Tehsil / District
Gurgaon / Gurugram
Building plans approved
14 Aug 2024
Construction start (as filed)
1 Sep 2024
Completion (as filed)
31 Dec 2031
Application submitted
9 Aug 2024
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Sh. Ajay Pathania (AR), Sh. Atul Mahindroo (AR) and Sh. Dinesh Chahal (AR) are present on behalf of the promoter. Approved as proposed subject to submission of BG/DD of Rs. 25 lakh each in lieu of submission of approved SPE, EC and fire clearance. The requisite rectification in the allotment letter, BBA, A to H Form and DPI shall be made before issuance of RC.
Registration grantedGGM/865/597/2024/92
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
6.95 acres
Total licensed area
6.95 acres
Licence
137 of 2023 Date 05.07.2023
FAR permissible / proposed
3.15 / 3.149
Estimated project cost
₹ 1,259.49 Cr
Cost of land
₹ 25.4 Cr
Cost of construction
₹ 507.65 Cr
Infrastructure and other structures
₹ 104.26 Cr
EDC, taxes, levies and other costs
₹ 622.17 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
0.8291
11.9%
Construction Of Roads
3.143
45.2%
Parks And Playgrounds
1.9031
27.4%
Electricity Sub-Station
0.1606
2.3%
Club House
0.2917
4.2%
Any Other
0.6225
9%
Apartments 458 units · 3 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
145.10
1,562
2
Apartment/Shops/Other Buildings
151.52
1,631
2
Apartment/Shops/Other Buildings
154.02
1,658
40
Apartment/Shops/Other Buildings
147.60
1,589
68
Apartment/Shops/Other Buildings
193.18
2,079
6
Apartment/Shops/Other Buildings
195.33
2,103
24
Apartment/Shops/Other Buildings
200.35
2,157
214
Apartment/Shops/Other Buildings
327.58
3,526
6
Apartment/Shops/Other Buildings
147.30
1,586
24
Apartment/Shops/Other Buildings
20.31
219
72
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
ALREADY CONNECTED
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 20.56 Cr
As Per Project Report
Water Supply System
₹ 7.11 Cr
As Per Project Report
Storm Water Drainage
₹ 2.59 Cr
As Per Project Report
Electricity Supply System
₹ 24.99 Cr
As Per Project Report
Street Lighting
₹ 57.59 lakh
As Per Project Report
Security And Fire Fighting
₹ 1.21 Cr
As Per Project Report
Playgrounds And Parks
₹ 9.32 Cr
As Per Project Report
Club House/Community Centre
₹ 17.41 Cr
As Per Project Report
Shopping Area
₹ 1.86 Cr
As Per Project Report
Renewable Energy System
₹ 60.95 lakh
As Per Project Report
Sewerage System
₹ 2.3 Cr
As Per Project Report
Parking
₹ 7.23 Cr
As Per Project Report
Underground Water Tank
₹ 80.03 lakh
As Per Project Report
Rain Water Harvesting
₹ 45.12 lakh
As Per Project Report
Stp
₹ 1.31 Cr
As Per Project Report
Electrical Sub Station
₹ 5.95 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Water Supply
Already Been Obtained
25 Aug 2023
Sewage Disposal
Already Been Obtained
23 Aug 2023
Storm Water Drainage
Already Been Obtained
23 Aug 2023
Electrical Load
Already Been Obtained
24 Nov 2023
Airport Height Clearance
Already Been Obtained
28 Mar 2023
Forest Noc
Already Been Obtained
15 Nov 2022
Power Line Shifting Noc
Already Been Obtained
10 Nov 2022
HUDA Construction
Already Been Obtained
10 Oct 2023
Building Plan
Already Been Obtained
14 Aug 2024
Specifications (as filed)
Flooring Details Of Various Parts Of House
Tile/Wooden Flooring/Marble
Wall Finishing Details
Acrylic Emulsion Paint
Kitchen Details
Single Lever Counter Top
Bathroom Fittings
Chinaware , Single Lever Counter Top
Wood Work Etc
No
Doors And Windos Frames
Windows - Aluminium Powder-Coated Sections And Flush Door
Glass Work
Windows- Aluminium Powder-Coated Sections
Electric Fittings
Fan And Electric Point
Conducting And Wiring Details
Heavy Duty , Modular
Water Storage
Yes
Lift Details
2 Passenger Lifts Serving Every Apartment
Windows/Glazings
Windows- Aluminium Powder Coated Sections
Doors
Flush Door
Main Doors
Flush Door
Internal Doors
Flush Door
Air Conditioning
Variable Rate Flow System
Electrical Fittings
Heavy Duty Conduting Modular Switches, C Curve Mcb
External Finishing/Colour Scheme
External Grade Texture Paint
Internal Finishing
Acrylic Emulsion Paint
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Tarc Ishva?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.