Village Dhankot, Tehsil Kadipr, Sector 102, Gurugram
Sector
Sector 102
Tehsil / District
Gurgaon / Gurugram
Layout plan approved
17 Feb 2025
Building plans approved
17 Feb 2025
Construction start (as filed)
30 Apr 2025
Completion (as filed)
15 Oct 2028
Application submitted
6 Mar 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyfirst hearing
Next hearingNot Required
Application submitted online
HearingExamination By AuthorityProceedings
The matter is adjourned and to come up on 07.04.2025.
HearingAdjournment
HearingAdjournmentProceedings
Ms. Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Praveen Hooda (AR) is present on behalf of the promoter. The concerned PE/PC to visit the site to ascertain access to the site from 24 mtr. wide road or any other existing access. Further, the NEC from Tehsildar will also be submitted along with the deficit documents. The matter to come up on 05.05.2025.
HearingApproved And Ready For Certificate Issuing ProcessProceedings
Ms. Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Praveen Hooda (AR) and Ms. Tanya (AR) are present on behalf of the promoter. Approved as proposed subject to rectification of remaining deficiencies. The registration certificate shall be issued after corrections in A to H and DPI.
Registration grantedGGM/948/680/2025/51
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
5.29 acres
Total licensed area
5.29 acres
Licence
223 of 2023
FAR permissible / proposed
2.9284 / 2.9283
Estimated project cost
₹ 526.75 Cr
Cost of land
₹ 21.47 Cr
Cost of construction
₹ 348.7 Cr
Infrastructure and other structures
₹ 28 Cr
EDC, taxes, levies and other costs
₹ 126.63 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
1.3818
26.1%
Construction Of Roads
2.1518
40.7%
Parks And Playgrounds
1.556
29.4%
Vehicle Parkings
0.168
3.2%
Electricity Sub-Station
0.0023
0%
Securityandfirefighting
0.004
0.1%
Commercial
0.0263
0.5%
Apartments 268 units · 2 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
166.66
1,794
2
Apartment/Shops/Other Buildings
200.24
2,155
2
Apartment/Shops/Other Buildings
166.66
1,794
64
Apartment/Shops/Other Buildings
200.24
2,155
32
Apartment/Shops/Other Buildings
200.24
2,155
28
Apartment/Shops/Other Buildings
181.67
1,955
4
Apartment/Shops/Other Buildings
409.42
4,407
2
Apartment/Shops/Other Buildings
138.64
1,492
2
Apartment/Shops/Other Buildings
154.48
1,663
2
Apartment/Shops/Other Buildings
138.64
1,492
62
Apartment/Shops/Other Buildings
154.48
1,663
62
Apartment/Shops/Other Buildings
136.34
1,468
2
Apartment/Shops/Other Buildings
120.57
1,298
2
Apartment/Shops/Other Buildings
296.88
3,196
2
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
CONNECTED
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3.24 Cr
As Per Project Report
Water Supply System
₹ 2.5 Cr
As Per Project Report
Storm Water Drainage
₹ 1.35 Cr
As Per Project Report
Electricity Supply System
₹ 13.5 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 1.85 Cr
As Per Project Report
Street Lighting
₹ 20 lakh
As Per Project Report
Security And Fire Fighting
₹ 65 lakh
As Per Project Report
Playgrounds And Parks
₹ 50 lakh
As Per Project Report
Renewable Energy System
₹ 30 lakh
As Per Project Report
Parking
₹ 81 lakh
As Per Project Report
Stp
₹ 75 lakh
As Per Project Report
Underground Water Tank
₹ 85 lakh
As Per Project Report
Rain Water Harvesting
₹ 30 lakh
As Per Project Report
Electrical Sub Station
₹ 60 lakh
As Per Project Report
Construction Of Circulation Road
₹ 60 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Aai Noc
Already Been Obtained
29 Apr 2024
License
Already Been Obtained
30 Oct 2023
Br III
Already Been Obtained
17 Feb 2025
Specifications (as filed)
Flooring Details Of Various Parts Of House
Tile
Wall Finishing Details
Emulsion Paint
Kitchen Details
Tile
Bathroom Fittings
Cp Fittings
Wood Work Etc
Marandi Wood
Doors And Windos Frames
Upvc / Aluminium Powder Coating
Electric Fittings
Modular Switch
Conducting And Wiring Details
Fire Proof Wiring
Cupboard Details
Ply And Laminate
Water Storage
Rcc Pipe
Lift Details
Lift With Ard
External Glazings
6MM Float G;Ass
Main Doors
Fire Door Painted
Internal Doors
Flush Door Painted
Air Conditioning
Provision
Cng Pipe Line
Provision
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Twin Horizon?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.