SS House , Plot No. -77, Sector-44, Gurugram-122003
CIN
U70109HR2010PTC048739
Site address
Sector-85, Gurugram
Sector
Sector 85
Tehsil / District
Manesar / Gurugram
Layout plan approved
4 Feb 2015
Building plans approved
4 Feb 2015
Application submitted
26 Feb 2019
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
Registration grantedGGM/329/61/2019/23
Registration valid till
Land, licence & cost
Land area of the project
11.093 acres
Total licensed area
11.093 acres
Licence
81 of 2011 (16-09-2011)
FAR permissible / proposed
1.75 / 1.74
Estimated project cost
₹ 435.46 Cr
Cost of land
₹ 12.26 Cr
Cost of construction
₹ 216.29 Cr
Infrastructure and other structures
₹ 66.78 Cr
EDC, taxes, levies and other costs
₹ 140.13 Cr
How the land will be used
Use
Area (as filed)
Share
Construction Of Roads
3,093.616
37.3%
Pavements
3,760.33
45.3%
Vehicle Parkings
660
8%
Electricity Sub-Station
311.26
3.8%
Sewage And Solid Waste Treatment Facility
173
2.1%
Area Falling Under Twenty Four Meter Sector Road
298.151
3.6%
External services
Service
Provided by
Approval taken
Roads
HARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)
Yes
Water Supply
HARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)
Yes
Electricity
HARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)
Yes
Sewage Disposal
HARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)
Yes
Storm Water Drainage
HARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 92.53 lakh
As Per Project Report
Water Supply System
₹ 73.65 lakh
As Per Project Report
Storm Water Drainage
₹ 42.97 lakh
As Per Project Report
Electricity Supply System
₹ 4 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 86.36 lakh
As Per Project Report
Street Lighting
₹ 11.2 lakh
As Per Project Report
Security And Fire Fighting
₹ 89.92 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
30 Dec 2013
Sanctioned Building Plan
Already Been Obtained
4 Feb 2015
Environmental Clearance
Already Been Obtained
24 Oct 2017
Forest Noc
Already Been Obtained
18 Feb 2016
Airport Height Clearance Noc
Already Been Obtained
17 Jun 2016
Fire Scheme Approval
Already Been Obtained
1 Jul 2016
Service Plan Approval
Already Been Obtained
3 Oct 2018
Water Assurance
Already Been Obtained
2 Jun 2016
Specifications (as filed)
Flooring Details Of Various Parts Of House
Lobby/Corridor: Granite/Vitrified Tiles
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about The Leaf?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.