Icon At M3M Merlin (Tower T-11)
by Consolidate Realtors Private Limited · Sector -67, Gurugram
- RERA registration
- Applied, not granted yet
- Applied on
- 20 Aug 2020
- Application status
- Withdrawn
- Project ID
- RERA-GRG-715-2020
- Land area
- 1.222 acres
- Apartments
- 118 in 1 tower
- Completion (as filed)
- 15 Sep 2025
- Estimated cost
- ₹ 145.25 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-715-2020 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Icon At M3M Merlin (Tower T-11) |
| Promoter | Consolidate Realtors Private Limited |
| Promoter’s registered office | Lgf F-22, Sushant Shopping Arcade, Sushant Lok Phase-1, Gurugram-122002, Haryana |
| CIN | U70109HR2006PTC047030 |
| Site address | Sector -67, Gurugram |
| Sector | Sector 67 |
| Tehsil / District | Badshahpur St / Gurugram |
| Layout plan approved | 15 Jul 2020 |
| Building plans approved | 15 Jul 2020 |
| Construction start (as filed) | 15 Sep 2020 |
| Completion (as filed) | 15 Sep 2025 |
| Application submitted | 20 Aug 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st deficiency notice
-
Hearing
Examination By Authority
Proceedings
The promoter had applied for registration of the project on 24.08.2020 at the Haryana Real Estate Regulatory Authority, Gurugram. The deficiencies were conveyed to the promoter on 03.09.2020 vide letter no. HARERA/GGM/ RPIN/259 whereby the promoter was given an opportunity of hearing on 14.09.2020 at 3:00 pm in the office of HARERA, Gurugram. The Authority received an application from the promoter dated 10.09.2020 requesting an adjournment of 7 days because the promoter require more time to collect and compile the required data from the concerned departments due to Covid-19. The authority has granted an adjournment and a fresh opportunity of online hearing on 21.09.2020 at 3:00 p.m.
-
Hearing
Adjournment
Proceedings
The matter fixed for 22.09.2020
-
Hearing
Adjournment
Proceedings
During online hearing, Mr. Abhijeet Faujidar is present on behalf of the promoter. The matter is discussed at length and it was found that group housing colony named M3M Merlin was developed on 13.344 acres of land under license no. 53 of 2011. The total FAR permissible as per earlier building plan dated 30.07.2016 is 9450.0412 sq. m and achieved is 93606.151 sq. m. Total towers in the project is 10 along with a leftover land marked as “Area for future development”. Occupation certificate for tower 1 to 6, 7, 8 to 10, EWS, community building, shops has been received vide DTCP memo no ZP-748/SD(BS)/2017/5648 dated 24.03.2017. Later on, DTCP, Haryana vide TDR certificate no 04 of 2018 dated 21.06.2018 has granted additional FAR to M/s Benchmark Infotech Pvt Ltd. Accordingly, as per TDR utilization certificate no.1257-D/Asstt. (AK)/2017/5648 dated 01.01.2020, DTCP, Haryana has granted permission to M/s Consolidate Realtors Pvt Ltd to utilize 19142.85 sq. m of FAR under license no. 53 of 2011 out of the approved FAR 55588.18 sq .m of TDR certificate no. 4 of 2018. Now, total approved FAR including permitted TDR is 113644.89 sq. m out of OC granted for 93605.08 sq. m. balance FAR is 20038.75 sq. m. Building plan is revised vide memo no. 12566 dated 15.07.2020 which includes new tower named T-11 (ICON at M3M Merlin). This tower is a G+29 floor with 2 basements and the approved FAR for this tower is 18223.494 sq. m and the same is applied for RERA registration. As per section 14(2) of Real Estate (Regulation and Development) Act, 2016 which is reproduced below: “Adherence to sanctioned plans and project specifications by the promoter (2) Notwithstanding anything contained in any law, contract or agreement, after the sanctioned plans, layout plans and specifications and the nature of the fixtures, fittings, amenities and common areas, of the apartment, plot or building, as the case may be, as approved by the competent authority, are disclosed or furnished to the person who agree to take one or more of the said apartment, plot or building, as the case may be, the promoter shall not make— (i) any additions and alterations ……… (ii) any other alterations or additions in the sanctioned plans, layout plans and specifications of the buildings or the common areas within the project without the previous written consent of at least two-thirds of the allottees, other than the promoter, who have agreed to take apartments in such building. Explanation.—For the purpose of this clause, the allottees, irrespective of the number of apartments or plots, as the case may be, booked by him or booked in the name of his family, or in the case of other persons such as companies or firms or any association of individuals, etc., by whatever name called, booked in its name or booked in the name of its associated entities or related enterprises, shall be considered as one allottee only.” Only the balance FAR out of the earlier permissible FAR can be used in this area left for future development and the rest area will be used for green area or open area. Therefore, the project has undergone revision and it is mandatory for the promoter to obtain 2/3rd allottees consent before taking registration from the authority because section 14(2) of RERA Act, 2016 is applicable on this project. Also, the promoter is required to submit the deficit documents along with deficit fees. The matter will be heard on 12.10.2020
-
Hearing
Objection
Proceedings
Matter is adjourned for 02.11.2020
-
Hearing
Adjournment
Proceedings
Sh. Abhijeet Singh authorized representative of the promoter is present during online hearing of Icon at M3M Merin Project being developed by M/s Consolidate Realtors Private Limited. Despite repeated requests to the promoter for completion of the below-noted deficiencies, the promoter has not submitted the reply till date. The deficiencies which are not fulfilled by the promoter is as follows: 1. Copy of approved environment clearance not submitted. 2. Deficit fee of Rs. 572096/- not paid. 3. Copy of approved service estimates and plans not submitted. 4. Copy of approved fire scheme approval along with plans not submitted. 5. Copy of mining permission not submitted. 6. Details of all the community facilities which shall be handed over to the RWA or competent authority and to be constructed by the promoter itself and not forming part of the basic sale price needs to be provided. 7. Details of sold unsold inventory unit wise needs to be submitted. 8. Information to revenue department about the fact that project land licensed and bonded for setting up of a colony not informed to the revenue department for entry in the record of ownership. Part-E-Project Cost/sale Proceeds 9. Approved document of adjustment of External development charges and infrastructure development charges needs to be provided. 10. Approved service estimate plan has not been provided. 11. Saleable area to be mention in the form of carpet area square feet Part-H-Details of separate bank 12. Copy of home loan tie-up with banks not provided 13. Affidavit by the promoter Keeping in view the provisions of section 4 (2) (l) (D) of the Real Estate (Regulation & Development) Act, 2016, a separate account is to be maintained in a scheduled bank wherein 70% of the amounts realized from the allottees of the real estate project from time to time is to be deposited. 14. REP-II form not notarized. Part- J Additional details in case of an ongoing project 15. As per the definition of the ongoing project it is an ongoing project hence details of Part-J need to be provided. 16. Builder buyer agreement as per prescribed format needs to be submitted 17. Allotment letter and payment receipt need to be submitted. 18. Copy of superimposed demarcation plan on an approved site plan on the A1 sheet not submitted. 19. Earlier approved building plan needs to be submitted. 20. Approved fire scheme plans not submitted. 21. PERT Chart not submitted 22. Brochure of “Icon At M3M Merlin” needs to be submitted. The promoter has requested for extension of time to submit the reply of the deficiencies. The request was considered by the authority and decided to grant 2 weeks time to complete all the deficiencies by 17.11.2020. Now the matter to come up on 17.11.2020.
-
Hearing
Objection
Proceedings
matter adjourned for 30.11.2020
-
Hearing
Adjournment
Proceedings
matter adjourned for 14.12.2020
-
Hearing
Adjournment
Proceedings
matter adjourned for 08.02.2021
-
Hearing
Adjournment
Proceedings
No reply submitted by the promoter. Authority considered the matter as per agenda note and decided that we should wait for reply of the reference sent to the Director, Town and Country Planning, Govt. of Haryana, Chandigarh for clarification and guidance in the matter. Hearing adjourned for 22.02.2021.
-
Hearing
Sine Die
Proceedings
sine -die
-
Hearing
Adjournment View order
Proceedings
The matter Adjourned for 04.10.2022
-
Hearing
Withdrawn View order
Proceedings
Proceedings dated 04.10.2022 : Sh. Ashish Kush, Planning Executive and Ms. Asha (Chartered Accountant) briefed the facts of the case. Sh. Manik Sharma (Authorized Signatory) and Sh. Abhijeet Singh (AR) are present on behalf of the promoter. The AR of the promoter requested for the withdrawal of the application for registration as they have deferred the launch and development of the said project and further requested to refund the paid fee or allow to be adjusted against further application for registration of this project or any other project for registration of their associate company’s project as and when submitted for registration before the Authority. The Authority allowed the withdrawal of the application for registration of their group housing colony subject to the forfeiture of the Processing fee – Rs 1,82,335/- and the balance amount if any will be adjusted at the time of fresh application of registration. The matter stands disposed of. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
Land, licence & cost
| Land area of the project | 1.222 acres |
|---|---|
| Total licensed area | 13.344 acres |
| Licence | 53 of 2011 dated 10.06.2011 |
| FAR permissible / proposed | 175 / 210 |
| Estimated project cost | ₹ 145.25 Cr |
| Cost of land | ₹ 6.67 Cr |
| Cost of construction | ₹ 71.21 Cr |
| Infrastructure and other structures | ₹ 5.34 Cr |
| EDC, taxes, levies and other costs | ₹ 62.04 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 0.212 | 17.3% |
| Pavements | 0.168 | 13.7% |
| Parks And Playgrounds | 0.821 | 67.2% |
| Vehicle Parkings | 0.02 | 1.6% |
| Rain | 0.001 | 0.1% |
Apartments 118 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 14,676.84 | - | 118 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP/ GMDA | Yes |
| Water Supply | HSVP/ GMDA | Yes |
| Electricity | DHBVNL | Yes |
| Sewage Disposal | HSVP/GMDA | Yes |
| Storm Water Drainage | HSVP/GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 49.03 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 22.39 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 6.9 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 2.63 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 4.12 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 1.94 lakh | Submitted To Town & Country Planning |
| Security And Fire Fighting | ₹ 78.31 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 1.73 lakh | Submitted To Town & Country Planning |
| Electrification | ₹ 8 lakh | As Per Project Report |
| Parking Paint | ₹ 3.57 lakh | As Per Project Report |
| Rain Water Harvesting | ₹ 4 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Licence | Already Been Obtained | 10 Jun 2011 |
| Zoning Plan | Already Been Obtained | 14 Jun 2011 |
| Building Plan Approval | Already Been Obtained | 15 Jul 2020 |
| Environment Clearance | Already Been Obtained | 17 Jun 2013 |
| Airport Height Noc | Already Been Obtained | 6 Aug 2019 |
| Forest Noc | Already Been Obtained | 30 Dec 2011 |
| Aravali | Already Been Obtained | 12 Nov 2012 |
| Building Plan Approval (Revised) | Already Been Obtained | 15 Jul 2020 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Marble/ Wooden Flooring / Anti-Skid Tiles |
|---|---|
| Wall Finishing Details | Plaster With Paint |
| Kitchen Details | Plaster With Paint, Counter Top With Sink And Standard Cp Fittings |
| Bathroom Fittings | Standard Chinaware, Cp Fittings, With/ Without Wash Basin Counter |
| Doors And Windos Frames | Aluminium/ Upvc Frame Shutter With Glass |
| Glass Work | External Glazing |
| Electric Fittings | All Common Areas To Be Provided With Led Light Fixtures. Toilets & Balcony Of The Flat Are Provided With Led Light Fixture. |
| Conducting And Wiring Details | Isi Approved Fr Conduits & Wires |
| Lift Details | Otis/Schindler Or Equivalent |
| External Glazings | 13.1 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.