Registration validHRERA Gurugram

Tathastu 35

by Tathastu Realty Pvt Ltd · Village Mohammadpur Gujjar And Sohna, Sector -35, Gurugram

RERA registration
GGM/764/496/2023/108
Registered on
4 Dec 2023
Valid till
23 Mar 2028
Project ID
RERA-GRG-1434-2023
Land area
9.906 acres
Apartments
1,862 in 6 towers
Completion (as filed)
23 Mar 2028
Estimated cost
₹ 450.6 Cr

RERA registration

Registration certificateGGM/764/496/2023/108, dated 4 Dec 2023
Registration valid till23 Mar 2028
Project IDRERA-GRG-1434-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameTathastu 35
PromoterTathastu Realty Pvt Ltd
Promoter’s registered officeHouse No. 48/3-A, Shop No 2, 1ST Floor Blk-C, Lawrance Road, Industrial Area Na Keshavpuram New Delhi- 110035
CINU70109DL2022PTC395151
Site addressVillage Mohammadpur Gujjar And Sohna, Sector -35, Gurugram
SectorSector 35
Tehsil / DistrictSohna / Gurugram
Layout plan approved23 Nov 2023
Building plans approved23 Nov 2023
Construction start (as filed)1 Dec 2023
Completion (as filed)23 Mar 2028
Application submitted27 Oct 2023

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Notice sent to the promoter By Hand
  3. Hearing Examination By Authority View order
    Proceedings

    First hearing

  1. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project.  Sh. Ashwani Kumar(AR) ,Sh. Neeraj Mishra(AR) are present on behalf of promoter. Approved as proposed and the RC shall be issued after compliance of all the conditions and correction in the DPI and A to H. 

  2. Registration granted GGM/764/496/2023/108
  3. Certificate uploaded RC Uploaded
  1. Registration valid till

Land, licence & cost

Land area of the project9.906 acres
Total licensed area9.906 acres
LicenceLICENSE NO. 131 OF 2023 DATED 23.06.2023
FAR permissible / proposed240 / 240
Estimated project cost₹ 450.6 Cr
Cost of land₹ 106.43 Cr
Cost of construction₹ 195.16 Cr
Infrastructure and other structures₹ 22.54 Cr
EDC, taxes, levies and other costs₹ 126.48 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments2.910229.4%
Construction Of Roads2.158621.8%
Parks And Playgrounds1.812618.3%
Vehicle Parkings1.810918.3%
Electricity Sub-Station0.12311.2%
Sewage And Solid Waste Treatment Facility0.21392.2%
Undergroundwatertank0.13931.4%
Streetlighting0.11121.1%
Watersupplysystem0.08650.9%
Stromwaterdrainage0.08650.9%
Electricitysupplysystem0.11121.1%
Securityandfirefighting0.12361.3%
Renewableenergysystem0.08650.9%
Rainwaterharvesting0.11121.1%

Apartments 1,862 units · 6 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings82,066.32-1368
Apartment/Shops/Other Buildings5,527.08-494

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsNANo
Water SupplyHSVPYes
ElectricityDHBVNYes
Sewage DisposalHSVPYes
Storm Water DrainageNo4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)1INTERNAL ROADS AND PAVEMENTS
181.46YET TO BE PREPARED2
Water Supply System125.48YET TO BE PREPARED
3STORM WATER DRAINAGE125.48
Yet To Be Prepared4ELECTRICITY SUPPLY SYSTEM
492.47YET TO BE PREPARED5
Sewage Treatment & Garbage Disposal129.28YET TO BE PREPARED
6STREET LIGHTING51.85
Yet To Be Prepared7SECURITY AND FIRE FIGHTING
438.39YET TO BE PREPARED8
Playgrounds And Parks10.37YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0
Yet To Be Prepared10SHOPPING AREA
0YET TO BE PREPARED11
Renewable Energy System13.97YET TO BE PREPARED
12SCHOOL0
Yet To Be Prepared13HOSPITAL/DISPENSARY
0YET TO BE PREPARED14
Any Other0YET TO BE PREPARED
15ELECTRICAL SUB STATION405.36
Yet To Be Prepared16RAIN WATER HARVESTING
44.58YET TO BE PREPARED17
Stp117.42YET TO BE PREPARED
18UNDERGROUND WATER TANK117.42
Yet To Be Prepared5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.23-11-2023
(date)6. Date of approval of Building Plans23-11-2023
(date)7. New projects:i) Likely date of starting the construction work
01-12-2023ii) Likely date of completing the project23-03-2028
iii) Sizes of the plots to be offered in the projectSr. NoPlot Area(In Square Meter)
Number of plots in the project10
0Total0
iv. Type of apartments to be constructed in the project:TypeCarpet area(In Square Meter)
Number of apartmentsNumber of towersApartment/Shops/Other Buildings
82066.32013686
Apartment/Shops/Other Buildings5527.077494
2(vi) Quarterly schedule of development of whole/remaining part of the project:(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)ParticularsExpenditure
Apartments0Shops
0Plots0
Expenditure to be made in each quarter (In Lakhs)ParticularsYear-2023
Jan-MarApr-JuneJuly-Sep
Oct-DecApartments271.48
Shops0Plots
0Commercial85.04
ParticularsYear-2024Jan-Mar
Apr-JuneJuly-SepOct-Dec
Apartments917.501622.24
892.931013.98Shops
000
0Plots0
000
Commercial234.28321.05
303.70140.57Particulars
Year-2025Jan-MarApr-June
July-SepOct-DecApartments
1782.811806.241618.43
1753.58Shops0
000
Plots00
00Particulars
Year-2026Jan-MarApr-June
July-SepOct-DecApartments
1545.581445.391154.60
913.30Shops0
000
Plots00
00Particulars
Year-2027Jan-MarApr-June
July-SepOct-DecApartments
797.22571.19220.53
Shops00
0Plots0
00(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)ParticularsExpenditure
Roads & Pavements0Water Supply System
0Sewerage treatment & garbage disposal0
Electricity Supply System0Storm Water Drainage
0Parks and Playgrounds0
Clubhouse/community centres0Shopping area
0Other0
Expenditure to be made in each quarter (In Lakhs)ParticularsYear-2023
Jan-MarApr-JuneJuly-Sep
Oct-DecRoads & Pavements0
Water Supply System0Sewerage treatment & garbage disposal
0Electricity Supply System0
Storm Water Drainage0Parks and Playgrounds
0Clubhouse/community centres0
Shopping area0Other
0UGT9.21
Stp9.21Particulars
Year-2024Jan-MarApr-June
July-SepOct-DecRoads & Pavements
000
0Water Supply System0
000
Sewerage treatment & garbage disposal00
00Electricity Supply System
000
0Storm Water Drainage0
000
Parks and Playgrounds00
00Clubhouse/community centres
045.6058.63
0Shopping area0
000
Other00
00UGT
25.3634.7632.88
15.22STP25.36
34.7632.8815.22
ParticularsYear-2026Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements0Water Supply System
26.34Sewerage treatment & garbage disposal0
Electricity Supply System103.36Storm Water Drainage
26.34Parks and Playgrounds0
Clubhouse/community centres0Shopping area
0Other0
ParticularsYear-2027Jan-Mar
Apr-JuneJuly-SepOct-Dec
Roads & Pavements00
79.39102.07Water Supply System
60.4238.730
0Sewerage treatment & garbage disposal0
27.1362.2539.90
Electricity Supply System237.12152.00
00Storm Water Drainage
60.4238.730
0Parks and Playgrounds0
04.545.83
Clubhouse/community centres00
00Shopping area
000
0Other0
000
Rainwater Harvesting00
19.5025.08Street Lighting
22.6829.170
0Security and Firefighting0
191.80246.590
Ess85.08195.17
125.110Renewable Energy System
06.117.86
0It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.Signature of the Applicant / Authorised Representative
Stamp _____________Date _____________FORM REP-I
Part - DAccounts related information:1. Annex copy of the balance sheet of last 3 years
Yes2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No3. Bank account to which the deposits received from apartment buyers will be creditedBank and Branch address
Icici Bank Limited, Groundfloor, World Trade Tower, C-1 Sector 16, Noida, U.p. 201301Bank Account number739005000523
IFSC codeICIC0007390MICR code
110229328Branch code7390

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.81 CrYet To Be Prepared
Water Supply System₹ 1.25 CrYet To Be Prepared
Storm Water Drainage₹ 1.25 CrYet To Be Prepared
Electricity Supply System₹ 4.92 CrYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 1.29 CrYet To Be Prepared
Street Lighting₹ 51.85 lakhYet To Be Prepared
Security And Fire Fighting₹ 4.38 CrYet To Be Prepared
Playgrounds And Parks₹ 10.37 lakhYet To Be Prepared
Renewable Energy System₹ 13.97 lakhYet To Be Prepared
Electrical Sub Station₹ 4.05 CrYet To Be Prepared
Rain Water Harvesting₹ 44.58 lakhYet To Be Prepared
Stp₹ 1.17 CrYet To Be Prepared
Underground Water Tank₹ 1.17 CrYet To Be Prepared

Statutory approvals

ApprovalStatusDate
LicenseAlready Been Obtained23 Jun 2023
Forest NocAlready Been Obtained30 Mar 2023
Sewer Connection AssuranceAlready Been Obtained24 Mar 2023
Construction Water Connection AssuranceAlready Been Obtained24 Mar 2023
Fresh Water Connection AssuranceAlready Been Obtained24 Mar 2023

Specifications (as filed)

Flooring Details Of Various Parts Of HouseBedrooms, Kitchen- Vitrified Tiles ,Toilets, Balcony - Ceramic Tiles ,Staircase - Tile/ Stone
Wall Finishing DetailsExternal Walls - Texture Paints,Internal Walls - Oil Bound Distemper
Kitchen DetailsWalls - Oil Bound Distemper, Flooring -Vitrified Tiles
Bathroom FittingsIsi Marked Standard Washbasin ,Wc
Wood Work EtcMain Door - Flushdoor , Internal Doors -Flushdoor
Doors And Windos FramesMain And Internal Doors- Pressed Steel/Wpc/ Hardwood/ Metal/ Upvc/ Alumin
Glass WorkWindow Shutter - Tinted Glass/Performance Glass
Electric FittingsSwitches - Modular Switch
Conducting And Wiring DetailsConduit - 25MM Heavy And Mediumduty,Wire - 1.5 Mm, 2.5 Mm, 4 Mm
Lift DetailsIsi Marked
External GlazingsPressed Steel/ Wpc/ Hardwood/ Metal/Upvc/ Aluminum
Windows/GlazingsTinted Glass/ Performance Glass
DoorsMain Door - Flushdoor , Internal Doors -Flushdoor , External Door Windows-Pressed Steel/ Wpc/ Hardwood/ Metal/Upvc/ Aluminum
Main DoorsFlushdoor
Internal DoorsFlushdoor
Electrical FittingsSwitches - Modular Switch, Sockets -Modular Sockets, Switch Boards -

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Tathastu 35?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.