Parsvnath City Rohtak
by Parsvnath Developers Limited · Sector-33 & 33A, Near Imt Industrial Area, Delhi Bypass Road, Rohtak, Haryana.
- RERA registration
- Applied, not granted yet
- Applied on
- 7 Mar 2019
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-83-2018
- Land area
- 104.038 acres
- Estimated cost
- ₹ 275.77 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-83-2018 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Parsvnath City Rohtak |
| Promoter | Parsvnath Developers Limited |
| Promoter’s registered office | Parsvnath Tower, Near Shahdara Mtero Station, Shahdara, Delhi - 110032 |
| CIN | L45201DL1990PLC040945 |
| Site address | Sector-33 & 33A, Near Imt Industrial Area, Delhi Bypass Road, Rohtak, Haryana. |
| Sector | Sector 33 |
| Tehsil / District | Rohtak / Rohtak |
| Layout plan approved | 16 Apr 2010 |
| Application submitted | 7 Mar 2019 |
Authority, hearings & orders
- Hearing Examination By Authority View order
- Hearing Adjournment View order
- Hearing Adjournment View order
- Hearing Adjournment View order
- Application received by HRERA Panchkula
- Application submitted online
-
Hearing
Adjournment View order
Proceedings
Adjourned to 08.04.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 29.04.2019
-
Hearing
Adjournment View order
Proceedings
Adjourned to 03.06.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 24.06.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 15.07.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 5.08.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 26.08.2019
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 30.09.2019
-
Hearing
Adjournment View order
Proceedings
Adjourned to 04.11.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 06.11.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 18.11.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 23.12.2019.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 03.02.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 02.03.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 04.05.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 01.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 24.08.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.10.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.11.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 14.12.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 04.01.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 15.03.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.03.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 19.04.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 21.06.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 22.06.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 23.08.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 20.09.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 11.10.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 27.12.2021.
-
Hearing
Adjournment View order
Proceedings
Postponed to 05.01.2022.
-
Hearing
Adjournment View order
Proceedings
Postponed to 10.01.2022.
-
Hearing
Withdrawn/Rejected View order
Proceedings
Revised application filed bearing Temp Id 971-2021
Land, licence & cost
| Land area of the project | 104.038 acres |
|---|---|
| Total licensed area | 104.038 acres |
| Licence | 36 of 2010(06-05-2014) |
| Estimated project cost | ₹ 275.77 Cr |
| Cost of land | ₹ 96.88 Cr |
| Infrastructure and other structures | ₹ 42.26 Cr |
| EDC, taxes, levies and other costs | ₹ 136.63 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 49.565 | 47.6% |
| Construction Of Roads | 28.026 | 26.9% |
| Parks And Playgrounds | 7.368 | 7.1% |
| Green Belts | 0.8 | 0.8% |
| Electricity Sub-Station | 0.484 | 0.5% |
| Sewage And Solid Waste Treatment Facility | 1.83 | 1.8% |
| Area To Be Left For Transferring To The Government For Community Services | 2 | 1.9% |
| Any Other | 13.965 | 13.4% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HUDA | No |
| Electricity | UHBVN | No |
| Sewage Disposal | HUDA | No |
| Storm Water Drainage | HUDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 15.23 Cr | As Per Project Report |
| Water Supply System | ₹ 4.73 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 2.35 Cr | As Per Project Report |
| Electricity Supply System | ₹ 11.85 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 4.45 Cr | As Per Project Report |
| Street Lighting | ₹ 1.19 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 2.45 Cr | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Environmental Clearance | Already Been Obtained | 9 Nov 2010 |
| Consent To Establish | Already Been Obtained | 17 Jun 2014 |
| Forest Noc | Already Been Obtained | 3 Jun 2011 |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.