Worldmark Gurgaon, Unit No. 1001, 10TH Floor, Sector 65, Gurgaon
CIN
U70109HR2021PTC092905
Site address
Revenue Estate Of Dhanwapur, Sector 103, Gurugram
Sector
Sector 103
Tehsil / District
Gurgaon / Gurugram
Layout plan approved
8 Apr 2025
Building plans approved
8 Apr 2025
Construction start (as filed)
10 May 2025
Completion (as filed)
31 Dec 2032
Application submitted
18 Apr 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Deepika, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Navdeep Sardana, Sh. Deepak Pant (AR), Ms. Monika Balhara (AR) are present on behalf of promoter and states that DTCP has granted the additional license vide license No. 158 of 2024 dated 20.11.2024, for an area of 9.7271 acres and the total area of the projects now becomes 19.23126 acres. Further, DTCP has approved the revised phasing vide DRG No. DTCP 10830 having memo no ZP-1942-II/SD(RD)/2025/12531 dated 08.04.2025 and the additional cum revised building plan was approved vide Memo No. ZP-1942-II/SD (RD)/2025/12535 dated 08.04.2025. The AR submits that as per the revised phasing plan there are total 6 phases now. The AR further submits that this application is for the registration of the project “Urban Resort Phase- 6” for an area measuring 0.8519 acres. The AR further submits that service plans and estimates of the whole licensed area i.e., 19.23126 acres has been approved by DTCP vide memo no LC-5229-D/JE(AK)/2025/17299 dated 09.05.2025 and copy of the same is being submitted in the Authority. Further Fire scheme approval for the whole project i.e., 19.23126 acres has been applied in the concerned department and further request to consider one security amount in all the five applications as all phases are under a single licensed colony and thus single approval for fire scheme will be issued by the concerned department. In view of the same, request is allowed. Further, the promote shall submit the BG/DD of Rs 25 lakhs as a security amount to submit the approved fire scheme for the whole project within 4 months of the issuance of registration certificate. Approved as proposed. The registration certificate shall be issued after the submission of form A-H, DPI and other deficit documents along with BG/DD as above.
Registration grantedGGM/950/682/2025/53
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
19.231 acres
Total licensed area
19.231 acres
Licence
License No. 263 of 2023 and 158 of 2024
FAR permissible / proposed
3.99 / 3.99
Estimated project cost
₹ 46.83 Cr
Cost of land
₹ 12.11 Cr
Cost of construction
₹ 22.37 Cr
Infrastructure and other structures
₹ 4.15 Cr
EDC, taxes, levies and other costs
₹ 8.21 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
0.548
64.3%
Construction Of Roads
0.0126
1.5%
Pavements
0.0026
0.3%
Green Belts
0.2444
28.7%
Any Other
0.0413
4.8%
Rainwater
0.003
0.4%
Apartments 274 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
18.72
202
90
Apartment/Shops/Other Buildings
19.59
211
90
Apartment/Shops/Other Buildings
18.62
200
90
Apartment/Shops/Other Buildings
392.23
4,222
2
Apartment/Shops/Other Buildings
889.89
9,579
2
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
CONNECTED
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 18.22 lakh
As Per Project Report
Water Supply System
₹ 2.66 lakh
As Per Project Report
Storm Water Drainage
₹ 5.82 lakh
As Per Project Report
Electricity Supply System
₹ 1.56 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 7.08 lakh
As Per Project Report
Street Lighting
₹ 2.16 lakh
As Per Project Report
Security And Fire Fighting
₹ 4.3 lakh
As Per Project Report
Playgrounds And Parks
₹ 50.6 lakh
As Per Project Report
Renewable Energy System
₹ 4.66 lakh
As Per Project Report
Electrification Cost Upto Project
₹ 1.35 Cr
As Per Project Report
Circulation Of Roads
₹ 35.29 lakh
As Per Project Report
Parking Mechanical Car Parking
₹ 18.89 lakh
As Per Project Report
Underground Water Tank
₹ 4.66 lakh
As Per Project Report
Rain Water Harvesting
₹ 2.65 lakh
As Per Project Report
Stp
₹ 7.06 lakh
As Per Project Report
Electrical Sub Station
₹ 94.26 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Environment Clearance
Already Been Obtained
19 Feb 2025
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified Tile, Laminate Wooden Flooring
Wall Finishing Details
Premium Acrylic Distemper
Kitchen Details
Single Lever Counter Top
Bathroom Fittings
Chinaware , Single Lever Counter Top
Wood Work Etc
No
Doors And Windos Frames
Full Height Windows- Aluminium Poder
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Urban Resort Phase 6?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.