41ST Floor, Tower-1, M3M International Financial Center, Sector-66,Gurugram,Haryana
CIN
U70109HR2006PTC047030
Site address
Sector-67, Gurugram
Sector
Sector 67
Tehsil / District
Badshahpur St / Gurugram
Construction start (as filed)
1 Oct 2024
Completion (as filed)
30 Apr 2030
Application submitted
4 Sep 2024
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. Approved as proposed subject to submission of DD/BG of Rs. 25 lakhs each on account of approval of service plan & estimates and fire NOC within 4 months.
Registration grantedGGM/876/608/2024/103
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
1 acres
Total licensed area
13.344 acres
Licence
License No. 53 of 2011 dated 10.06.2011 renewed up to 09.06.2029
FAR permissible / proposed
2.14 / 2.14
Estimated project cost
₹ 194.02 Cr
Cost of land
₹ 23.7 Cr
Cost of construction
₹ 108.3 Cr
Infrastructure and other structures
₹ 5.27 Cr
EDC, taxes, levies and other costs
₹ 56.75 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
1
100%
Apartments 134 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
16,495.00
-
134
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
GMDA
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 39.4 lakh
As Per Project Report
Water Supply System
₹ 18.43 lakh
As Per Project Report
Storm Water Drainage
₹ 8 lakh
As Per Project Report
Electricity Supply System
₹ 70.62 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 13.34 lakh
As Per Project Report
Street Lighting
₹ 6.42 lakh
As Per Project Report
Security And Fire Fighting
₹ 34.2 lakh
As Per Project Report
Playgrounds And Parks
₹ 4.73 lakh
As Per Project Report
Any Other
₹ 87 lakh
As Per Project Report
Hardscape And Softscape
₹ 96.13 lakh
As Per Project Report
Boundary Wall
₹ 33.1 lakh
As Per Project Report
Gaurd House
₹ 15.76 lakh
As Per Project Report
Parking
₹ 12.89 lakh
As Per Project Report
Consultancy
₹ 87 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Building Plan Approval
Already Been Obtained
3 Sep 2024
Electricity Approval
Already Been Obtained
3 May 2017
Assurance Treateed Water
Already Been Obtained
4 Sep 2024
Assurance Sewerage
Already Been Obtained
4 Sep 2024
Assurance Water Supply
Already Been Obtained
28 Aug 2024
Specifications (as filed)
Flooring Details Of Various Parts Of House
Combination Of Tile/Wooden Flooring/ Anti Skid Tiles In Drawing/Dining Room/Bedroom/Kitchen/Toilets
Wall Finishing Details
Cement Plaster/Gypsum Plaster/Obd/Acrylic Emulsion Paint/Dado Tile/Stone As Applicable In Bedroom/Kitchen/Drawing/Dining/Toilets Etc.
Kitchen Details
Stone Over Kitchen Counter And SS Sink.
Bathroom Fittings
Cp Fittings And Chinaware
Wood Work Etc
Wooden Flooring As Applicable
Doors And Windos Frames
Flush Doors/Laminated Doors With Hardwares
Glass Work
Glass Railing
Electric Fittings
Branded Ceiling Lights/ Branded Ceiling Lights
Conducting And Wiring Details
Fr Wires, Pvc Conduits
Water Storage
Ugwt And Ohwt
Lift Details
Elevators With Speed As Per Vertical Traffic
External Glazings
Aluminium / Upvc Framing
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about M3M Opus At M3M Merlin?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.