAYOUT PLAN SG PARK 3 10.55 18.11.20 | 18-11-2020 |
| View Document | 15 | COLLABORATION AGREEMENT STERNAL AND HOMES PARK 3 EXTENSION |
| 12-11-2020 | View Document | 16 |
| Ec Park 3 10.55 | 12-11-2020 | View Document |
| 17 | EDC SCHEDULE 4.2625 | 12-11-2020 |
| View Document | 18 | SALE DEED 26.11 ACRES |
| 12-11-2020 | View Document | 19 |
| Fire Scheme Park 3 Extn | 12-11-2020 | View Document |
| 20 | FORM INC-22 SIGNED (4) | 12-11-2020 |
| View Document | 21 | ASSURANCE WATER SUPPLY(SITE-3)-ADD |
| 12-11-2020 | View Document | 22 |
| Licence-130 0F 2019 | 12-11-2020 | View Document |
| 23 | LICENSE 40 OF 2019 SECTOR-36 ACRES6.29375 SGHPL | 12-11-2020 |
| View Document | 24 | ASSURANCE STP(SITE3 ADDITIONAL) |
| 12-11-2020 | View Document | 25 |
| Sternal Park 3 Extn Sale Deed & Collaboration | 12-11-2020 | View Document |
| 26 | BANK UNDERTAKING PARK III | 12-11-2020 |
| View Document | 27 | ZONING LETTER SITE 3 (1) |
| 12-11-2020 | View Document | 28 |
| Layout Plan Park 3 Extension Revise Site Layout Plan | 12-11-2020 | View Document |
| 29 | MUTATION 21.9.20 | 12-11-2020 |
| View Document | 30 | LAYOUT LETTER PARK 3 EXTN |
| 12-11-2020 | View Document | 31 |
| Receiving(Power Assurance)-SITE3 Extension | 12-11-2020 | View Document |
| 32 | CASH FLOW STATEMENT OF THE PROPOSED PROJECT | 24-11-2020 |
| View Document | 33 | PL-DRAINAGE LAYOUT SG PARK 3 10.55 18.11.20 |
| 18-11-2020 | View Document | 34 |
| In Case Of Plotted Colony, The Latest Layout Plan | 18-08-2020 | View Document |
| 35 | IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN | 18-08-2020 |
| View Document | 36 | COPY OF LICENSE ALONG WITH SCHEDULE OF LAND |
| 18-08-2020 | View Document | I hereby declare that the above information and particulars are based on record and are true to the |
| best of my knowledge and belief and nothing has been concealed. | Signature of the Applicant / Authorised Representative | Stamp _____________ |
| Date _____________ | Documents Uploaded After Registration | Sr. No. |
| Document Description | Date of Document Upload | View Document |
| 1 | Completion Certificate | 28-07-2023 |
| View Document | I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2 Cr | Submitted To HUDA |
| Water Supply System | ₹ 1.88 Cr | Submitted To HUDA |
| Storm Water Drainage | ₹ 83.53 lakh | Submitted To HUDA |
| Sewage Treatment & Garbage Disposal | ₹ 1.18 Cr | Submitted To HUDA |
| Street Lighting | ₹ 24.29 lakh | Submitted To HUDA |
| Playgrounds And Parks | ₹ 15.27 lakh | Submitted To HUDA |
| Any Other | ₹ 1.67 Cr | Submitted To HUDA |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No. 130 Of 2019 | Already Been Obtained | 7 Dec 2019 |
| Water Supply Memo NO.6510 | Already Been Obtained | 10 Jan 2020 |
| Sewage Disposal Memo No. 6507 | Already Been Obtained | 10 Jan 2020 |
| Memo No.ch-56/Drg-26B | Already Been Obtained | 15 Jan 2020 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.