Ultimus
by B D Infradevelopers Private Limited · Village Badha, Sector 90, Gurugram
- RERA registration
- GGM/378/110/2019/72
- Registered on
- 23 Dec 2019
- Valid till
- 29 Jun 2025
- Project ID
- RERA-GRG-340-2019
- Land area
- 5 acres
- Apartments
- 720 in 8 towers
- Plots
- 720
- Completion (as filed)
- 1 Jan 2024
- Estimated cost
- ₹ 148.74 Cr
RERA registration
| Registration certificate | GGM/378/110/2019/72, dated 23 Dec 2019 |
|---|---|
| Registration valid till | 29 Jun 2025 |
| Project ID | RERA-GRG-340-2019 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Ultimus |
| Promoter | B D Infradevelopers Private Limited |
| Promoter’s registered office | Unit No. 131, Vatika Tower-A, Sector 54, Gurugram |
| CIN | U70109HR2012PTC045209 |
| Site address | Village Badha, Sector 90, Gurugram |
| Sector | Sector 90 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 11 Sep 2019 |
| Building plans approved | 11 Sep 2019 |
| Construction start (as filed) | 1 Jan 2020 |
| Completion (as filed) | 1 Jan 2024 |
| Application submitted | 19 Nov 2019 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Examination By Authority
Proceedings
1st deficiency notice sent.
-
Hearing
Adjournment View order
Proceedings
Online information has not been updated. The service plan estimates as has been submitted to the competent authority be uploaded on the web page of the project on the web site of the authority till approved service estimates are submitted. Necessary rectification of deficiencies be done. In the meanwhile, the matter is adjourned to 16.12.2019.
-
Hearing
Adjournment
Proceedings
NEXT DATE OF HEARING ON 18.12.2019
-
Hearing
Adjournment
Proceedings
NEXT DATE OF HEARING ON 24.12.2019
- Registration granted GGM/378/110/2019/72
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Approved
- Registration valid till
Land, licence & cost
| Land area of the project | 5 acres |
|---|---|
| Total licensed area | 5 acres |
| Licence | 30 of 2019 |
| FAR permissible / proposed | 47550.488 / 400 |
| Estimated project cost | ₹ 148.74 Cr |
| Cost of land | ₹ 31.65 Cr |
| Cost of construction | ₹ 92.32 Cr |
| Infrastructure and other structures | ₹ 13.5 Cr |
| EDC, taxes, levies and other costs | ₹ 11.28 Cr |
How the land will be used
| Use | Sq m | Share |
|---|---|---|
| Plots To Be Sold | 720 | 3.4% |
| Land Area To Be Used For Construction Of Apartments | 4,401.786 | 21% |
| Construction Of Roads | 3,204 | 15.3% |
| Pavements | 5,869.962 | 28% |
| Parks And Playgrounds | 3,261.53 | 15.6% |
| Green Belts | 1,145.05 | 5.5% |
| Vehicle Parkings | 1,440 | 6.9% |
| Electricity Sub-Station | 35 | 0.2% |
| Club House | 201.25 | 1% |
| Any Other | 675.674 | 3.2% |
Apartments 720 units · 8 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 41,007.90 | - | 720 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
Plots 720 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 46,036.97 | 55,060 | 495,537 | 720 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | DGTCP | No |
| Water Supply | HSVP, DIV NO. III, GURUGRAM | Yes |
| Electricity | DAKSHIN HARYANA BIJLI VITRAN NIGAM | Yes |
| Sewage Disposal | DGTCP | Yes |
| Storm Water Drainage | DGTCP | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 44.61 lakh | Yet To Be Prepared |
| Water Supply System | ₹ 52.9 lakh | Yet To Be Prepared |
| Storm Water Drainage | ₹ 25.31 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 27.83 lakh | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 27 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 9.07 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 10.03 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Aravali | Already Been Obtained | 31 May 2019 |
| Sewrage Connection | Already Been Obtained | 14 May 2019 |
| Building Plans | Already Been Obtained | 11 Sep 2019 |
| Forest | Already Been Obtained | 15 Feb 2019 |
| Aai | Already Been Obtained | 11 Jul 2019 |
| Enviornment Clearance | Applied For But Yet To Receive |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified & Ceramic Tiles |
|---|---|
| Wall Finishing Details | Obd |
| Kitchen Details | Isi Marked |
| Bathroom Fittings | Isi Marked |
| Doors And Windos Frames | Wooden(Door Frame), Aluminiumn /Upvc(Window Frame) |
| Glass Work | Isi Marked |
| Electric Fittings | Isi Marked |
| Conducting And Wiring Details | Isi Marked |
| Water Storage | Rcc/Pvc |
| Lift Details | Isi Marked |
| External Glazings | Aluminiumn/Upvc |
| Windows/Glazings | Aluminiumn/Upvc |
| Doors | As Mentioned Below |
| Main Doors | Flush Door |
| Internal Doors | Flush Door |
| Electrical Fittings | Isi Marked |
| External Finishing/Colour Scheme | Texture Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.