12A Floor, Tower 2 M3M International Financial Center, Sect, Or-66, Gurgaon, Gurugram, Haryana, India, 122002
CIN
U70109HR2020PTC091616
Site address
Sector 113, Village Chauma,Gurugram
Sector
Sector 113
Tehsil / District
Gurgaon / Gurugram
Layout plan approved
26 Apr 2024
Building plans approved
26 Apr 2024
Construction start (as filed)
1 Jul 2024
Completion (as filed)
31 Aug 2031
Application submitted
2 May 2024
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
HearingExamination By AuthorityView order Proceedings
The matter is adjourned and to come up on 24.06.2024
Notice sent to the promoterBy Hand
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) are present on behalf of promoter. The public notice has been issued on 11.06.2024 with respect to the revision in building plans against which no objection has been received in the Authority till 20.06.2024. Approved as proposed subject to submission of BG/DD of Rs. 25 lakhs for obtaining of approved fire scheme within four months and BG in respect of service plans estimates has already been submitted to DTCP, Haryana after technical approval of CE, HSVP. The approved service plans and estimates shall be submitted within three months and a condition to this effect shall be incorporated in the RC.
Registration grantedGGM/842/574/2024/69
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
5.106 acres
Total licensed area
16.113 acres
Licence
106 OF 2022 DATED 05-08-2022 BY DTCP
FAR permissible / proposed
4.79 / 2.44
Estimated project cost
₹ 2,719.84 Cr
Cost of land
₹ 671.34 Cr
Cost of construction
₹ 1,111.36 Cr
Infrastructure and other structures
₹ 97.22 Cr
EDC, taxes, levies and other costs
₹ 839.93 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
1.7064
33.4%
Construction Of Roads
1.4533
28.5%
Parks And Playgrounds
0.825
16.2%
Vehicle Parkings
0.4068
8%
Rainwaterharvesting
0.1069
2.1%
Boundarywall
0.6071
11.9%
Apartments 890 units · 8 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
125,791.00
-
890
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
GMDA
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.62 Cr
As Per Project Report
Water Supply System
₹ 63.6 lakh
As Per Project Report
Storm Water Drainage
₹ 95.4 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 95.4 lakh
As Per Project Report
Street Lighting
₹ 1.01 Cr
As Per Project Report
Security And Fire Fighting
₹ 1.14 Cr
As Per Project Report
Playgrounds And Parks
₹ 1.79 Cr
As Per Project Report
Hardscape And Softscape
₹ 1.34 Cr
As Per Project Report
Boundary Wall
₹ 1.34 Cr
As Per Project Report
Guard House
₹ 50.51 lakh
As Per Project Report
Parking
₹ 6.64 lakh
As Per Project Report
Stp
₹ 2.43 Cr
As Per Project Report
Underground Water Tank
₹ 1.68 Cr
As Per Project Report
Rain Water Harvesting
₹ 46.11 lakh
As Per Project Report
Electrical Sub Station
₹ 23.78 Cr
As Per Project Report
Consultancy
₹ 31.44 Cr
As Per Project Report
Infra Establishments
₹ 22.46 Cr
As Per Project Report
Dewatering
₹ 1.33 Cr
As Per Project Report
Gas Works
₹ 1.29 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License Approval
Already Been Obtained
5 Aug 2022
Specifications (as filed)
Flooring Details Of Various Parts Of House
Bare R.c.c. Slab
Wall Finishing Details
Plaster / White Putty
Doors And Windos Frames
Aluminium Frame
Glass Work
Glass With Aluminium Frame
Electric Fittings
Led Type Fittings In Common Area Only
Conducting And Wiring Details
Pvc/Ms Conduit With Fr / Frls Pvc Wires
Water Storage
Ugt (Fire, Raw & Domastic) = 550 Klrecycled Water = 385 Kloht = 90 Kl
Lift Details
Passenger And Service Lift As Per Vertical Traffic
External Glazings
External FaçAde - Sgu
Main Doors
Aluminium And Glass For Retail
Internal Doors
Aluminium And Glass For Retail / Flus Laminated Doors
Air Conditioning
Provision In Retail & Common Area Non A/C
Electrical Fittings
Led Type Fitting Common Area Only
External Finishing/Colour Scheme
Glass With Stone / Aluminium Cladding
Internal Finishing
Gypsum Plaster & Paint
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Smartworld One Dxp Phase-2?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.