Ferrous City Phase 1
by Ferrous Infrastructure Pvt Ltd · Keri Chowk, Near Sudha Rastogi Dental College, Sector 89, Faridabad
- RERA registration
- Applied, not granted yet
- Applied on
- 20 Jul 2019
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-612-2019
- Land area
- 14.8 acres
- Estimated cost
- ₹ 192.23 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-612-2019 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Ferrous City Phase 1 |
| Promoter | Ferrous Infrastructure Pvt Ltd |
| Promoter’s registered office | L-7, Lower Ground Floor, Lajpat Nagar-3, New Delhi-24 |
| CIN | U45201DL2006PTC145748 |
| Site address | Keri Chowk, Near Sudha Rastogi Dental College, Sector 89, Faridabad |
| Sector | Sector 89 |
| Tehsil / District | Faridabad / Faridabad |
| Application submitted | 20 Jul 2019 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 09.09.2019
-
Hearing
Adjournment View order
Proceedings
Adjourned to 30.09.2019
-
Hearing
Sine Die View order
Proceedings
Sine die
-
Hearing
Adjournment View order
Proceedings
Adjourned to 02.03.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 08.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 13.07.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 07.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 21.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 23.11.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.02.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.04.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 07.06.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 12.07.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 20.09.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 08.11.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 29.11.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 20.12.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 14.02.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 28.02.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 07.03.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 10.03.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 09.05.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 03.10.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 31.10.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Approved for registration
-
Hearing
Re-Open/Adjournment View order
Proceedings
listing for 27-03-2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 29.05.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 10.07.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 11.07.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 28.08.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 06.11.2023
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.02.2024
-
Hearing
Withdrawn/Rejected View order
Proceedings
DISPOSED OF. Authority decides to reject the present applications with direction to the IRP to file fresh application for the registration of the project.
Land, licence & cost
| Land area of the project | 14.8 acres |
|---|---|
| Total licensed area | 48.38 acres |
| Licence | 34 - 36 of 2007 |
| FAR permissible / proposed | 1.75 / 1.75 |
| Estimated project cost | ₹ 192.23 Cr |
| Cost of land | ₹ 16.23 Cr |
| Cost of construction | ₹ 142 Cr |
| Infrastructure and other structures | ₹ 2 Cr |
| EDC, taxes, levies and other costs | ₹ 32 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 6,550.932 | 15.7% |
| Construction Of Roads | 4,258 | 10.2% |
| Pavements | 416 | 1% |
| Parks And Playgrounds | 4,302.89 | 10.3% |
| Green Belts | 5,950 | 14.2% |
| Vehicle Parkings | 18,683.6 | 44.6% |
| Electricity Sub-Station | 354 | 0.8% |
| Club House | 849.18 | 2% |
| Sewage And Solid Waste Treatment Facility | 493.24 | 1.2% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HUDA | No |
| Electricity | DHBVN | No |
| Sewage Disposal | HUDA | No |
| Storm Water Drainage | HUDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.63 Cr | As Per Project Report |
| Water Supply System | ₹ 2.39 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 55.95 lakh | As Per Project Report |
| Electricity Supply System | ₹ 2.46 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.18 Cr | As Per Project Report |
| Street Lighting | ₹ 22.71 lakh | As Per Project Report |
| Security And Fire Fighting | ₹ 4.6 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 10.25 lakh | As Per Project Report |
| Club House/Community Centre | ₹ 1.35 Cr | As Per Project Report |
| Shopping Area | ₹ 56 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Fire Fighting | Applied For But Yet To Receive | 2 Apr 2016 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tiles |
|---|---|
| Wall Finishing Details | Painted In Pleasant Shades Of Design Prints Of Oil Bound |
| Kitchen Details | Ceramic Tiles Above Working Platform |
| Bathroom Fittings | Ceramic Tiles, White Sanitary Fixture, Cp Fitting & Provision For Geysers |
| Doors And Windos Frames | Anodized Aluminum Glazing |
| Electric Fittings | Isi Marked Fittings |
| Conducting And Wiring Details | Conduit Copper Electrical Wiring For All Light & Power Points |
| Cupboard Details | Provision For Cupboard |
| Water Storage | Over Head Water Tanks Of Sufficient Capacity |
| Lift Details | Kone Lifts Installed |
| External Glazings | Aluminum Frame Glass In Staircase |
| Windows/Glazings | Aluminum Glazing |
| Doors | Wooden Doors |
| Main Doors | Skin Door |
| Internal Doors | Flush Door |
| Air Conditioning | Window Ac Provided On Ground Floor Only |
| Electrical Fittings | Isi Marked Fittings |
| External Finishing/Colour Scheme | Sleek Modern Elevation With Combination Of Texture Paint & Exclusive Club |
| Internal Finishing | Wall And Ceiling - Pleasant Shades In Kitchen & Tiolet, Flooring - Vitrified Tiles |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Ferrous City Phase 1?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.