M3M Soulitude 2
by Aawam Residency Private Limited · Sector 89, Gurugram
- RERA registration
- Applied, not granted yet
- Applied on
- 27 Sep 2024
- Application status
- Approved And Ready For Certificate Issuing Process
- Project ID
- RERA-GRG-1741-2024
- Land area
- 6.88 acres
- Estimated cost
- ₹ 575.94 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-1741-2024 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | M3M Soulitude 2 |
| Promoter | Aawam Residency Private Limited |
| Promoter’s registered office | 41ST Floor, Tower-1, M3M International Financial Center, Sector-66, Badshahpur, Gurgaon, Badshahpur, Haryana, India, 122101 |
| CIN | U70109HR2020PTC091883 |
| Site address | Sector 89, Gurugram |
| Sector | Sector 89 |
| Tehsil / District | Harsaru St / Gurugram |
| Layout plan approved | 27 Jul 2022 |
| Building plans approved | 24 Sep 2024 |
| Application submitted | 27 Sep 2024 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
The matter is adjourned and to come up on 28.10.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 11.11.2024.
-
Hearing
Adjournment
Proceedings
The matter is adjourned and to come up on 09.12.2024.
-
Hearing
Adjournment
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma (AR) are present on behalf of the promoter. The AR of the promoter states that all the complaints filed in the matter have been settled and withdrawn and reply to this effect is being submitted today. Further, 100% consent of the allottees of the sold plots shall be submitted by 11.12.2024. Further, a public notice was published in the leading newspapers w.r.t. revision in the building plan from stilt +3 to stilt +4 on 22.10.2024 a copy of which has been placed on record. The office to verify the above. The matter to come up on 23.12.2024
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. The AR of the promoter states that regarding fire scheme of commercial plot no. 1, the size of the plot 1 is 211.50 sqmtr which is less than 500 sqmtr and they don’t require the fire scheme approval as per the clause no. 18(2)(b)(vi) of Haryana Fire and Emergency Services Bill, 2022(Act no 14 of 2022). The requisite consents of all the allottees (100%) for revision in the plans from S+3 to S+4 has been submitted and a public notice for objections, if any also issued on 22.10.2024 in three prominent newspapers. Eight no of complaints (1 joint complaint, 2 complaints through email, 1 individual complaint and 4 no. of online complaints in registry) were received and now have sent emails/settlement letters for withdrawal of the said complaints along with the said withdrawal of 1 joint complaint through counsel. This is without prejudice to the rights of allottees u/s 14 of the Act of 2016 and the individual complaints if any, filed under section 31 of the Act of 2016 shall be taken up on the date fixed in the court. A random confirmation of consents submitted by the promoter has also been done by the concerned AEE. The Fire scheme approval for commercial component i.e., commercial plot no. 1 is not mandatorily required being the area less than 500 sq.m. and height less than 15 mtrs. The approved service plan and estimates have already been submitted with density of 18 persons per plot. Approved as proposed. The addendum certificate shall be issued after submission of corrections in form A-H and DPI along with the other deficit documents.
Land, licence & cost
| Land area of the project | 6.88 acres |
|---|---|
| Total licensed area | 57.4 acres |
| Licence | License No- 102 of 2022 dated 27.07.2022 License No- 32 of 2021 dated 03.07.2021 |
| FAR permissible / proposed | 2.64 / 2.64 |
| Estimated project cost | ₹ 575.94 Cr |
| Cost of land | ₹ 40.19 Cr |
| Cost of construction | ₹ 387.32 Cr |
| EDC, taxes, levies and other costs | ₹ 148.43 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 25,669.65 | 92.2% |
| Commercial | 2,177.24 | 7.8% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License Approval | Already Been Obtained | 27 Jul 2022 |
| License Approval | Already Been Obtained | 3 Jul 2021 |
| Forest Noc | Already Been Obtained | 24 Mar 2021 |
| Aravalli Noc | Already Been Obtained | 13 Apr 2021 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tile / Laminated Wooden Flooring / Ceramic Tile |
|---|---|
| Wall Finishing Details | Plaster With Paint |
| Kitchen Details | Granite Counter With SS Sink |
| Bathroom Fittings | As Per Approved Make |
| Doors And Windos Frames | Hardwood Door Frame With Laminated Flush/Wooden Door |
| Electric Fittings | As Per Approved Make |
| Conducting And Wiring Details | As Per Approved Make |
| Water Storage | As Per Norms |
| Lift Details | 4 To 6 Passenger Lifts As Per Norms |
| Windows/Glazings | Aluminium Glazing / Upvc Glazing |
| Main Doors | Hardwood Door Frame With Laminated Flush Door |
| Internal Doors | Hardwood Door Frame With Laminated Wooden Door |
| Air Conditioning | Provision (Electrical And Drain Only) |
| Electrical Fittings | As Per Approved Make |
| External Finishing/Colour Scheme | Provision (Electrical And Drain Only) |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about M3M Soulitude 2?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.