by Tedre Ralcon India Pvt Ltd · Village Rampur,Atta,Sohna
RERA registration
Applied, not granted yet
Applied on
27 Jan 2024
Application status
In process
Project ID
RERA-PKL-1404-2024
Land area
5.986 acres
Estimated cost
₹ 24.45 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
Registration certificate
Not issued yet: the application is being processed by HRERA Panchkula
Project ID
RERA-PKL-1404-2024
Authority
HRERA Panchkula
Project type (as filed)
Ongoing
Project name
Zara Flora
Promoter
Tedre Ralcon India Pvt Ltd
Promoter’s registered office
C-12, Defence Colony, New Delhi
Site address
Village Rampur,Atta,Sohna
Tehsil / District
Nuh / Nuh
Application submitted
27 Jan 2024
Authority, hearings & orders
Current statusStatus not given
Next hearingNot Required
Application submitted online
Land, licence & cost
Land area of the project
5.986 acres
Total licensed area
5.963 acres
Licence
88 of 2019 (02.08.2019)
FAR permissible / proposed
2 / 2
Estimated project cost
₹ 24.45 Cr
Cost of land
₹ 16.38 Cr
Infrastructure and other structures
₹ 4.47 Cr
EDC, taxes, levies and other costs
₹ 3.4 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
12,151
50.4%
Construction Of Roads
5,427
22.5%
Pavements
1,410
5.8%
Parks And Playgrounds
1,410
5.8%
Electricity Sub-Station
110
0.5%
Sewage And Solid Waste Treatment Facility
12
0%
Area To Be Left For Transferring To The Government For Community Services
2,453
10.2%
Any Other
1,156
4.8%
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
HSVP,DIVNO6.GURUGRAM
Yes
ELECTRICITY
HSVP,DIVNO6.GURUGRAM
Yes
SEWAGE DISPOSAL
HSVP,DIVNO6.GURUGRAM
Yes
STORM WATER DRAINAGE
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
50
As Per Project Report
2
WATER SUPPLY SYSTEM
85
YET TO BE PREPARED
3
Storm Water Drainage
40
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
122
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
52
YET TO BE PREPARED
6
Street Lighting
33
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
40
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
20
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
5
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
Na
(date)
6. Date of approval of Building Plans
Na
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type DDJAY
1438.40
12
17260.8
12
0
0
2
PLOT Type DDJAY
1269.18
12
15230.16
12
0
0
3
PLOT Type DDJAY
1408.31
12
16899.72
12
0
0
4
PLOT Type DDJAY
1081.08
9
9729.72
9
0
0
5
PLOT Type DDJAY
2189.40
20
43788
11
9
0
6
PLOT Type DDJAY
1292.40
12
15508.8
1
11
0
7
PLOT Type DDJAY
1164.28
12
13971.36
1
11
0
8
PLOT Type DDJAY
2036.38
21
42763.98
12
9
0
Total
110
175152.54
70
40
0
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
NA
0
NA
(b) Time schedule of completion of already booked apartments:
Start Date
N/A
Earlier date of completion
N/A
Revised date of completion
N/A
(c) Time schedule for development of infrastructure:
Start Date
01-01-2021
Percentage completion Upto the
date of application
68
Projected date of completion
31-12-2024
(d) Provide further details in the proforma REP-I Part-C-X.
(e) Plan of action for completing the Project along with requisite infrastructure.
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
Plot
70
NIL
(b) Schedule for development of Infrastructure:
Start Date
01-01-2021
Percentage completion
68
Projected date of completion
31-01-2024
(c) Provide further details in the proforma REP-I Part-C-X.
(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-
a) Underground parking
0
b) Stilt parking
0
c) Covered parking
0
d) Open parking
0
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
1093
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
1382
OTHER COST
229
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
10
Water Supply System
20
Sewerage treatment & garbage disposal
18
Electricity Supply System
2
Storm Water Drainage
16
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
452
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
2023
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
110
ii. No. of Flats/ Apartments booked
70
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
1907.41 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
1365.44 Lakhs
Amount Excluding Taxes
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
541.975 Lakhs
Amount excluding taxes
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
1093 Lakhs
Land Purchase 669 lakh and Collaboration cost 424 lakh
Apartments
0 Lakhs
Infrastructure
450 Lakhs
EDC/ Taxes Etc.
70 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
812 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. Internal Roads And Pavements
40
10
II. Water Supply System
30
20
III. Storm Water Drainage
30
16
IV. Electricity Supply System
122
2
V. Sewage Treatment & Garbage Disposal
40
0
Vi. Club House/Community Centre
0
0
Vii. School
0
0
Viii. Any Other
20
0
Ix. Solid Waste Collection & Mgmt System
0
0
X. Clubhouse
0
0
Xi. Neighbourhood Shopping
0
0
Xii. Green Areas,Parks,Playgrounds Etc.
10
0
Xiii. Covered Parking
0
0
Xiv. Open Parking
0
0
Xv. Garages
0
0
Xvi. Security System
20
0
Xvii. Other Facilities As Per Project Report
0
0
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
Yes
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
Axis Bank Ltd Lajpat Nagar
Bank Account number
921020039396565
IFSC code
UTIB0000126
MICR code
11021017
Branch code
000126
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 50 lakh
As Per Project Report
Water Supply System
₹ 85 lakh
Yet To Be Prepared
Storm Water Drainage
₹ 40 lakh
Yet To Be Prepared
Electricity Supply System
₹ 1.22 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 52 lakh
Yet To Be Prepared
Street Lighting
₹ 33 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 40 lakh
Yet To Be Prepared
Playgrounds And Parks
₹ 20 lakh
Yet To Be Prepared
Renewable Energy System
₹ 5 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
1 Noc For Arawali Project Planation 1992 For Constructionn An Affordable Plotted Colony
Already Been Obtained
7 Aug 2019
2 Clarification Regarding Applicability Of Forest Laws On Non Forest Land
Already Been Obtained
22 Apr 2019
3 Assurance Of 190 Kld Fresh Water Supply For Drinking And Domestic Purpose Required For Condtruction Our Affordable Plotted Colony Project
Already Been Obtained
22 Sep 2019
4 Assurance Of Sewerage Connection For Discharge Of 190 Kld Treated Effluent From Our Affordable Plotted Colony Project
Already Been Obtained
22 Sep 2019
5 Assurance Of Supply Of 50 Kld Treated Water Required For Construction Of Our Affordable Plotted Colony Project
Already Been Obtained
22 Sep 2019
6 Assurance Certificate Of DHBVN For 624.44KW Requried During Commissioning Of Our Affordable Plotted Colony Project
Already Been Obtained
16 Sep 2019
Specifications (as filed)
Flooring Details Of Various Parts Of House
N/A
Wall Finishing Details
N/A
Kitchen Details
N/A
Bathroom Fittings
N/A
Wood Work Etc
N/A
Doors And Windos Frames
N/A
Glass Work
N/A
Electric Fittings
N/A
Conducting And Wiring Details
N/A
Cupboard Details
N/A
Water Storage
Completed
Lift Details
N/A
External Glazings
N/A
Windows/Glazings
N/A
Doors
N/A
Main Doors
N/A
Internal Doors
N/A
Air Conditioning
N/A
Electrical Fittings
N/A
Cng Pipe Line
N/A
Provision Of Wifi And Broadband Facility
N/A
External Finishing/Colour Scheme
N/A
Internal Finishing
N/A
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Zara Flora?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.