HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Registration Certificate issued.
Application submitted online
Registration valid till
Land, licence & cost
Land area of the project
10.838 acres
Total licensed area
10.838 acres
Licence
70 of 2012
FAR permissible / proposed
1.75 / 174.69
Estimated project cost
₹ 234.07 Cr
Cost of land
₹ 6.45 Cr
Cost of construction
₹ 99.91 Cr
Infrastructure and other structures
₹ 46.54 Cr
EDC, taxes, levies and other costs
₹ 81.17 Cr
How the land will be used
Use
Sq m
Share
Land Area To Be Used For Construction Of Apartments
9,329.73
18.8%
Construction Of Roads
11,501
23.2%
Pavements
10,656
21.5%
Green Belts
5,830
11.8%
Vehicle Parkings
9,709
19.6%
Electricity Sub-Station
545
1.1%
Club House
615
1.2%
Commercial
189
0.4%
School
1,144.13
2.3%
External services
Service
Provided by
Approval taken
Roads
HUDA
No
Water Supply
HUDA
No
Electricity
UHBVN
Yes
Sewage Disposal
HUDA
No
Storm Water Drainage
HUDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.44 Cr
As Per Project Report
Water Supply System
₹ 86 lakh
As Per Project Report
Storm Water Drainage
₹ 4.5 Cr
As Per Project Report
Electricity Supply System
₹ 6.66 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 75 lakh
As Per Project Report
Security And Fire Fighting
₹ 4.15 Cr
As Per Project Report
Playgrounds And Parks
₹ 30 lakh
As Per Project Report
Club House/Community Centre
₹ 1.53 Cr
As Per Project Report
Shopping Area
₹ 20 lakh
As Per Project Report
Renewable Energy System
₹ 35 lakh
As Per Project Report
Residential Building
₹ 99.91 Cr
As Per Project Report
Lift
₹ 5.82 Cr
As Per Project Report
Basement
₹ 15.51 Cr
As Per Project Report
EWS
₹ 2.47 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
Environment Clearance
Already Been Obtained
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified /Wooden Flooring/Anti Skied Tiles
Wall Finishing Details
Obd With Wall Putty
Kitchen Details
Sink With Mixture And Granite/ Marble Counter
Bathroom Fittings
Ewc With Cistern Wash Bashing And Shower
Wood Work Etc
Door And Window
Doors And Windos Frames
Wooden
Glass Work
4/5 Mm Float Glass
Electric Fittings
Isi Mark
Conducting And Wiring Details
Isi Mark
Cupboard Details
No
Water Storage
Rcc Over Head Tank
Lift Details
Jhonshan Make
External Glazings
Wooden
Windows/Glazings
Wooden
Doors
Skin Molded
Main Doors
Laminated /Skin Molded
Internal Doors
Skin Molded
Air Conditioning
No
Electrical Fittings
Isi Mark
Cng Pipe Line
No
Provision Of Wifi And Broadband Facility
Yes
External Finishing/Colour Scheme
Berger Texture Paint
Internal Finishing
Obd Enamel Paint
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Espania- 2?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.