Gokulam The Sanctuary
by Nb Buildcon Pvt. Ltd. · Sector 7, Sohna
- RERA registration
- GGM/892/624/2024/119
- Registered on
- 11 Dec 2024
- Valid till
- 30 Sep 2027
- Project ID
- RERA-GRG-1715-2024
- Land area
- 1.262 acres
- Apartments
- 105 in 24 towers
- Completion (as filed)
- 30 Sep 2027
- Estimated cost
- ₹ 93.19 Cr
RERA registration
| Registration certificate | GGM/892/624/2024/119, dated 11 Dec 2024 |
|---|---|
| Registration valid till | 30 Sep 2027 |
| Project ID | RERA-GRG-1715-2024 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Gokulam The Sanctuary |
| Promoter | Nb Buildcon Pvt. Ltd. |
| Promoter’s registered office | 77-B, Shaheed Ripon Katyal Marg ,Sector -18,Gurugram |
| CIN | U45201DL2006PTC146913 |
| Site address | Sector 7, Sohna |
| Sector | Sector 7 |
| Tehsil / District | Sohna / Gurugram |
| Construction start (as filed) | 1 Sep 2024 |
| Completion (as filed) | 30 Sep 2027 |
| Application submitted | 19 Aug 2024 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
-
Hearing
Examination By Authority
Proceedings
The matter is adjourned and to come up on 14.10.2024.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Sunil Mehta (AR) is present on behalf of the promoter. Approved as proposed subject to rectification/compliances as indicated above and submission of 4(2)(l)(D) report for 2023-24. The registration certification shall be issued after the above compliances.
- Registration granted GGM/892/624/2024/119
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 1.262 acres |
|---|---|
| Total licensed area | 10.413 acres |
| Licence | Licence No. granted by TCP, Haryana is 168 of 2022 dated 21.10.2022 |
| FAR permissible / proposed | 1.64 / 1.24 |
| Estimated project cost | ₹ 93.19 Cr |
| Cost of land | ₹ 3.41 Cr |
| Cost of construction | ₹ 51.57 Cr |
| Infrastructure and other structures | ₹ 3.33 Cr |
| EDC, taxes, levies and other costs | ₹ 34.89 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 1.2616 | 100% |
Apartments 105 units · 24 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 950.13 | 10,227 | 33 |
| Apartment/Shops/Other Buildings | 913.53 | 9,833 | 72 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | No | WATER SUPPLY |
| HSVP | Yes | ELECTRICITY |
| DHBVN | Yes | SEWAGE DISPOSAL |
| HSVP | Yes | STORM WATER DRAINAGE |
| HSVP | Yes | 4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report: |
| Sr. No. | Name of the facility | Estimated cost (In Lakhs)(Within the project area only) |
| Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) | 1 | INTERNAL ROADS AND PAVEMENTS |
| 27.27 | SUBMITTED TO TOWN & COUNTRY PLANNING | 2 |
| Water Supply System | 33.91 | SUBMITTED TO TOWN & COUNTRY PLANNING |
| 3 | STORM WATER DRAINAGE | 14.57 |
| Submitted To Town & Country Planning | 4 | ELECTRICITY SUPPLY SYSTEM |
| 0 | YET TO BE PREPARED | 5 |
| Sewage Treatment & Garbage Disposal | 18.95 | SUBMITTED TO TOWN & COUNTRY PLANNING |
| 6 | STREET LIGHTING | 4.84 |
| Submitted To Town & Country Planning | 7 | SECURITY AND FIRE FIGHTING |
| 0 | YET TO BE PREPARED | 8 |
| Playgrounds And Parks | 0.82 | SUBMITTED TO TOWN & COUNTRY PLANNING |
| 9 | CLUB HOUSE/COMMUNITY CENTRE | 0 |
| Yet To Be Prepared | 10 | SHOPPING AREA |
| 0 | YET TO BE PREPARED | 11 |
| Renewable Energy System | 0 | YET TO BE PREPARED |
| 12 | SCHOOL | 0 |
| Yet To Be Prepared | 13 | HOSPITAL/DISPENSARY |
| 0 | YET TO BE PREPARED | 14 |
| Any Other | 0 | YET TO BE PREPARED |
| 15 | MTC CHARGES | 32.22 |
| Submitted To Town & Country Planning | 5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed. | NA |
| (date) | 6. Date of approval of Building Plans | NA |
| (date) | 7. New projects: | i) Likely date of starting the construction work |
| 01-09-2024 | ii) Likely date of completing the project | 30-09-2027 |
| iii) Sizes of the plots to be offered in the project | Sr. No | Plot Area(In Square Meter) |
| Number of plots in the project | 1 | 0 |
| 0 | Total | 0 |
| iv. Type of apartments to be constructed in the project: | Type | Carpet area(In Square Meter) |
| Number of apartments | Number of towers | Apartment/Shops/Other Buildings |
| 950.13 | 33 | 11 |
| Apartment/Shops/Other Buildings | 913.53 | 72 |
| 24 | (vi) Quarterly schedule of development of whole/remaining part of the project: | (c) Apartments/Shops/Other Buildings |
| Expenditure incurred till the date of application (In Lakhs) | Particulars | Expenditure |
| Apartments | 0 | Shops |
| 0 | Plots | 0 |
| Expenditure to be made in each quarter (In Lakhs) | Particulars | Expenditure to be made in each quarter ( |
| ) | Apr-June | July-Sep |
| Oct-Dec | Jan-Mar | (d) Infrastructure |
| Expenditure incurred till the date of application (In Lakhs) | Particulars | Expenditure |
| Roads & Pavements | 27.27 | Water Supply System |
| 33.91 | Sewerage treatment & garbage disposal | 18.95 |
| Electricity Supply System | 0 | Storm Water Drainage |
| 0 | Parks and Playgrounds | 0.82 |
| Clubhouse/community centres | 0 | Shopping area |
| 0 | Other | 0 |
| Street light | 4.84 | Expenditure to be made in each quarter (In Lakhs) |
| Particulars | Expenditure to be made in each quarter ( | ) |
| Apr-June | July-Sep | Oct-Dec |
| Jan-Mar | It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented. | Signature of the Applicant / Authorised Representative |
| Stamp _____________ | Date _____________ | FORM REP-I |
| Part - D | Accounts related information: | 1. Annex copy of the balance sheet of last 3 years |
| Yes | 2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D. | Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form. |
| No | 3. Bank account to which the deposits received from apartment buyers will be credited | Bank and Branch address |
| Federal Bank, 5, Sewa Corporate Park, M.g. Road, Gurugram | Bank Account number | 15280200009711 |
| IFSC code | FDRL0001528 | MICR code |
| 110049017 | Branch code | GRNB |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 27.27 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 33.91 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 14.57 lakh | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 18.95 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 4.84 lakh | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 0.82 lakh | Submitted To Town & Country Planning |
| Mtc Charges | ₹ 32.22 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Licence No. 168 Of 2022 | Already Been Obtained | 21 Oct 2022 |
| Zoning (Dgtcp-9571) | Already Been Obtained | 6 Sep 2023 |
| Layout Plan | Already Been Obtained | 21 Oct 2022 |
| Building Plans Approval For Plot No. B-2,3,4,5,6,7,8,9,10,11,12,13,16,17,18,19,20,21,22,23,24,25,26,27 | Already Been Obtained | 19 Jun 2024 |
| Building Plans Approval For Plot No. C-13,14,15,16,17,18,19,20,21,22,23 | Already Been Obtained | 19 Jun 2024 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vertified Italian Finish Tiles |
|---|---|
| Wall Finishing Details | Paint Wall Claddin Wood As Per Design |
| Kitchen Details | Vertified Italian Finish Tiles |
| Bathroom Fittings | Anti Skid Tiles |
| Wood Work Etc | Flush Door With Laminate |
| Doors And Windos Frames | Flush Door |
| Glass Work | Toughend Glass |
| Electric Fittings | Isi Marked |
| Conducting And Wiring Details | Isi Marked |
| Cupboard Details | N/A |
| Water Storage | Pvc Tanks. 1000 And 500 Liters (Flushing) |
| Lift Details | N/A |
| External Glazings | Toughened |
| Windows/Glazings | Upvc 5 Mm Thickness |
| Doors | Flush With Laminates |
| Main Doors | Flush With Laminates |
| Internal Doors | Flush With Laminates |
| Air Conditioning | N/A |
| Electrical Fittings | N/A |
| Cng Pipe Line | N/A |
| Provision Of Wifi And Broadband Facility | N/A |
| External Finishing/Colour Scheme | Weather Coat |
| Internal Finishing | N/A |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.