Land Area To Be Used For Construction Of Apartments
21,942.117
14.5%
Construction Of Roads
23,965.75
15.8%
Pavements
24,668.938
16.3%
Parks And Playgrounds
54,661.216
36%
Vehicle Parkings
2,549.062
1.7%
Electricity Sub-Station
1,030.542
0.7%
Club House
3,244.157
2.1%
Any Other
19,745.678
13%
External services
Service
Provided by
Approval taken
Roads
GMDA
Yes
Water Supply
GMDA
Yes
Electricity
DHBVNL
Yes
Sewage Disposal
GMDA
No
Storm Water Drainage
GMDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 12 Cr
As Per Project Report
Water Supply System
₹ 9.5 Cr
As Per Project Report
Storm Water Drainage
₹ 20 Cr
As Per Project Report
Electricity Supply System
₹ 56.5 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 5 Cr
As Per Project Report
Street Lighting
₹ 1.5 Cr
As Per Project Report
Security And Fire Fighting
₹ 14 Cr
As Per Project Report
Playgrounds And Parks
₹ 2 Cr
As Per Project Report
Club House/Community Centre
₹ 42 Cr
As Per Project Report
Renewable Energy System
₹ 20 lakh
As Per Project Report
Any Other
₹ 5.5 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
22 Feb 2013
Forest Noc
Already Been Obtained
30 Oct 2013
Airport Authority Of India Noc
Already Been Obtained
1 May 2013
HUDA Construction Water Noc
Already Been Obtained
2 Jul 2013
Environment Clearance
Already Been Obtained
12 Dec 2013
Consent To Establish
Already Been Obtained
18 Feb 2014
Mining Permission
Already Been Obtained
4 Mar 2014
Fire Scheme Approval
Already Been Obtained
27 Nov 2014
Service Estimates And Plans Approvals
Already Been Obtained
9 Dec 2014
Specifications (as filed)
Flooring Details Of Various Parts Of House
Stone/ Wooden/ Tiles
Wall Finishing Details
Paint
Kitchen Details
Modular Kitchen With Hob, Hood, Solid Surface Counter Top, Stainless Steel Sink And Cp Fittings/Vitrifies Tiles/Acrylic Emulsion
Bathroom Fittings
Chinaware, Cp Fittings,
Doors And Windos Frames
Powder-Coated Aluminium Windows & Frames
Lift Details
1 Passanger And 1 Service Lift
Windows/Glazings
Powder-Coated Aluminium Windows With Single Glass
Main Doors
Eco Door (Veneered)
Internal Doors
Eco Door (Laminated)
Cng Pipe Line
Provided
Provision Of Wifi And Broadband Facility
Provided
External Finishing/Colour Scheme
Texture Paint - Grey And Melon Color
Internal Finishing
Acrylic Emulsion
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about The Corridors (Phase 1)?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.