RERA registration
GGM/510/242/2021/78
Registered on
9 Nov 2021
Valid till
30 Jan 2025
Project ID
RERA-GRG-942-2021
Land area
2.161 acres
Apartments
288 in 22 towers
Plots
72
Completion (as filed)
30 Jan 2025
Estimated cost
₹ 99.51 Cr

RERA registration

Registration certificateGGM/510/242/2021/78, dated 9 Nov 2021
Registration valid till30 Jan 2025
Project IDRERA-GRG-942-2021
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameSuncity Vatsal Valley Independent Floors 1
PromoterNamdev Construction Pvt. Ltd.
Promoter’s registered officeUnit No 214 Suncity Business Tower Sector 54
CINU45201DL2013PTC258094
Site addressGual Pahari
Tehsil / DistrictWazirabad St / Gurugram
Layout plan approved7 May 2021
Building plans approved24 Sep 2021
Construction start (as filed)15 Oct 2021
Completion (as filed)30 Jan 2025
Application submitted1 Oct 2021

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutiny1st deficiency notice sent on 18.10.2021
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Proceedings dated: 09.11.2021 Ms. Prachi Singh, Planning Executive briefed the facts about the project. Sh. Ravi Kant Kumar (Manager Business Development) is present on behalf of the promoter.  The deficiencies conveyed to the promoter vide letter dated 18.10.2021 have been rectified except for a few online corrections in the DPI, REP-I (A to H) and submission of final approval of environment clearance. The AR submitted that the proposal for grant of EC has been approved by SEAC and final approval letter is awaited shortly. Further that the proposal for grant of final approval is fixed before the SEIAA Committee on 15.11.2021 and thus final approval is expected in two months’ time. Keeping in view the above facts, the authority has decided to grant registration certificate for the project with the following condition mentioned above and directed the promoter to comply within three months from issuance of the registration certificate. The promoter is directed to submit the corrected DPI and REP-I (A to H) within 7 days. 

  1. Registration granted GGM/510/242/2021/78
  2. Certificate uploaded RC Approved and Certificate Uploaded
  3. Registration valid till

Land, licence & cost

Land area of the project2.161 acres
Total licensed area9.5 acres
LicenceLicense No 21 of 2021 dated 07.05.2021
FAR permissible / proposed2.64 / 2.424
Estimated project cost₹ 99.51 Cr
Cost of land₹ 38.18 Cr
Cost of construction₹ 48.66 Cr
Infrastructure and other structures₹ 4.28 Cr
EDC, taxes, levies and other costs₹ 8.39 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments8,746.8100%

Apartments 288 units · 22 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings71.5377040
Apartment/Shops/Other Buildings70.6176048
Apartment/Shops/Other Buildings70.6176088
Apartment/Shops/Other Buildings50.0353980
Apartment/Shops/Other Buildings46.4550032

Areas are as filed with HRERA.

Plots 72 plots

Plot size (sq m)Sq ydSq ftPlots
95.281141,0268
104.031241,12020
133.521601,43722
134.331611,44612
135.451621,45810

External services

ServiceProvided byApproval taken
RoadsALREADY CONNECTED ON SECTOR ROADNo
Water SupplyASSURANCE FROM GMDAYes
ElectricityASSURANCE FROM DHVBNYes
Sewage DisposalASSURANCE FROM GMDAYes
Storm Water DrainageRAINWATER HARVESTING PIT PERMISSIONYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 77.25 lakhSubmitted To Town & Country Planning
Water Supply System₹ 69.2 lakhSubmitted To Town & Country Planning
Storm Water Drainage₹ 37 lakhSubmitted To Town & Country Planning
Electricity Supply System₹ 1.44 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 56.65 lakhSubmitted To Town & Country Planning
Street Lighting₹ 16.55 lakhSubmitted To Town & Country Planning
Security And Fire Fighting₹ 1.25 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 10.65 lakhSubmitted To Town & Country Planning
Ugtank₹ 6.8 lakhSubmitted To Town & Country Planning
Rwhpit₹ 8.3 lakhSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
LicenseAlready Been Obtained7 May 2021
Zoning PlanAlready Been Obtained9 Jul 2021
Building PlanAlready Been Obtained24 Sep 2021
Electrical Load Sanction AssuranceAlready Been Obtained22 Mar 2021
Water Supply AssuranceAlready Been Obtained23 Mar 2021
Sewerage Disposal AssuranceAlready Been Obtained15 Mar 2021
Service Estimate ApprovalAlready Been Obtained28 Jul 2021
Forest NocAlready Been Obtained28 Oct 2020
Natural Conservation Zone NocAlready Been Obtained28 Aug 2021
Wildlife NocAlready Been Obtained15 Feb 2021
Environmental Clearance( Approved By Seac & Approval From Seiaa Awaited)

Specifications (as filed)

Flooring Details Of Various Parts Of HouseIps Flooring / Tiles /Wooden Flooring / Imported Marble
Wall Finishing DetailsWhite Wash / Obd
Kitchen DetailsWhite Wash / Obd
Bathroom FittingsEauset
Doors And Windos FramesMs / Al
Glass WorkPlain Glass
Electric FittingsModular Fittings
Conducting And Wiring DetailsPvc Conduits, Frls Wiring
Water StorageOht Water Tanks
Lift DetailsBranded Make
External GlazingsSingle Glass Unit With Clear Glass Upvc/Al Frames And Shutters In Habitable Rooms. Clear/Frosted Glass In Toilets
Windows/GlazingsAluminium
DoorsPre-Laminated Flush Door/Hdhmr Door
Main DoorsPre-Laminated Flush Door/Hdhmr Door
Internal DoorsPre-Laminated Flush Door/Hdhmr Door
Air ConditioningProviding In Living, Dining & Bedrooms
Electrical FittingsModular Fitting
External Finishing/Colour SchemeWeather Shield Paint On External Surfaces, Obd In Stilts.
Internal FinishingPaint /Obd

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Suncity Vatsal Valley Independent Floors 1?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.