HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Registration Certificate Issued.
Application received by HRERA Panchkula
Registration valid till
Land, licence & cost
Land area of the project
7.505 acres
Total licensed area
7.505 acres
Licence
15 of 2019 (11.02.2019)
Estimated project cost
₹ 41 Cr
Cost of land
₹ 19.44 Cr
Infrastructure and other structures
₹ 3.03 Cr
EDC, taxes, levies and other costs
₹ 2.47 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
17,866
58.8%
Construction Of Roads
3,765
12.4%
Pavements
1,750
5.8%
Parks And Playgrounds
2,278
7.5%
Green Belts
109
0.4%
Electricity Sub-Station
37
0.1%
Sewage And Solid Waste Treatment Facility
225
0.7%
Area To Be Left For Transferring To The Government For Community Services
3,037
10%
Commercial
1,215
4%
Milk
28
0.1%
Ug
100
0.3%
Plots 143 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
90.90
109
978
5
94.50
113
1,017
1
98.70
118
1,062
13
99.70
119
1,073
12
99.70
119
1,073
12
99.90
119
1,075
10
99.90
119
1,075
20
99.90
119
1,075
10
108.30
130
1,166
16
113.50
136
1,222
20
124.60
149
1,341
1
129.50
155
1,394
2
130.20
156
1,401
2
130.20
156
1,401
2
134.20
161
1,445
2
141.80
170
1,526
4
144.80
173
1,559
1
149.80
179
1,612
10
External services
Service
Provided by
Approval taken
Roads
HUDA
No
Water Supply
HUDA
No
Electricity
DHBVN
No
Sewage Disposal
HUDA
No
Storm Water Drainage
HUDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 51.83 lakh
Submitted To HUDA
Water Supply System
₹ 44.13 lakh
Submitted To HUDA
Storm Water Drainage
₹ 17.81 lakh
Submitted To HUDA
Electricity Supply System
₹ 1 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 42.8 lakh
Submitted To HUDA
Street Lighting
₹ 4.87 lakh
As Per Project Report
Playgrounds And Parks
₹ 2.06 lakh
Submitted To HUDA
Shopping Area
₹ 4.76 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Layout Plan
Already Been Obtained
15 Jan 2019
Service Plan Estimates
Applied For But Yet To Receive
13 Feb 2019
Ultimate Power Load Requirement
Applied For But Yet To Receive
12 Feb 2019
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Spring Woods City?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.