- Project ID
- RERA-GRG-347-2019
- Land area
- 7.7 acres
- Plots
- 181
- Completion (as filed)
- 5 Nov 2022
- Estimated cost
- ₹ 19.44 Cr
RERA registration
| Registration certificate | GGM/420/152/2020/36, dated 16 Oct 2020 |
|---|---|
| Registration valid till | 4 Nov 2023 |
| Project ID | RERA-GRG-347-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Yash Vihar |
| Promoter | M/S Ksd Buildtech Pvt. Limited |
| Promoter’s registered office | SCO-35, Sector-15, Gurugram, Haryana- 122001 |
| CIN | U70100HR2011PTC043811 |
| Site address | Revenue Estate Of Village Pataudi, Sector-5, Pataudi, District- Gurugram, Haryana |
| Sector | Sector 5 |
| Tehsil / District | Pataudi / Gurugram |
| Layout plan approved | 1 Oct 2019 |
| Construction start (as filed) | 1 Oct 2020 |
| Completion (as filed) | 5 Nov 2022 |
| Application submitted | 24 Nov 2019 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter By Hand
-
Hearing
Examination By Authority
Proceedings
The matter is Adjourned for hearing on 23.12.2019.
-
Hearing
Adjournment View order
Proceedings
The matter is Adjourned for hearing on 20.01.2020.
-
Hearing
Adjournment
Proceedings
The matter is Adjourned for hearing on 03.02.2020.
-
Hearing
Adjournment View order
Proceedings
The matter is Adjourned for hearing on 09.03.2020.
-
Hearing
Adjournment
Proceedings
The matter will be heard on 07.04.2020
-
Hearing
Objection
Proceedings
The matter will be heard on 09.06.2020
-
Hearing
Objection View order
Proceedings
During online hearing, Ms. Priyanka Aggarwal is present on behalf of the builder. The promoter is directed to complete the deficiencies otherwise their project will be rejected. The deficit documents are as follows: 1. Deficit fee of Rs 135/-. 2. Copy of approved service estimates and plans. 3. Copy of approved zoning plan. 4. Copy of approved layout plan. 5. Electrical load availability NOC. 6. Project report. The next date of hearing is fixed for 22.06.2020.
-
Hearing
Objection View order
Proceedings
The promoter was not present for online hearing and requested for next date. The Authority considered the project and noticed that there are following deficiencies: 1. Deficit fee of Rs. 135/- 2. Copy of approved service estimates and plans. 3. Electrical load availability NOC. 4. Project report. The Authority has opinion that without approval of service estimates and plans, registration of the project shall not be granted although the Authority has been granting registration earlier in such cases but the experience is that even after many years, the service plan estimates are not got sanctioned and without service plan estimates, services cannot be laid down. The promoter be issued show cause notice under section 5 as why the application for grant of registration shall not be rejected on account of deficiencies mentioned above. The promoter is granted personal hearing on 27th July, 2020.
-
Hearing
Objection Compliance Done
Proceedings
Next date of Hearing 04.08.2020
-
Hearing
Adjournment View order
Proceedings
The Planning Assistant briefed details of the project. The deficiencies were brought in thenotice of the promoter. The main deficiencies are regarding non approval of the serviceplan and estimates and electrical load availability NOC. There are large number ofcorrections required to be made in DPI and Part A to H of online format. Seven hearingshave already been given to the promoter. Show cause notice has already been givenregarding rejection of the application. Keeping in view the deficiencies the Authoritydecided to reject the application for registration of project. Detailed order will follow.
-
Hearing
Objection View order
Proceedings
The Planning Assistant briefed details of the project. The deficiencies were brought in thenotice of the promoter. The main deficiencies are regarding non approval of the serviceplan and estimates and electrical load availability NOC. There are large number ofcorrections required to be made in DPI and Part A to H of online format. Seven hearingshave already been given to the promoter. Show cause notice has already been givenregarding rejection of the application. Keeping in view the deficiencies the Authoritydecided to reject the application for registration of project. Detailed order will follow.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
The Promoter submitted an application for revival of project registration application on 12-10-2020 in the Authority. The Authority accepted his application and fixed the hearing for 16-10-2020. In the hearing the Authority has decided to grant the Registration Certificate.
- Registration granted GGM/420/152/2020/36
- Certificate uploaded RC Approved and Certificate Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 7.7 acres |
|---|---|
| Total licensed area | 7.7 acres |
| Licence | 94 of 2017 |
| FAR permissible / proposed | 100 / 100 |
| Estimated project cost | ₹ 19.44 Cr |
| Cost of land | ₹ 2 Cr |
| Infrastructure and other structures | ₹ 4.86 Cr |
| EDC, taxes, levies and other costs | ₹ 12.57 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Plots To Be Sold | 18,866.141 | 60.5% |
| Construction Of Roads | 4,117.001 | 13.2% |
| Pavements | 1,419.342 | 4.6% |
| Parks And Playgrounds | 2,359.317 | 7.6% |
| Area To Be Left For Transferring To The Government For Community Services | 3,132.267 | 10.1% |
| Any Other | 1,266.727 | 4.1% |
Plots 181 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 17,306.76 | 20,699 | 186,288 | 181 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HSVP | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HUDA | Yes |
| Storm Water Drainage | HUDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 25.09 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 32.02 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 14.71 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 12.5 lakh | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 19.03 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 74.19 lakh | Submitted To Town & Country Planning |
| Security And Fire Fighting | ₹ 95 lakh | Submitted To Town & Country Planning |
| Playgrounds And Parks | ₹ 13.84 lakh | Submitted To Town & Country Planning |
| Club House/Community Centre | ₹ 50 lakh | Submitted To Town & Country Planning |
| Renewable Energy System | ₹ 22.5 lakh | Submitted To Town & Country Planning |
| Stp | ₹ 49.5 lakh | Submitted To Town & Country Planning |
| Under Ground Water Tank | ₹ 30 lakh | Submitted To Town & Country Planning |
| Rain Water Harvesting | ₹ 15 lakh | Submitted To Town & Country Planning |
| Electrical Sub Station | ₹ 15 lakh | Submitted To Town & Country Planning |
| Construction Of Cerculation Road | ₹ 5 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Layout Plan | Already Been Obtained | 6 Nov 2017 |
| Zoning Plan | Already Been Obtained | 31 Jan 2020 |
| Natural Conservation | Already Been Obtained | 11 Jun 2018 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Yash Vihar?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.