Registration validHRERA Gurugram

Alban

by Pyramid Infratech Private Limited · Village Begampur Khatola Sector 71

RERA registration
GGM/796/528/2024/23
Registered on
11 Mar 2024
Valid till
31 May 2030
Project ID
RERA-GRG-1503-2023
Land area
4.525 acres
Apartments
622 in 4 towers
Completion (as filed)
30 Jun 2030
Estimated cost
₹ 1,651.08 Cr

RERA registration

Registration certificateGGM/796/528/2024/23, dated 11 Mar 2024
Registration valid till31 May 2030
Project IDRERA-GRG-1503-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameAlban
PromoterPyramid Infratech Private Limited
Promoter’s registered officeH 38 M2K White House Sector 57 Gurugram Haryana 122002
CINU45400HR2008PTC038509
Site addressVillage Begampur Khatola Sector 71
SectorSector 71
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved11 Jan 2024
Building plans approved11 Jan 2024
Construction start (as filed)1 Feb 2024
Completion (as filed)30 Jun 2030
Application submitted21 Dec 2023

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter By Hand
  1. Hearing Examination By Authority View order
    Proceedings

    Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority through deficiency notice dated 04.01.2024. Therefore, in view of the same the matter is adiourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4week,s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016.

  2. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Sunil Kumar (AR), Sh. Praveen Kumar Singh (AR) and Sh. Rahul Singh (AR) and Sh. Ajay Pratap Singh (AR) are present on behalf of the promoter. The AR states that the GMDA has granted in principle approval for road access and final approval will be submitted within four weeks. The approval of EC is listed in the agenda for tomorrow i.e. 27.02.2024 and final approval will be submitted within four months. The Fire NOC will be submitted within three months and the promoter shall submit a DD/BG of Rs. 25 lakhs as a guarantee for submission of fire NOC within three months. The 66 KV line passing through the site adversely affect the part of the proposed building and till it’s shifting, no construction in its ROW can be raised and hence will be submitting the approval from concerned authority within two weeks. The AR seeks two weeks’ time for submission of deficit documents. The matter to come up on 11.03.2024.

  3. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Sunil Kumar (AR), Sh. Praveen Kumar Singh (AR) is present on behalf of the promoter. Approved as proposed subject to the above.

  1. Registration granted GGM/796/528/2024/23
  2. Certificate uploaded RC Uploaded
  3. Registration valid till

Land, licence & cost

Land area of the project4.525 acres
Total licensed area4.525 acres
Licence155 OF 2023
FAR permissible / proposed3.5 / 3.5
Estimated project cost₹ 1,651.08 Cr
Cost of land₹ 117.99 Cr
Cost of construction₹ 539.37 Cr
Infrastructure and other structures₹ 97.82 Cr
EDC, taxes, levies and other costs₹ 895.9 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.564912.5%
Construction Of Roads0.660914.6%
Parks And Playgrounds0.93520.7%
Sewage And Solid Waste Treatment Facility0.0972.1%
Any Other0.712715.8%
Watersupplysystem0.05161.1%
Stormwaterdrainage0.17593.9%
Streetlighting0.0240.5%
Electricitysupplysystem0.0120.3%
Horticulture1.29128.5%

Apartments 622 units · 4 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings88,678.92-622

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsGMDANo
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.36 CrAs Per Project Report
Water Supply System₹ 3.74 CrAs Per Project Report
Storm Water Drainage₹ 75.92 lakhAs Per Project Report
Electricity Supply System₹ 7.81 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 1.37 CrAs Per Project Report
Street Lighting₹ 17.36 lakhAs Per Project Report
Security And Fire Fighting₹ 3.91 CrAs Per Project Report
Playgrounds And Parks₹ 1.67 CrAs Per Project Report
Renewable Energy System₹ 2.23 CrAs Per Project Report
Any Other₹ 12.25 CrAs Per Project Report
Parking₹ 5.02 CrAs Per Project Report
Stp₹ 4.35 CrAs Per Project Report
Underground Water Tank₹ 3.23 CrAs Per Project Report
Rain Water Harvesting₹ 83.73 lakhAs Per Project Report
Electrical Sub Station₹ 3.35 CrAs Per Project Report
Lift Work₹ 2.23 CrAs Per Project Report
Horticulture₹ 6.28 lakhAs Per Project Report
Service And Resurfacing Of Road₹ 1.44 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
License 155 Of 2023Already Been Obtained3 Aug 2023
Forest NocAlready Been Obtained24 May 2023
Aravali NocAlready Been Obtained11 Jul 2023
Air Port Height ClearanceAlready Been Obtained5 Jun 2023
Noc Stp WaterAlready Been Obtained8 Sep 2023
Water SupplyAlready Been Obtained22 Sep 2023
Electricity Load AvailablityAlready Been Obtained25 Sep 2023
Sewerage Disposal NocAlready Been Obtained8 Sep 2023
Zoning PlanAlready Been Obtained3 Aug 2023
Building PlanApplied For But Yet To Receive10 Oct 2023
Environment ClearanceApplied For But Yet To Receive10 Oct 2023
Service Plan EstimatesApplied For But Yet To Receive10 Oct 2023
Fire Acknowledgement SlipApplied For But Yet To Receive10 Oct 2023

Specifications (as filed)

Flooring Details Of Various Parts Of HouseTiles, Kajaria/Simpolo/ Orient /

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Alban?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp