Registration period overHRERA PanchkulaOC / CC on record

White Lily

by Aakarshak Realators Pvt. Ltd. · Sector-8, Village Kamaspur, Near Tau Devi Lal Par, Main NH -1, Sonepat

RERA registration
HRERA-PKL-SNP-2-2018
Valid till
31 Dec 2018
Project ID
RERA-PKL-601-2019
Land area
9.262 acres
Estimated cost
₹ 237.61 Cr

RERA registration

Registration certificateHRERA-PKL-SNP-2-2018
Registration valid till31 Dec 2018
Project IDRERA-PKL-601-2019
AuthorityHRERA Panchkula
Project type (as filed)Ongoing
Project nameWhite Lily
PromoterAakarshak Realators Private Limited
Promoter’s registered office410, 4TH Floor, D Mall, Netaji Subhash Place, Pitampura, New Delhi-110034
CINU45201DL2005PTC133483
Site addressSector-8, Village Kamaspur, Sonepat
SectorSector 8
Tehsil / DistrictSonipat / Sonipat
Layout plan approved21 Jan 2013
Building plans approved21 Jan 2013
Application submitted24 Oct 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration valid till
  2. Application submitted online
  3. Application received by HRERA Panchkula

Land, licence & cost

Land area of the project9.262 acres
Total licensed area9.262 acres
Licence182 of 2007 Dated 14.05.2007
FAR permissible / proposed1.75 / 1.75
Estimated project cost₹ 237.61 Cr
Cost of land₹ 29.3 Cr
Cost of construction₹ 90 Cr
Infrastructure and other structures₹ 40.92 Cr
EDC, taxes, levies and other costs₹ 77.39 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments6,419.110.7%
Construction Of Roads12,116.920.3%
Parks And Playgrounds8,55314.3%
Green Belts1,5002.5%
Vehicle Parkings24,56041.1%
Club House195.80.3%
Sewage And Solid Waste Treatment Facility4800.8%
Area To Be Left For Transferring To The Government For Community Services1,6682.8%
Stilt4,297.097.2%

External services

ServiceProvided byApproval taken
RoadsHSVPYes
Water SupplyHSVPYes
ElectricityUHBVNYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.31 CrSubmitted To Town & Country Planning
Water Supply System₹ 2.67 CrSubmitted To Town & Country Planning
Storm Water Drainage₹ 90.96 lakhSubmitted To Town & Country Planning
Electricity Supply System₹ 5 CrSubmitted To Town & Country Planning
Sewage Treatment & Garbage Disposal₹ 1.37 CrAs Per Project Report
Street Lighting₹ 35.52 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 7.98 lakhSubmitted To Town & Country Planning
Club House/Community Centre₹ 50 lakhSubmitted To Town & Country Planning
Shopping Area₹ 50 lakhSubmitted To Town & Country Planning
School₹ 2 CrSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
Permanent Electrical ConnectionsAlready Been Obtained22 Jul 2019
Public Health Approval From HUDAAlready Been Obtained31 Oct 2012
Environment ClearanceAlready Been Obtained11 Jul 2014
Noc From Airport AuthorityAlready Been Obtained13 Nov 2013
Service Plan EstimatesAlready Been Obtained27 Dec 2017
Consent To Establish From Pollution Control BoardAlready Been Obtained27 Apr 2015
Fire NocAlready Been Obtained16 Jan 2019
Sanctioned PlansAlready Been Obtained23 Jan 2013
Lift RegistrationAlready Been Obtained
Consent To OperateApplied For But Yet To Receive

Specifications (as filed)

Flooring Details Of Various Parts Of House• Vitrified Tiles In Drawing Room, Bed Rooms

Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about White Lily?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.