The matter is adjourned and to come up on 13.01.2025.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Ankit Chadha (AR), Sh. Santosh Pandey (AR) are present on behalf of the promoter. Approved as proposed. The RC shall be issued after submission of corrected REP-I (A to H) and DPI.
Registration grantedGGM/899/631/2025/02
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Licence
The land for the project was allotted by the Haryana Shehri Vikas Pradhikaran (HSVP) to the Promoter through an e-auction process on a freehold basis, vide Allotment Letter dated 29.09.2023 ( Vide Memo No. ZO002/EO018/UE029/GALOT/0000001157) for the development of group housing tower thereon.
FAR permissible / proposed
4.12 / 4.12
Estimated project cost
₹ 263.44 Cr
Cost of land
₹ 67.99 Cr
Cost of construction
₹ 127.93 Cr
Infrastructure and other structures
₹ 16.53 Cr
EDC, taxes, levies and other costs
₹ 50.99 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
1,375.53
40%
Pavements
1,189.37
34.6%
Green Belts
515.812
15%
Electricity Sub-Station
8.9
0.3%
Sewage And Solid Waste Treatment Facility
91.05
2.6%
Any Other
258.008
7.5%
Apartments 74 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
162.56
1,750
14
Apartment/Shops/Other Buildings
163.57
1,761
15
Apartment/Shops/Other Buildings
162.56
1,750
15
Apartment/Shops/Other Buildings
163.06
1,755
14
Apartment/Shops/Other Buildings
158.05
1,701
14
Apartment/Shops/Other Buildings
162.56
1,750
1
Apartment/Shops/Other Buildings
163.06
1,755
1
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
ALREADY CONNECTED (HSVP)
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Sewerage Connection
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 50 lakh
As Per Project Report
Water Supply System
₹ 1.39 Cr
As Per Project Report
Storm Water Drainage
₹ 50 lakh
As Per Project Report
Electricity Supply System
₹ 2.87 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 1.39 Cr
As Per Project Report
Street Lighting
₹ 10 lakh
As Per Project Report
Security And Fire Fighting
₹ 2.01 Cr
As Per Project Report
Renewable Energy System
₹ 1.5 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Assurance For Sewerage Connection For Discharge Of 50 Kld Surplus Domestic Treated Effluent.
Already Been Obtained
22 Jul 2024
Assurance For Storm Water Connection Of Proposed Group Housing Project.
Already Been Obtained
22 Jul 2024
No Objection Certificate For Hight Clearance
Already Been Obtained
20 Aug 2024
No Objection Certificate For Fire
Already Been Obtained
24 Feb 2024
Environment Clearance
Already Been Obtained
29 Oct 2024
Mining Permission
Already Been Obtained
5 Nov 2024
Tree Cutting Permission
Already Been Obtained
19 Dec 2023
Green Rating For Integrated Habitat Assessment
Already Been Obtained
5 Aug 2024
Building Plan
Already Been Obtained
10 Oct 2024
Assurance For Water Supply 5 Kld For Domestic Purpose.
Already Been Obtained
23 Jul 2024
Assurance For Supply Of 30 Kld Stp Treated Water For Construction Of Group Housing Project.
Already Been Obtained
22 Jul 2024
Site Plan
Already Been Obtained
10 Oct 2024
Possession Certificate
Already Been Obtained
8 Nov 2023
Non Encumbrance Certificate
Already Been Obtained
10 Sep 2024
Letter Of Intent
Already Been Obtained
8 Nov 2023
Specifications (as filed)
Flooring Details Of Various Parts Of House
Good Quality Italian Stone
Wall Finishing Details
Plastic Paint
Kitchen Details
Modular Kitchen
Bathroom Fittings
Cp Fittings
Doors And Windos Frames
Cpvc
Glass Work
As Per Isi Specifications
Conducting And Wiring Details
As Per Isi Specifications
Cupboard Details
As Per Isi Specifications
External Glazings
Upvc
Windows/Glazings
Upvc
Doors
Cpvc
Main Doors
Flush Doors 30MM Thick With 1MM Sunmica
Internal Doors
Flush Doors 30MM Thick With 1MM Sunmica
Air Conditioning
As Per Isi Specifications
Electrical Fittings
As Per Isi Specifications
Provision Of Wifi And Broadband Facility
Provision
External Finishing/Colour Scheme
Exterior Paint
Internal Finishing
Plastic Paint
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Anantavilasa?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.