Registration period overHRERA GurugramOC / CC on record

Yash Vihar

by M/S Ksd Buildtech Pvt. Limited · Revenue Estate Of Village Pataudi, Sector-5, Pataudi, District- Gurugram, Haryana

RERA registration
GGM/420/152/2020/36
Registered on
16 Oct 2020
Valid till
4 Nov 2023
Project ID
RERA-GRG-347-2019
Land area
7.7 acres
Plots
181
Completion (as filed)
5 Nov 2022
Estimated cost
₹ 19.44 Cr

RERA registration

Registration certificateGGM/420/152/2020/36, dated 16 Oct 2020
Registration valid till4 Nov 2023
Project IDRERA-GRG-347-2019
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameYash Vihar
PromoterM/S Ksd Buildtech Pvt. Limited
Promoter’s registered officeSCO-35, Sector-15, Gurugram, Haryana- 122001
CINU70100HR2011PTC043811
Site addressRevenue Estate Of Village Pataudi, Sector-5, Pataudi, District- Gurugram, Haryana
SectorSector 5
Tehsil / DistrictPataudi / Gurugram
Layout plan approved1 Oct 2019
Construction start (as filed)1 Oct 2020
Completion (as filed)5 Nov 2022
Application submitted24 Nov 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyDeficiencies conveyed and Notice Sent Harveer
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter By Hand
  1. Hearing Examination By Authority
    Proceedings

    The matter is Adjourned for hearing on 23.12.2019.

  2. Hearing Adjournment View order
    Proceedings

    The matter is Adjourned for hearing on 20.01.2020.

  3. Hearing Adjournment
    Proceedings

    The matter is Adjourned for hearing on 03.02.2020.

  1. Hearing Adjournment View order
    Proceedings

    The matter is Adjourned for hearing on 09.03.2020.

  2. Hearing Adjournment
    Proceedings

    The matter will be heard on 07.04.2020

  3. Hearing Objection
    Proceedings

    The matter will be heard on 09.06.2020

  1. Hearing Objection View order
    Proceedings

    During online hearing, Ms. Priyanka Aggarwal is present on behalf of the builder. The promoter is directed to complete the deficiencies otherwise their project will be rejected. The deficit documents are as follows:  1.   Deficit fee of Rs 135/-. 2.   Copy of approved service estimates and plans.  3.   Copy of approved zoning plan.  4.   Copy of approved layout plan.  5.   Electrical load availability NOC.  6.   Project report.  The next date of hearing is fixed for 22.06.2020.

  2. Hearing Objection View order
    Proceedings

    The promoter was not present for online hearing and requested for next date. The Authority considered the project and noticed that there are following deficiencies: 1.      Deficit fee of Rs. 135/- 2.      Copy of approved service estimates and plans. 3.      Electrical load availability NOC. 4.      Project report. The Authority has  opinion that without approval of service estimates and plans, registration of the project shall not be granted although the Authority has been granting registration earlier in such cases but the experience is that even after many years, the service plan estimates are not got sanctioned and without service plan estimates, services cannot be laid down. The promoter be issued show cause notice under section 5 as why the application for grant of registration shall not be rejected on account of deficiencies mentioned above. The promoter is granted personal hearing on 27th July, 2020.

  3. Hearing Objection Compliance Done
    Proceedings

    Next date of Hearing 04.08.2020

  1. Hearing Adjournment View order
    Proceedings

    The Planning Assistant briefed details of the project. The deficiencies were brought in thenotice of the promoter. The main deficiencies are regarding non approval of the serviceplan and estimates and electrical load availability NOC. There are large number ofcorrections required to be made in DPI and Part A to H of online format. Seven hearingshave already been given to the promoter. Show cause notice has already been givenregarding rejection of the application. Keeping in view the deficiencies the Authoritydecided to reject the application for registration of project. Detailed order will follow.

  2. Hearing Objection View order
    Proceedings

    The Planning Assistant briefed details of the project. The deficiencies were brought in thenotice of the promoter. The main deficiencies are regarding non approval of the serviceplan and estimates and electrical load availability NOC. There are large number ofcorrections required to be made in DPI and Part A to H of online format. Seven hearingshave already been given to the promoter. Show cause notice has already been givenregarding rejection of the application. Keeping in view the deficiencies the Authoritydecided to reject the application for registration of project. Detailed order will follow.

  3. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    The Promoter submitted an application for revival of project registration application on 12-10-2020 in the Authority. The Authority accepted his application and fixed the hearing for 16-10-2020. In the hearing the Authority has decided to grant the Registration Certificate.

  1. Registration granted GGM/420/152/2020/36
  2. Certificate uploaded RC Approved and Certificate Uploaded
  3. Registration valid till

Land, licence & cost

Land area of the project7.7 acres
Total licensed area7.7 acres
Licence94 of 2017
FAR permissible / proposed100 / 100
Estimated project cost₹ 19.44 Cr
Cost of land₹ 2 Cr
Infrastructure and other structures₹ 4.86 Cr
EDC, taxes, levies and other costs₹ 12.57 Cr

How the land will be used

UseSq mShare
Plots To Be Sold18,866.14160.5%
Construction Of Roads4,117.00113.2%
Pavements1,419.3424.6%
Parks And Playgrounds2,359.3177.6%
Area To Be Left For Transferring To The Government For Community Services3,132.26710.1%
Any Other1,266.7274.1%

Plots 181 plots

Plot size (sq m)Sq ydSq ftPlots
17,306.7620,699186,288181

External services

ServiceProvided byApproval taken
RoadsHUDANo
Water SupplyHSVPYes
ElectricityDHBVNYes
Sewage DisposalHUDAYes
Storm Water DrainageHUDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 25.09 lakhSubmitted To Town & Country Planning
Water Supply System₹ 32.02 lakhSubmitted To Town & Country Planning
Storm Water Drainage₹ 14.71 lakhSubmitted To Town & Country Planning
Electricity Supply System₹ 12.5 lakhSubmitted To Town & Country Planning
Sewage Treatment & Garbage Disposal₹ 19.03 lakhSubmitted To Town & Country Planning
Street Lighting₹ 74.19 lakhSubmitted To Town & Country Planning
Security And Fire Fighting₹ 95 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 13.84 lakhSubmitted To Town & Country Planning
Club House/Community Centre₹ 50 lakhSubmitted To Town & Country Planning
Renewable Energy System₹ 22.5 lakhSubmitted To Town & Country Planning
Stp₹ 49.5 lakhSubmitted To Town & Country Planning
Under Ground Water Tank₹ 30 lakhSubmitted To Town & Country Planning
Rain Water Harvesting₹ 15 lakhSubmitted To Town & Country Planning
Electrical Sub Station₹ 15 lakhSubmitted To Town & Country Planning
Construction Of Cerculation Road₹ 5 lakhSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
Layout PlanAlready Been Obtained6 Nov 2017
Zoning PlanAlready Been Obtained31 Jan 2020
Natural ConservationAlready Been Obtained11 Jun 2018

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Yash Vihar?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.