4-7B, Ground Floor, Tolstoy House, Tolstoy Marg, New Delhi-110001
CIN
U45201DL1971PTC005522
Site address
Sector 89, Faridabad
Sector
Sector 89
Tehsil / District
Faridabad / Faridabad
Layout plan approved
14 Sep 2020
Building plans approved
14 Sep 2020
Construction start (as filed)
14 Sep 2020
Completion (as filed)
19 Feb 2021
Application submitted
19 Feb 2021
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing.
Next hearingNot Required
Registration valid till
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Registration Certificate to be issued.
Land, licence & cost
Land area of the project
14.588 acres
Total licensed area
14.588 acres
Licence
25 of 2020
Estimated project cost
₹ 79.04 Cr
Cost of land
₹ 51.03 Cr
Infrastructure and other structures
₹ 10.82 Cr
EDC, taxes, levies and other costs
₹ 17.19 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
33,769.37
57.2%
Construction Of Roads
11,596.923
19.6%
Parks And Playgrounds
4,448.38
7.5%
Electricity Sub-Station
226.66
0.4%
Sewage And Solid Waste Treatment Facility
456.769
0.8%
Area To Be Left For Transferring To The Government For Community Services
5,904.808
10%
Ugt
239.16
0.4%
Scos
2,363.853
4%
Mb
27.5
0%
Plots 274 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
27.50
33
296
1
71.12
85
766
1
73.75
88
794
6
84.60
101
911
1
91.08
109
980
1
97.56
117
1,050
1
104.01
124
1,120
1
110.46
132
1,189
1
113.22
135
1,219
14
113.88
136
1,226
1
116.94
140
1,259
1
117.36
140
1,263
18
118.62
142
1,277
1
123.42
148
1,328
1
124.55
149
1,341
11
125.94
151
1,356
26
125.94
151
1,356
24
129.90
155
1,398
1
131.47
157
1,415
40
132.26
158
1,424
1
132.66
159
1,428
22
136.38
163
1,468
1
137.40
164
1,479
1
138.00
165
1,485
39
144.00
172
1,550
20
144.90
173
1,560
1
145.60
174
1,567
4
145.80
174
1,569
17
149.99
179
1,614
5
168.47
201
1,813
2
179.69
215
1,934
2
181.69
217
1,956
1
186.46
223
2,007
1
193.42
231
2,082
1
196.95
236
2,120
5
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
Yes
Electricity
DHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.43 Cr
As Per Project Report
Water Supply System
₹ 2.06 Cr
As Per Project Report
Storm Water Drainage
₹ 99.4 lakh
As Per Project Report
Electricity Supply System
₹ 2.58 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 1.37 Cr
As Per Project Report
Street Lighting
₹ 56 lakh
As Per Project Report
Playgrounds And Parks
₹ 7.5 lakh
As Per Project Report
Shopping Area
₹ 75 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Licence No. 25 Of 2020
Already Been Obtained
14 Sep 2020
Approval Of Service Plan Estimates
Already Been Obtained
19 Feb 2021
Zoning Plan Approval
Already Been Obtained
17 Dec 2020
Cte
Already Been Obtained
30 Oct 2020
Sld Approval
Already Been Obtained
21 Dec 2020
Approval For Change In Beneficial Interest
Already Been Obtained
14 Jan 2021
Completion Certificate
Applied For But Yet To Receive
18 Feb 2021
Electricity Approval
Applied For But Yet To Receive
5 Nov 2020
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Puri Kohinoor?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.