HearingExamination By AuthorityView order Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefedthe facts of the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma(AR) are present on behalf of the promoter. Although the AR submits that the approval of revised lay out plan has been obtained from DTCP after obtaining objections from the existing allottees in pursuance to the policy dated 25.01.2021 issued by Principal Secretary to Govt. Haryana T&CP; Department. The AR submits that the consent of 2/3rd allottees prior to revision were obtained and shall be submitted in the Authority. Further a list of the changes in the revised plan viz a viz earlier sanctioned plan shall also be submitted duly marked on the plan for inspection of the allottees and one-week public notice shall be issued by the Authority in two newspapers at the cost of the applicant promoter. Deficit fee, if any be also paid before the next date of hearing along with proof of having deposited the deficit fee. The matter to come up on 27.09.2022.
Ar. Neeraj Gautam (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e. Public notice issued and last date of receiving objections is 29.09.2022. The matter is adjourned for 04.10.2022.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Proceedings dated 04.10.2022 : Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed the facts of the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma (AR) are present on behalf of the promoter. Approved as proposed. A condition be incorporated in the registration certificate that in the eventuality of final outcome in the matter decided against the land owners/license holders and/or collaborator in the matter pending in Hon’ble Supreme Court in CA No. 8977 of 2014 titled as Jai Narayan @ Jai Bhagwan & others V/s State of Haryana and final outcome of CBI investigation under process, then the promoter is obligated to refund the amount received from allottees along with interest at the prescribed rate without prejudice to any other remedy including compensation. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram
Registration grantedGGM/617/349/2022/92
Registration valid till
Land, licence & cost
Land area of the project
23.3 acres
Total licensed area
23.3 acres
Licence
68 of 2021 dated 16.09.2021 , 62 of 2022 dated 25.05.2022
FAR permissible / proposed
2.64 / 2.629
Estimated project cost
₹ 986.26 Cr
Cost of land
₹ 287.13 Cr
Cost of construction
₹ 37.55 Cr
Infrastructure and other structures
₹ 547.02 Cr
EDC, taxes, levies and other costs
₹ 114.56 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
13.3913
57.5%
Construction Of Roads
4.7322
20.3%
Parks And Playgrounds
1.7475
7.5%
Area To Be Left For Transferring To The Government For Community Services
2.3301
10%
Area Under Commercial Units
0.9309
4%
Vegetable Booth
0.007
0%
Stp
0.111
0.5%
Transformer
0.001
0%
Under Ground Water Tank
0.049
0.2%
External services
Service
Provided by
Approval taken
Roads
GMDA
Yes
Water Supply
GMDA
Yes
Electricity
DHBVNL
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 11.45 Cr
As Per Project Report
Water Supply System
₹ 5.2 Cr
As Per Project Report
Storm Water Drainage
₹ 2.36 Cr
As Per Project Report
Electricity Supply System
₹ 4.21 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 3.93 Cr
As Per Project Report
Street Lighting
₹ 89.4 lakh
As Per Project Report
Playgrounds And Parks
₹ 38.94 lakh
As Per Project Report
Security
₹ 5.65 lakh
As Per Project Report
Stp Other Than Structural Works
₹ 1.61 Cr
As Per Project Report
Underground Tank Other Than Structural Works
₹ 1.77 Cr
As Per Project Report
Rain Water Harvesting
₹ 1.13 Cr
As Per Project Report
Electrical Sub Station Other Than Structural Works
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Smartworld Orchard?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.