Royal Heritage
by Pivotal Infrastructure Pvt Ltd · Sector-70 Village Mujheri
- RERA registration
- HRERA-PKL-FBD-47-2018 Lapsed Project
- Valid till
- 31 Dec 2020
- Project ID
- RERA-PKL-636-2019
- Land area
- 20.313 acres
- Estimated cost
- ₹ 539.18 Cr
RERA registration
| Registration certificate | HRERA-PKL-FBD-47-2018 Lapsed Project |
|---|---|
| Registration valid till | 31 Dec 2020 |
| Project ID | RERA-PKL-636-2019 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Royal Heritage |
| Promoter | M/S Pivotal Infrastructure Pvt. Ltd. |
| Promoter’s registered office | 704-705, Jmd Pacific Square, Sector 15 Part-II, Gurugram |
| CIN | U70109HR2006PTC038348 |
| Site address | Sector-70 Village Mujheri |
| Sector | Sector 70 |
| Tehsil / District | Ballabgarh / Faridabad |
| Layout plan approved | 27 Aug 2012 |
| Building plans approved | 27 Aug 2012 |
| Application submitted | 8 Nov 2019 |
Authority, hearings & orders
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 05.06.2018.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 19.06.2018.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 29.08.2018.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Registration Certificate to be issued.
- Application submitted online
- Application received by HRERA Panchkula
- Registration valid till
Land, licence & cost
| Land area of the project | 20.313 acres |
|---|---|
| Total licensed area | 20.313 acres |
| Licence | 78 of 2009 |
| FAR permissible / proposed | 139451.42 / 1.75 |
| Estimated project cost | ₹ 539.18 Cr |
| Cost of land | ₹ 39.44 Cr |
| Cost of construction | ₹ 388.36 Cr |
| Infrastructure and other structures | ₹ 65.04 Cr |
| EDC, taxes, levies and other costs | ₹ 46.34 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 6,333.24 | 7.7% |
| Construction Of Roads | 34,562 | 42% |
| Parks And Playgrounds | 13,371.44 | 16.3% |
| Green Belts | 5,000 | 6.1% |
| Vehicle Parkings | 14,418 | 17.5% |
| Electricity Sub-Station | 872 | 1.1% |
| Club House | 1,114 | 1.4% |
| Sewage And Solid Waste Treatment Facility | 400 | 0.5% |
| Any Other | 665 | 0.8% |
| Nursary And Primary School | 4,800 | 5.8% |
| Swimming Pool And Deck | 665 | 0.8% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | Yes |
| Water Supply | HUDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HUDA | Yes |
| Storm Water Drainage | HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 4.71 Cr | Submitted To Town & Country Planning |
| Water Supply System | ₹ 83 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 75 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 12.91 Cr | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 83 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 1.23 Cr | Submitted To Town & Country Planning |
| Security And Fire Fighting | ₹ 1.38 Cr | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 68 lakh | Submitted To Town & Country Planning |
| Club House/Community Centre | ₹ 35 lakh | Submitted To Town & Country Planning |
| Shopping Area | ₹ 29 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Environment Clearance | Already Been Obtained | 8 May 2008 |
| Aai | Already Been Obtained | 13 Jun 2012 |
| Fire Scheme Approval | Already Been Obtained | 7 May 2018 |
| Building Plan Approval | Already Been Obtained | |
| Service Plan And Estimates | Already Been Obtained | 3 Feb 2017 |
| Electricity Load Availability | Already Been Obtained | 28 Jul 2017 |
| Forest Noc | Already Been Obtained | |
| Construction Noc | Already Been Obtained | |
| Water Noc | Already Been Obtained | 15 Jan 2014 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tiles, Wooden Tiles, Ceramic Tiles |
|---|---|
| Wall Finishing Details | Oil Bound Distemper, Glazed Tiles In Toilet |
| Kitchen Details | Floor: Ceramic Tiles, Above Counter 2-0 Glazed Tiles, Rest Oil Bound Distemper, Counter: Marble/Granite |
| Bathroom Fittings | Floor: Ceramic Tiles, Walls: Glazed Tiles, Ceiling: Oil Bound Distemper, Fittings/Fixtures: Angle Valve/Basin Mixture/Wall Mixture,Shower. |
| Wood Work Etc | Door: Mirandi Wood |
| Doors And Windos Frames | Door: Mirandi Wood 2 2/1"*5", Window:Pvc |
| Glass Work | %Mm Toughened Glass |
| Electric Fittings | Modular Switches |
| Conducting And Wiring Details | Conduit: 25MM, Wire: 1.5MM/2.5MM/4MM |
| Cupboard Details | Wooden Finish With High Gloss Mica |
| Water Storage | All Towers Have Oht & Ugt |
| Lift Details | 2 Lifts In Each Tower |
| External Glazings | Upvc |
| Windows/Glazings | Upvc |
| Doors | Flush Door |
| Main Doors | Flush Door |
| Internal Doors | Flush Door |
| Air Conditioning | One Ac In Master Bedroom Of Luxury Flat |
| Provision Of Wifi And Broadband Facility | Provision Only |
| External Finishing/Colour Scheme | Wether Shield, Cravet Work 20YY74/121 |
| Internal Finishing | Oil Bound Distemper |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.