RERA applied, not grantedHRERA Gurugram

The Leaf

by Navi Estates LLP · Village Dhunela, Sector-34

RERA registration
Applied, not granted yet
Applied on
6 Nov 2024
Application status
Approved And Ready For Certificate Issuing Process
Project ID
RERA-GRG-1777-2024
Land area
2.625 acres
Apartments
1,005 in 1 tower
Completion (as filed)
30 Jun 2025
Estimated cost
₹ 101.3 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Gurugram
Project IDRERA-GRG-1777-2024
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameThe Leaf
Site addressVillage Dhunela, Sector-34
SectorSector 34
Tehsil / DistrictSohna / Gurugram
Construction start (as filed)15 Dec 2020
Completion (as filed)30 Jun 2025
Application submitted6 Nov 2024

Authority, hearings & orders

Current statusApproved And Ready For Certificate Issuing Process
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Hearing Examination By Authority
    Proceedings

    The matter is adjourned and to come up on 16.12.2024.

  3. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 30.12.2024. 

  1. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 27.01.2025. 

  2. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 24.02.2025. 

  3. Hearing Adjournment
    Proceedings

    Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Vijay K Goel, Sh. Anil Kumar (AR) and Sh. Om Singh (AR) are present on behalf of the promoter. The contact details of the allottees who have consented for change be verified by the office at random. The promoter is directed to submit an unconditional bank undertaking with respect to the project. Further, a 2 week public notice to be published in three prominent newspapers (one Hindi and two English) intimating the revisions in building plan and for inviting objections, if any. Other deficiencies be also rectified by the applicant promoter in meanwhile. The matter to come up on 10.03.2025.

  1. Hearing Adjournment
    Proceedings

    The matter is adjourned and to come up on 24.03.2025.

  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Vijay K. Goel (Partner) and Sh. Om Singh (AR) are present on behalf of the promoter. Approved as proposed subject to above corrections and submission of BG/DD of Rs. 25 lakhs for obtaining approved SPE and revised fire scheme approval within four months. This is without prejudice to the rights of the allottees under section 14 who have not consented for revision in building plans.   The amendment in registration certificate shall be issued after compliance of the balance deficiencies.

Land, licence & cost

Land area of the project2.625 acres
Total licensed area2.625 acres
Licence79 of 2018 Dated 17/11/2018
FAR permissible / proposed1.87 / 1.8335
Estimated project cost₹ 101.3 Cr
Cost of land₹ 8.42 Cr
Cost of construction₹ 55 Cr
Infrastructure and other structures₹ 1.31 Cr
EDC, taxes, levies and other costs₹ 36.57 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments2,262.6421.5%
Construction Of Roads2,323.5622%
Pavements5004.7%
Parks And Playgrounds1,162.0311%
Any Other4,300.0640.8%

Apartments 1,005 units · 1 tower

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings116,885.27-1005

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsHSVP/NHAINo
Water SupplyHSVPYes
ElectricityDHBVNYes
Sewage DisposalHSVPYes
Storm Water DrainageHSVPYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 32 lakhSubmitted To Town & Country Planning
Water Supply System₹ 48 lakhSubmitted To Town & Country Planning
Storm Water Drainage₹ 15 lakhSubmitted To Town & Country Planning
Electricity Supply System₹ 42 lakhSubmitted To Town & Country Planning
Sewage Treatment & Garbage Disposal₹ 30 lakhSubmitted To Town & Country Planning
Street Lighting₹ 3 lakhSubmitted To Town & Country Planning
Security And Fire Fighting₹ 10 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 2 lakhSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
License No. 79 Of 2018Already Been Obtained17 Nov 2018

Specifications (as filed)

Flooring Details Of Various Parts Of HouseGranite, Marble, Vitrified Tiles In Common

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about The Leaf?

This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.