B-2/3, Kh. No. 8/8, Chhatterpur Extn., Nanda Hospital, New Delhi-110074
CIN
U74899DL1983PTC014992
Site address
Sector-37C, Village-Gharoli And Basai
Sector
Sector 37
Tehsil / District
Kadipur St / Gurugram
Application submitted
9 Dec 2019
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Next hearingNot Required
Registration granted352 OF 2017
Application submitted online
Application received by HRERA Gurugram
Registration valid till
Land, licence & cost
Land area of the project
8.5 acres
Total licensed area
17 acres
Licence
64 of 2011 dated 16.07.2011
FAR permissible / proposed
1.75 / 1.75
Estimated project cost
₹ 245.85 Cr
Cost of land
₹ 36.88 Cr
Cost of construction
₹ 100.14 Cr
Infrastructure and other structures
₹ 28.61 Cr
EDC, taxes, levies and other costs
₹ 38.66 Cr
How the land will be used
Use
Area (as filed)
Share
Plots To Be Sold
493
96.7%
Land Area To Be Used For Construction Of Apartments
8.5
1.7%
Construction Of Roads
2.1
0.4%
Pavements
0.85
0.2%
Parks And Playgrounds
3.1
0.6%
Green Belts
1.5
0.3%
Vehicle Parkings
0.3
0.1%
Electricity Sub-Station
0.4
0.1%
Club House
0.25
0%
External services
Service
Provided by
Approval taken
Roads
HSVP
Yes
Water Supply
HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HSVP
Yes
Storm Water Drainage
HUDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 665,240 Cr
Yet To Be Prepared
Water Supply System
₹ 221,750 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 221,750 Cr
Yet To Be Prepared
Electricity Supply System
₹ 576,540 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 332,620 Cr
Yet To Be Prepared
Street Lighting
₹ 88,700 Cr
Yet To Be Prepared
Security And Fire Fighting
₹ 665,240 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 110,870 Cr
Yet To Be Prepared
Club House/Community Centre
₹ 354,790 Cr
Yet To Be Prepared
Shopping Area
₹ 133,050 Cr
Yet To Be Prepared
Renewable Energy System
₹ 110,870 Cr
Yet To Be Prepared
Parking
₹ 110,870 Cr
Yet To Be Prepared
Underground Tank
₹ 110,870 Cr
Yet To Be Prepared
Rain Water Harvesting
₹ 66,520 Cr
Yet To Be Prepared
Elctrical Sub Station
₹ 665,240 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Town And Country Planing Department
Already Been Obtained
16 Jul 2011
Fire Department
Already Been Obtained
13 Dec 2013
State Environment Impact Assessment Authority Haryana
Already Been Obtained
15 Apr 2015
Haryana State Pollution Control Board, Panchkula
Already Been Obtained
1 Jan 2018
Deputy Commissioner Gurugram - Forest And Aravali
Already Been Obtained
13 Jan 2014
Airport Authority Of India
Already Been Obtained
20 Feb 2013
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified Tiles/Wooden Laminated/Ceramic Tiles
Wall Finishing Details
Obd/Ceramic Dado
Kitchen Details
Vitrified Tile On Flooring/Ceramic Tiles Dado & Obd Paint
Bathroom Fittings
Isi Marked
Doors And Windos Frames
Al. External
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Esfera, Phase-II?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.