Lotus Green City
by Lotus Infraestates Pvt.ltd. · Sector 23-24,Dharuhera,Haryana
- RERA registration
- Applied, not granted yet
- Applied on
- 4 Dec 2020
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-882-2020
- Land area
- 50.144 acres
- Estimated cost
- ₹ 26.6 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-882-2020 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Lotus Green City |
| Promoter | Lotus Infraestates Pvt.ltd. |
| Promoter’s registered office | Dsc 260 South Court DLF Saket New Delhi South Delhi Dl 110017 |
| CIN | U70100DL2011PTC215874 |
| Site address | Sector 23-24,Dharuhera,Haryana |
| Sector | Sector 23 |
| Tehsil / District | Dharuhera St / Rewari |
| Layout plan approved | 22 Apr 2012 |
| Application submitted | 4 Dec 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Objections conveyed and adjourned to 15.02.2021.
-
Hearing
Objection View order
Proceedings
Objections conveyed and adjourned to 22.03.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 03.05.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 24.05.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.07.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.08.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 20.09.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 27.09.2021.
-
Hearing
Withdrawn/Rejected View order
Proceedings
Applied a fresh application for registration vide Temp. id 952-2021.
Land, licence & cost
| Land area of the project | 50.144 acres |
|---|---|
| Total licensed area | 50.144 acres |
| Licence | 39 0f 2012 |
| FAR permissible / proposed | 100 / 100 |
| Estimated project cost | ₹ 26.6 Cr |
| Cost of land | ₹ 13.71 Cr |
| Infrastructure and other structures | ₹ 0.7 Cr |
| EDC, taxes, levies and other costs | ₹ 5 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Plots To Be Sold | 22,568.63 | 100% |
| Construction Of Roads | 1.788 | 0% |
| Pavements | 2 | 0% |
| Parks And Playgrounds | 2.76 | 0% |
| Green Belts | 2.76 | 0% |
| Vehicle Parkings | 0.5 | 0% |
| Sewage And Solid Waste Treatment Facility | 0.05 | 0% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HUDA REWARI | No |
| Electricity | DHBVN | No |
| Sewage Disposal | HUDA REWARI | No |
| Storm Water Drainage | HUDA REWARI | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.55 lakh | As Per Project Report |
| Water Supply System | ₹ 1.69 lakh | As Per Project Report |
| Storm Water Drainage | ₹ 2.16 lakh | As Per Project Report |
| Electricity Supply System | ₹ 0.55 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 2.15 lakh | As Per Project Report |
| Street Lighting | ₹ 1.15 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 1.1 lakh | As Per Project Report |
| Any Other | ₹ 70.49 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Yet To File | Yet To File For Approval |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.