Wal Street 73
by M/S Evfyme Technologies Pvt. Ltd. · Near DLF Almeda Entry, Sector 73
- RERA registration
- GGM/627/359/2022/102
- Registered on
- 21 Nov 2022
- Valid till
- 30 Mar 2026
- Project ID
- RERA-GRG-1073-2022
- Land area
- 2.825 acres
- Plots
- 33
- Completion (as filed)
- 31 Mar 2025
- Estimated cost
- ₹ 44.18 Cr
RERA registration
| Registration certificate | GGM/627/359/2022/102, dated 21 Nov 2022 |
|---|---|
| Registration valid till | 30 Mar 2026 |
| Project ID | RERA-GRG-1073-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Wal Street 73 |
| Promoter | M/S Evfyme Technologies Pvt. Ltd. |
| Promoter’s registered office | Plot No. 151P Sector 52, Gurugram |
| CIN | U72900HR2019PTC084257 |
| Site address | Near DLF Almeda Entry, Sector 73 |
| Sector | Sector 73 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 24 Feb 2022 |
| Construction start (as filed) | 30 Nov 2022 |
| Completion (as filed) | 31 Mar 2025 |
| Application submitted | 15 Jul 2022 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter Deficiency notice
-
Hearing
Examination By Authority View order
Proceedings
Sh. Sumeet, Engineer Executive briefed about the facts of the project. Sh. Pawan Kumar (Advocate-AR) is present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. Matter to come up on 27.09.2022
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineer Executive briefed about the facts of the project and following major deficiencies have pointed out i.e. (1) Standard Designs / Architectural Control Sheets. (2.) Approval/ NOCs for external services. The matter is adjourned for 11.10.2022.
-
Hearing
Adjournment View order
Proceedings
The major deficiencies Architectural Control sheet & Approval for external services. The promoter is further advised to rectify the deficiencies and submit the deficient document apart from filing information in REP-I A to H format and detailed project information. Matter to come up on 26.10.2022.
-
Hearing
Objection View order
Proceedings
The coram is not complete. So the matter is adjourned for 27.10.2022.
-
Hearing
Adjournment View order
Proceedings
The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Praveen Kumar (AR) is present on behalf of the promoter. Approved as proposed.
- Registration granted GGM/627/359/2022/102
- Registration valid till
Land, licence & cost
| Land area of the project | 2.825 acres |
|---|---|
| Total licensed area | 2.825 acres |
| Licence | Licence No. 14 of 2022 Granted by Town and Country Planning, Haryana |
| FAR permissible / proposed | 1.5 / 1.5 |
| Estimated project cost | ₹ 44.18 Cr |
| Cost of land | ₹ 24.16 Cr |
| Infrastructure and other structures | ₹ 3.34 Cr |
| EDC, taxes, levies and other costs | ₹ 16.69 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Plots To Be Sold | 4,000.345 | 35% |
| Construction Of Roads | 1,898.5 | 16.6% |
| Pavements | 2,450.75 | 21.4% |
| Green Belts | 474.68 | 4.2% |
| Vehicle Parkings | 1,425.5 | 12.5% |
| Electricity Sub-Station | 400.25 | 3.5% |
| Sewage And Solid Waste Treatment Facility | 428.3 | 3.7% |
| Any Other | 354.033 | 3.1% |
Plots 33 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 96.08 | 115 | 1,034 | 1 |
| 101.14 | 121 | 1,089 | 2 |
| 102.00 | 122 | 1,098 | 2 |
| 103.70 | 124 | 1,116 | 8 |
| 106.02 | 127 | 1,141 | 1 |
| 113.42 | 136 | 1,221 | 12 |
| 115.49 | 138 | 1,243 | 1 |
| 123.44 | 148 | 1,329 | 1 |
| 144.77 | 173 | 1,558 | 1 |
| 162.64 | 195 | 1,751 | 1 |
| 176.66 | 211 | 1,902 | 1 |
| 229.23 | 274 | 2,467 | 1 |
| 249.13 | 298 | 2,682 | 1 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 93.11 lakh | Submitted To Town & Country Planning |
| Water Supply System | ₹ 79.3 lakh | Submitted To Town & Country Planning |
| Storm Water Drainage | ₹ 35.84 lakh | Submitted To Town & Country Planning |
| Electricity Supply System | ₹ 16.92 lakh | Submitted To Town & Country Planning |
| Sewage Treatment & Garbage Disposal | ₹ 32.59 lakh | Submitted To Town & Country Planning |
| Street Lighting | ₹ 10.84 lakh | Submitted To Town & Country Planning |
| Stp | ₹ 25 lakh | Submitted To Town & Country Planning |
| Under Ground Water Tank | ₹ 10 lakh | Submitted To Town & Country Planning |
| Rwh | ₹ 5 lakh | Submitted To Town & Country Planning |
| Electrical Substation | ₹ 15 lakh | Submitted To Town & Country Planning |
| Parkin | ₹ 10 lakh | Submitted To Town & Country Planning |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 24 Feb 2022 |
| Layout | Already Been Obtained | 24 Feb 2022 |
| Service Plan & Estimates | Already Been Obtained | 6 Jun 2022 |
| Standard Design | Already Been Obtained | 21 Nov 2022 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.